36H79718R0011-037.docx
DOCX document 114 KB Posted
- Attached to
- Phoenix Scrub Ex machines Federal contract opportunity
- Solicitation number
- 36H79718R0011
About this file
36H79718R0011 36H79718R0011 copy.docx
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36H79718C0004-000.docx | DOCX document | |
| 36H79718R0011-038.pdf | ||
| 36H79718R0011-039.docx | DOCX document | |
| 36H79718R0011-036.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36H79718R0011
PAGE 1 OF
1. REQUISITION NO.
2. CONTRACT NO.
3. AWARD/EFFECTIVE DATE
4. ORDER NO.
5. SOLICITATION NUMBER
6. SOLICITATION ISSUE DATE
a. NAME
b. TELEPHONE NO. (No Collect Calls)
8. OFFER DUE DATE/LOCAL
TIME
9. ISSUED BY
CODE
10. THIS ACQUISITION IS
UNRESTRICTED OR
SET ASIDE:
% FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
8(A)
NAICS:
SIZE STANDARD:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
RFQ
IFB
RFP
15. DELIVER TO
CODE
16. ADMINISTERED BY
CODE
17a. CONTRACTOR/OFFEROR
CODE
FACILITY CODE
18a. PAYMENT WILL BE MADE BY
CODE
TELEPHONE NO.
DUNS:
DUNS+4:
PHONE:
FAX:
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED
SEE ADDENDUM
19.
20.
21.
22.
23.
24.
ITEM NO.
SCHEDULE OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only) 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________
29. AWARD OF CONTRACT: REF. ___________________________________ OFFER
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
DATED ________________________________. YOUR OFFER ON SOLICITATION
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) 30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
(REV. 2/2012)
PREVIOUS EDITION IS NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.212
7. FOR SOLICITATION
INFORMATION CALL:
STANDARD FORM 1449
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
644-B78031 36H79718R0011 12-04-2017 Patricia Gibson 708-786-4987 12-22-2017 2:00 pm CT Dept. of Veterans Affairs OA&L / National Acquisition Center Building 37 1st Avenue, One Block North of Cermak Hines
IL
60141 X X 333318 1000 Employees N/A X VA Medical Center Laundry Facility Bldg 2 650 East Indian School Road Phoenix
AZ
85012 Department of Veterans Affairs OPAL/ National Acquisition Center Building 37 1st Avenue, One Block North of Cermak Hines
IL
60141
CHIEF, FISCAL DIVISION (901A)
HINES SERVICE AND DISTRIBUTION CENTER
HINES
IL
60141-7005 Scrub Medium Volume Dispenser/Receiver
EA
X X x x x X
VA797H-17-R-0027
12-12-2017 Patricia Gibson
CONTRACTING OFFICER
Table of Contents
| SECTION A | 1 |
| A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS | 1 |
| SECTION B - CONTINUATION OF SF 1449 BLOCKS | 4 |
| B.1 CONTRACT ADMINISTRATION DATA | 4 |
| B.2 SCHEDULE OF SUPPLIES & DELIVERY | 5 |
| B.3 DELIVERY SCHEDULE | 6 |
| B.3 STATEMENT OF WORK | 7 |
| This acquisition covers the acquisition and installation of Six (6) Scrub Medium Volume Dispenser/Receiver Machines within an existing textile care processing facility located at: | 7 |
| B.4 LIST OF DELIVERABLES | 11 |
| SECTION C - CONTRACT CLAUSES | 17 |
| C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL ITEMS (JAN 2017) | 17 |
| C.2 LIMITATIONS ON SUBCONTRACTING-- MONITORING AND COMPLIANCE (JUN 2011) | 23 |
| C.3 52.203-99 PROHIBITION ON CONTRACTING WITH ENTITIES THAT REQUIRE CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS (DEVIATION) (FEB 2015) | 23 |
| C.4 52.227-19 COMMERCIAL COMPUTER SOFTWARE LICENSE (DEC 2007) | 24 |
| C.5 52.237-2 PROTECTION OF GOVERNMENT BUILDINGS, EQUIPMENT, AND VEGETATION (APR 1984) | 25 |
| C.6 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 25 |
