36L79722Q0012 AMENDMENT 0001.docx

DOCX document 102 KB Posted

Attached to
3695--120/130 WASHER EXTRACTOR Federal contract opportunity
Solicitation number
36L79722Q0012
Issued by
Department of Veterans Affairs

About this file

This document is an amendment to a federal solicitation requesting quotes for a 120/130 pound washer extractor. The Department of Veterans Affairs is seeking to procure and install one washer extractor within 120 days of contract award at its facility in Lake City, Florida. The amendment provides answers to questions from interested vendors to clarify requirements. The washer extractor must be supplied by a Service-Disabled Veteran Owned Small Business and installed no more than 33 days after delivery. The contractor will train staff for two hours on operating and maintaining the new equipment. The award will be made to the responsible bidder that can meet the delivery timeframe and technical specifications for supplying and installing the washer extractor.

View the file

Other files for this federal contract opportunity

Other files attached to 3695--120/130 WASHER EXTRACTOR, newest first.
File Type Posted
36L79722Q0012 AMENDMENT 0002.docx DOCX document
36L79722Q0012 0002.docx DOCX document
36L79722Q0012 0001_1.docx DOCX document
36L79722Q0012_2.docx DOCX document
36L79722Q0012_1.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

06/23/2022

36L797 Department of Veterans Affairs OPAL/National Acquisition Center Building 37 1st Avenue, One Block North of Cermak Hines IL 60141

36L797 Department of Veterans Affairs OPAL/National Acquisition Center Building 37 1st Avenue, One Block North of Cermak Hines IL 60141 To all Offerors/Bidders

36L79722Q0012 06-07-2022

X

Request for Quote (RFQ) 36L79722Q0012 is amended to provide Answers to Questions on pages 2 thru 8 of this amendment as a result of Questions submitted by interested parties.

Linda D. Shirley-Diaz Contract Specialist

RFQ 36L79722Q0012

Amendment #0001

The following are Questions and Answers pertaining to subject RFQ answered by VAMC Lake City

Question 1)

Due to ongoing supply chain disruptions, the delivery timeframe of the requested washer/extractor likely could not be completed within 120 calendar days after the effective date of the contract. Would a delivery modification to 150 calendar days after the effective date of the contract be acceptable?

Answer 1)

The delivery timeframe will remain 120 days after the effective date of the contract.

Question 2)

This solicitation is focused on the replacement of 1-each washer/extractor at the VAMC Lake City project. Based on this summary, does the VAMC classify this as the addition of a workstation or storage area that would require LED lighting modifications? If the relocation or adding of the LED lighting is needed, please provide a based line specification for an acceptable LED lighting fixture and the quantity of these fixtures that are needed.

Answer 2)

The washer extractor will be placed in the same spot and therefore the existing lighting is sufficient, and no new lighting is required.

Question 3)

Please validate the distance and/or location in which the referenced utility services associated with the removed equipment shall be removed back to?

Answer 3)

All utilities are currently established in their existing location.

Question 4)

Since this washer does not require any type of gas service, please validate those modifications to any gas piping is not part of this solicitation?

Answer 4)

There is no gas piping required therefore, at time of award any “gas” reference will be deleted from the Statement of Work.

Question 5)

Please validate if the drain piping referenced is only pertaining to the new washer/extractor specified in this solicitation?

Answer 5)

Yes, the drain piping referenced is only pertaining to the new washer extractor specified in the solicitation.

Question 6)

Please validate if the drain piping referenced is only referring to above grade interior drain piping. If it is referring to below grade drain piping, are there any reports available on the current state and/or integrity of the below grade piping?

Answer 6)

The drain piping referenced is pertaining to all drains for the new washer extractor and no reports are available at this time.

Question 7)

If no reports are available, whose responsibility would it be to perform the necessary scoping activities to validate the integrity of the below grade drain piping?

Answer 7)

The contractor is responsible to perform the necessary scoping activities to validate the integrity of the below grade drain piping.

Question 8)

Due to the size and scope of this solicitation if a staging area is not deemed needed by the awarded contractor is it acceptable to not erect the staging area?

Answer 8)

If there is no storage of any items while the project is ongoing, then it would be acceptable to not erect the staging area.

Question 9)

Please validate the only drain that is directly connected and servicing the new 120# washer/extractor is to be cleaned?

Answer 9)

Only the drain pertaining to the new washer extractor.

Question 10)

With this new washer replacing an existing washer/extractor, please validate if is acceptable to maintain similar spacing around the new equipment as is currently present around the existing equipment? Or will the 36 inch/24 inch minimum clearance be required for the new equipment regardless of the current status quo?

Answer 10)

The minimum clearance shall be required.

Question 11)

Typically, an Uninterrupted Power Supply is not required for washer/extractors. The inclusion of this requirement could significantly increase cost and scope of the project and provide limited operational benefit. Please validate if in this instance an Uninterrupted Power Supply is truly needed to support the washer/extractor requested in this solicitation?

