This is Addendum #2 to the contract documents for the SUNO Chiller Replacement at Central Plant project located at 6400 Press Drive, New Orleans, Louisiana 70126, issued by Parish Engineering, LLC on November 5, 2025. The addendum modifies the project schedule and mechanical specifications for the chiller replacement work at the central plant facility. Key modifications include extending the project timeline from 200 consecutive calendar days to 300 consecutive calendar days, as stated in the General section referencing Addendum 1 and Pre-Bid Meeting Minutes. The mechanical items section provides detailed revisions to drawing sheets M0.0 and M1.1, requiring the new chiller (CH-3) to include BacNet compatibility and specifying connections to existing chilled and condensing water piping, refrigerant vent piping, and installation of weld-o-let connections with ball valves on the condenser water inlet piping. Additional work includes providing a new coupling for the existing condenser water pump (CP-3(E)), draining and cleaning the existing cooling tower (CT-3(E)), installing a domestic water makeup meter, and coordinating system filling with the owner's water treatment provider.
The specifications section requires coordination of all water treatment activities with the owner's designated water treatment provider, Thornton, Musso, & Bellemin, Inc., with primary contact Jeff LeJeune at 225-938-6522. The addendum establishes these requirements as binding modifications to the original contract documents and specifications section 232113, with all revisions taking precedence over conflicting statements in previously issued contract documents. No pricing information, set-asides, funding sources, or award details are contained in this addendum.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| 50014-0002A-1.pdf | ||
| 50014-0002A.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1450 Seabord Drive
Baton Rouge, LA 70810
P: 225.332.0222 parisheng.com | contact@parisheng.com
Date: November 5, 2025
Project Name: SUNO Chiller Replacement at Central Plant Project Address: 6400 Press Drive, New Orleans, LA 70126 Parish Project No.: 25-039
ADDENDUM # 2
The following items shall be considered part of the Contract Documents for the above referenced project and shall take precedence over any conflicting statements contained therein. Revise all other notes, schedules, details, elevations, and sections as required.
GENERAL:
Addendum 1, Pre-Bid Meeting Minutes, Page 4, Number 4 shall state 300 consecutive calendar days to match contract documents in lieu of 200 consecutive calendar days.
MECHANICAL ITEMS:
Drawings:
1. Sheet Number: M0.0
a. Chiller Schedule
i. Add the following note: Provide Chiller with BacNet compatibility.
2. Sheet Number: M1.1
a. Keynote 1 shall read: Provide new Chiller, CH-3. Connect to existing chilled and condensing water piping. Connect to existing refrigerant vent piping. Provide three (one for each chiller) ¾” weld-o-let with ball valves on Condenser Water inlet piping in vertical below 90 degree fitting above chiller, extend existing water treatment piping to new connection point. Provide domestic water make up meter in existing make up water piping, modify piping as necessary to place meter in accessible location.
b. Keynote 2 shall read: Provide new coupling for existing condenser water pump, CP-3(E). Drain and clean existing Cooling Tower CT-3(E) and fill condenser water system. Coordinate work with Owners Water Treatment Provider.
Addendum – SUNO Chiller Replacement at Central Plant Date: November 5, 2025
Parish Engineering, LLC
1450 Seabord Drive | Baton Rouge, LA 70810 | P: 225.332.0222
Specifications:
1. Section Number: 232113
a. 3.7 Chemical Treatment/E shall read:
Coordinate all water treatment with the Owners Water Treatment Provider:
Thornton, Musso, & Bellemin, Inc. Contact: Jeff LeJeune, Cell 225-938-6522.
If you have any questions, please contact our office.