| C.7 VAAR 852.211-70 SERVICE DATA MANUALS, MECHANICAL EQUIPMENT (JAN 2008) | 26 |
| C.8 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2012) | 26 |
| C.9 VAAR 852.237-70 CONTRACTOR RESPONSIBILITIES (APR 1984) | 27 |
| C.10 VAAR 852.246-70 GUARANTEE (JAN 2008) | 27 |
| C.11 SUBCONTRACTING COMMITMENTS--MONITORING AND COMPLIANCE (JUN 2011) | 28 |
| C.12 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS—COMMERCIAL ITEMS (JAN 2017) | 28 |
| SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS | 36 |
| SECTION E - SOLICITATION PROVISIONS | 37 |
| E.1 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL ITEMS (JAN 2017) | 37 |
| SUBMITTAL INSTRUCTIONS | 41 |
| E.2 52.212-2 EVALUATION—COMMERCIAL ITEMS (OCT 2014) | 42 |
| E.3 VAAR 852.215-70 SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESS EVALUATION FACTORS (JUL 2016)(DEVIATION) | 44 |
| E.4 52.203-98 PROHIBITION ON CONTRACTING WITH ENTITIES THAT REQUIRE CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS—REPRESENTATION (DEVIATION) (FEB 2015) | 44 |
| E.5 52.209-5 REPRESENTATION BY CORPORATIONS REGARDING AN UNPAID TAX LIABILITY OR A FELONY CONVICTION UNDER ANY FEDERAL LAW (DEVIATION)(MAR 2012) | 45 |
| E.6 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (JUL 2013) | 45 |
| E.7 52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY (APR 1991) | 46 |
| E.8 52.216-1 TYPE OF CONTRACT (APR 1984) | 46 |
| E.9 52.232-38 SUBMISSION OF ELECTRONIC FUNDS TRANSFER INFORMATION WITH OFFER (JUL 2013) | 47 |
| E.10 52.233-2 SERVICE OF PROTEST (SEP 2006) | 47 |
| E.11 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (JAN 2008) | 48 |
| E.12 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (JAN 2008) | 48 |
| E.13 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (JAN 1998) | 48 |
| E.14 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008) | 49 |
| E.15 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—COMMERCIAL ITEMS (JAN 2017) | 49 |
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA
(continuation from Standard Form 1449, block 18A.)
1. Contract Administration: All contract administration matters will be handled by the following individuals:
a. CONTRACTOR:
b. GOVERNMENT: Contracting Officer Patricia Gibson Dept. of Veterans Affairs OA&L / National Acquisition Center Building 37 1st Avenue, One Block North of Cermak Hines IL 60141
2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:
| [] |
| 52.232-33, Payment by Electronic Funds Transfer—System For Award Management, or |
| [] |
| 52.232-36, Payment by Third Party |
3. INVOICES: Invoices shall be submitted in arrears:
| a. Quarterly | [] |
| b. Semi-Annually | [] |
| c. Other | [x] Interim Payments 80% of the equipment price upon delivery; |
4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests.
CHIEF, FISCAL DIVISION (901A)
HINES SERVICE AND DISTRIBUTION CENTER
HINES IL 60141-7005
ACKNOWLEDGMENT OF AMENDMENTS: The offeror acknowledges receipt of amendments to the Solicitation numbered and dated as follows:
| AMENDMENT NO |
| DATE |
B.2 SCHEDULE OF SUPPLIES & DELIVERY
This will be a single award contract. Offerors are requested to provide an offer on the line item listed below in accordance with the attached Technical/ Performance Specifications. The line item must be delivered within 60 days after receipt of award. Installation of the equipment shall be within 15 days after delivery of equipment. The item must be installed in accordance with the attached Technical/Performance Specifications. Final price should include the cost of each item and installation costs.
