PROJECT_DESCRIPTION.pdf

PDF 184 KB Posted

Attached to
MT PRA GLAC 10(42), GTSR Final Phase Federal contract opportunity
Solicitation number
69056719B000008
Issued by
Department of Transportation Federal Highway Administration

View the file

Other files for this federal contract opportunity

Other files attached to MT PRA GLAC 10(42), GTSR Final Phase, newest first.
File Type Posted
Bid Opening Summary_GTSR Final Phase.pdf PDF
Q&A_11-07-19.pdf PDF
Amendment_A005.pdf PDF
Amendment_A004.pdf PDF
Q&A_11-01-19.pdf PDF
Q&A_10-30-19.pdf PDF
Amendment_A003.pdf PDF
Amendment_A002.pdf PDF
Q&A_10-16-19.pdf PDF
Amendment_A001.pdf PDF
Plans_glac01042.pdf PDF
Plan_Request_form.pdf PDF
IFB_Final_Phase.pdf PDF
Physical_Data_Final_Phase.zip ZIP file
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MT PRA GLAC 10(42), GTSR Final Phase, Flathead and Glacier Counties, MT.

The work consists of Turnouts, Drainage Repairs, Masonry Repairs, Pedestrian Bridge Replacement, and other small items of work.

Project length: 49.1 Miles

Tentative Fixed Completion Date: Fall 2020.

(Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)

Estimated Price Range: $2 million to $3 million

Location: 35 Miles NE of Columbia Falls, MT

DESCRIPTION OF WORK in US CUSTOMARY UNITS

FP-14

On e S ch ed ul e

Sc h

Na m e

_A

DIVISION 150 – Project Requirements 151 MOBILIZATION (yes/no) Yes 152 Construction Survey & Staking (yes/no) Yes 153 Contractor Quality Control

(yes/no) Yes 154 Contractor Testing (yes/no) Yes 155 Construction Schedule (yes/no) Yes DIVISION 200 – Earthwork

203 REMOVAL OF GATE 2 EACH

REMOVAL OF FENCE (LOG RAIL) 528 LNFT

REMOVAL OF MASONRY GUARDWALL (FOOTING) 103 LNFT

REMOVAL OF MASONRY GUARDWALL (AND

SALVAGE) 55 LNFT

REMOVAL OF HANDRAIL 45 LNFT

REMOVAL OF PAVEMENT, ASPHALT 95 SQYD

REMOVAL OF BRIDGE ALL LPSM

204 SELECT BORROW 25 TON

208 DEWATERING (AND BYPASS PUMPING) ALL LPSM

DIVISION 250 – Slope Reinforcement and Retaining Walls

251 BOULDER 30 EACH

ch ed ul e

Sc h

Na m e

_A

REMOVE AND RESET BOULDER 5 EACH

DIVISION 300 – Aggregate and Base Courses

301 AGGREGATE SURFACE COURSE (PATH, 2-

INCH DEPTH, TAN)

30 TON

AGGREGATE SURFACE COURSE (PATH, 2-INCH

DEPTH, RED) 13 TON

302 ROADWAY AGGREGATE, METHOD 2 17 TON

DIVISION 400 – Asphalt Pavements & Surface Treatments

401 ASPHALT CONCRETE PAVEMENT,

GYRATORY MIX, 1/2-INCH OR 3/4-INCH NOMINAL

MAXIMUM SIZE

AGGREGATE, 0.3 TO <3 MILLION ESAL 15 TON

DIVISION 550 – Bridge Construction

552 REPAIR CONCRETE (SUBSTRUCTURE) ALL LPSM

555 STRUCTURAL STEEL (FURNISHED,

FABRICATED, AND ERECTED, DIAPHRAGM AND

BEARING) ALL LPSM

556 BRIDGE RAILING, TIMBER (STEEL CABLE) 521 LNFT

557 STRUCTURAL TIMBER AND LUMBER,

TREATED (PLANK DECK) 5 MFBM

STRUCTURAL TIMBER AND LUMBER, TREATED

(GLULAM BEAM) 9 MFBM

DIVISION 600 – Incidental Construction

605 STANDARD UNDERDRAIN SYSTEM 70 LNFT

607 REPAIRING DRAINAGE STRUCTURE

(JACKSON CREEK CULVERT) ALL LPSM

609 CURB, STONE, TYPE 2, 8-INCH DEPTH 25 LNFT

617 GUARDRAIL SYSTEM SBLG, REMOVABLE

RAIL 110 LNFT

619 FENCE (LOG RAIL) 380 LNFT

GATE, METAL (REMOVABLE) 2 EACH

620 STONE MASONRY (SPILLWAY REPAIR AND

REPOINT) 375 SQYD

STONE MASONRY WALL (UNDERPINNING) 65 SQYD

STONE MASONRY WALL (REPOINT) 175 SQYD

STONE MASONRY WALL (REPAIR) 45 SQYD

622 Rental Equipment (yes/no) Yes ch ed ul e

Sc h

Na m e

_A

623 General Labor (yes/no) Yes

633 SIGNS, ALUMINUM PANELS, TYPE 3

SHEETING 65 SQFT

SNOW POLE HOLDER 5 EACH

635 TEMPORARY TRAFFIC CONTROL,

BARRICADE TYPE 3 22 EACH

TEMPORARY TRAFFIC CONTROL, DRUM 75 EACH

TEMPORARY TRAFFIC CONTROL, WARNING

LIGHT TYPE B 95 EACH

TEMPORARY TRAFFIC CONTROL, PAVEMENT

MARKINGS 110 LNFT

TEMPORARY TRAFFIC CONTROL, CONSTRUCTION

SIGN 350 SQFT

TEMPORARY TRAFFIC CONTROL, TRAFFIC

CONTROL SUPERVISOR 130 DAY

TEMPORARY TRAFFIC CONTROL, FLAGGER 5000 FXHR

646 FIXTURE, HANDRAIL 50 LNFT

ROADSIDE DEVELOPMENT (BUS SHELTER) ALL LPSM

ROADSIDE DEVELOPMENT (JOHNS LAKE

TRAILHEAD) ALL LPSM

DIVISION 200 – Earthwork
DIVISION 250 – Slope Reinforcement and Retaining Walls
DIVISION 300 – Aggregate and Base Courses
DIVISION 400 – Asphalt Pavements & Surface Treatments
DIVISION 550 – Bridge Construction

File details come from the government source that posted it.