Answer 11)

No, the Uninterrupted Power Supply is not required. At time of award the verbiage will be deleted from the Statement of Work.

Question 12)

Will as built structural drawings of the existing laundry facility be provided to support the structural drawing portion of the installation drawing requirement?

Answer 12)

No, as built structural drawings will not be provided.

Question 13)

In our experience, is not common practice in commercial or government procurements to require Signed and sealed Engineered installation drawings / signed and sealed Engineered As-Built drawings for a solicitation of this relatively modest size and scope. This inclusion of this requirement could significantly increase cost and provide limited operational or risk mitigation benefits. Due to the size and scope of this solicitation, are signed and sealed Engineered installation drawings truly needed to support this project?

Answer 13)

Yes, 45 after contract award the contractor shall provide Installation Design Drawings.

Question 14)

Confirm if it is a requirement to demolish the existing concrete drain trench structure complete, and design and install a new reinforced concrete foundation system flush with the finished floor level capable of supporting the loads imposed by the new washer extractor, or if the VA will perform this work?

Answer 14)

No, it is not a requirement to design and install a new reinforced concrete foundation system.

Question 15)

Confirm if it is a requirement to submit preliminary structural design information with the technical volume that clearly illustrates the proposed foundation system to best enable review by the VA?

Answer 15)

The contractor shall submit this design information pertaining to the size and weight of the new machine and the floor able to support machine.

Question 16)

Confirm new washer is to be installed within the clean production area, same position where the existing washer being traded-in is located next to the non-production drying/conditioning tumbler.

Answer 16)

The new washer is to be installed in the same area where the existing trade-in washer is located.

Question 17)

Confirm the required new hot water, cold water, compressed air, and steam utility connection points shall be to the existing branch lines located within 25-feet below the first floor in the pipe space; and new piping is to be extended up through the floor structure and connected to the new washer extractor.

Answer 17)

The hot water lines are present and within 25-feet above the current machine not below grade in the pipe space so it will not be necessary to extend anything through the floor in order to make connections.

Question 18)

In addition to the required ball valves to be provided at the final utility connection points on the new washer, are new ball-type branch shut-off valves required to be installed at the points of connection to the existing main branch lines located in the pipe space?

Answer 18)

No, new ball-type branch shut-off valves are not required to be installed at the points of connection to the existing main branch lines located in the pipe space.

Question 19)

Confirm if the reference “all drain piping” pertains only to the lateral equipment drain line located in the pipe space connecting the existing Braun trade-in washer drain trench to the main branch line?

Answer 19)

All drain lines only pertain to the existing trade-in washer drain.

Question 20)

Confirm if the requirement to “replace any piping outside to the sewer” is a typo from a previous project?

Answer 20)

The requirement ‘to replace any piping outside to the sewer” is not applicable to this requirement.

Question 21)

Identify, all hazardous materials, if any, which are known to be present in laundry space that will affect the work areas specified (i.e., roofing system, insulation, flooring, interior finishes, etc.)?

Answer 21)

There are no known hazardous materials present that will affect the work or outcome of this project.

Question 22)

Is the contractor responsible for repairing the VTC floor covering where disturbed by the installation work to match adjacent existing floor conditions, or if the VA will perform this work?

Answer 22)

Yes, the Contractor is responsible for returning the area to it’s original condition.

Question 23)

Is PVC/CPVC piping with solvent-welded fittings permitted for exposed, above-grade equipment drains and washer vents ≤ 4” diameter?

Answer 23)

No, PVC/CPVC piping with solvent-welded fittings is not permitted for exposed, above-grade equipment drains and washer vents ≤ 4” diameter.

Question 24)

Is the new washer vent required to be extended direct to the building exterior (i.e., not connected to an existing vent line)?

Answer 24)

The new washer vent is to be extended directly to the building exterior, not connected to any existing vent lines.

Question 25)

Confirm drain cleaning work is limited to the existing branch drain line in the pipe space serving the non-production wash.

Answer 25)

Work is limited only to drain servicing the new washer.

Question 26)

Confirm Para. 2.6 (p.5) specification statement “new electrical for soft-mount washer will originate from electrical panel identified by the station” means the complete installation of new branch circuit from existing electrical sub panel to the new washer includes new conduit, wire, circuit breaker and fused safety disconnect switch?

Answer 26)

A new branch circuit from existing sub panel includes new conduit, wire, circuit breeder and safety disconnect switch.

Question 27)

Confirm if installation work also includes demolishing the existing utilities that served the old washer extractor that was previously removed by the VA.

Answer 27)

Yes, the contractor shall remove all unused utilities that served the old washer extractor that was removed previous to this job and any unused utilities in conjunction with this job.

Question 28)

Upon receipt of award, will the Medical Center provide a valid certificate of exemption for State of Florida sales and use tax to the contractor?

Answer 28)

Yes, the Contracting Officer Representative will provide a valid certificate of exemption for the State of Florida sales and use tax to the Contractor.