EQUIPMENT
ITEM # 1
Scrub Medium Volume Dispenser/Receiver
Furnish and install six (6) each medium volume scrub dispenser/receiver machines with control unit.
Qty: 1 each Unit Price$ ______________ each Total for each $____________
Equipment Trade-in No Trade in Installation: $_____________ Other (Identify) (Include all material and labor necessary for the installation of equipment and any modifications necessary for its connection and proper operation, in offered price for installation) Total Installed Price (Total price of equipment and installation): $______________
SHIP TO:
Carl T. Hayden VA Medical Center Environmental Management Service 650 East Indian School Road Laundry Facility Bldg. # 2 Phoenix, AZ 85012
B.3 DELIVERY SCHEDULE
EVENT
DELIVERY TIME
Equipment Delivery
60 days after award
Installation
15 days after equipment delivery
B.3 STATEMENT OF WORK
This acquisition covers the acquisition and installation of Six (6) Scrub Medium Volume Dispenser/Receiver Machines within an existing textile care processing facility located at:
Department of Veterans Affairs VA Medical Center 650 East Indian School Road Laundry Facility Building 2 Phoenix, AZ 85012
GENERAL EQUIPMENT REQUIREMENTS:
Contractor shall provide all labor, material, tools, parts, equipment, operating and/or Technical/maintenance manuals, training, delivery, and accessories necessary to furnish and install the ScrubEx Dispensing equipment as defined herein.
1. Specifications of component equipment as set forth in this section are minimum specifications, unless otherwise stated, and shall not be construed as limiting the overall quality, quantity or performance characteristics of items furnished in the system. The new offered equipment shall meet or exceed the minimum requirements. The contractor shall be held responsible for the supply, performance and overall quality of the furnished equipment.
2. All equipment shall be supplied under this specification shall be new and the current model.
INSTALLATION:
It is agreed upon and understood that the contractor shall be responsible for installation. Installation to be completed by the contractor shall take place during normal working hours as stated unless otherwise agreed upon with the COR. Installation work shall be scheduled with the COR who will be responsible to coordinate the work described herein. If site prep is required to include mounting of Brackets along with Electrical and Internet connections will be supplied by the VA, this work will be coordinated between the contractor and the COR.
TESTING AND CERTIFICATION:
Upon completing installation of the system, the Contractor shall notify the COR that the system is ready for testing, and that it meets all requirements as specified.
| ACCEPTANCE TESTING: |
| The system shall be tested, in the presence of the COR for proof-of-performance. Acceptance Testing shall be performed at a mutually agreed upon date and time. |
TRAINING:
Contractor shall provide training on the use and operations of the equipment. Cost for training is included in the contract price and shall be conducted at the facility at the discretion of the COR. Training shall include on-site orientation and training of using personnel in operation and care of the equipment furnished, as well as an actual demonstration of the operation of the equipment. Contractor shall provide guidance on completing any adjustments or other actions which may be undertaken by operating personnel in the event of failure of equipment, provided that such adjustment or action will in no way jeopardize the Government's rights under contract guarantee clause. Only qualified Contractor’s personnel will give this training.
HOURS OF OPERATION:
| 1. | Normal hours of operations at the VAMC are Monday through Friday from 8:00 am to 4:30 pm, excluding holidays. All work will be performed during normal hours of coverage unless requested or approved by COR or his designee. |
| Special Notes: The VA will have access to a technical support hotline at (888) 200-4797 during the hours of 8am – 5pm. Cost for same is included in the contract price. If however, a problem or malfunction of the equipment cannot be resolved with technical support via telephone, then the Contractor shall be responsible to meet the response times. |
GUARANTEE/WARRANTY:
The Contractor warrants that the system will be free from defects from materials and workmanship under normal use for a period of not less than one (1) year for equipment defined herein. Contractor will replace or repair equipment if necessary to the satisfaction of the Government. Contractor shall provide a copy of the written warranty upon delivery of the equipment.
SERVICE
1. Service during the guarantee period (per VAAR 852.246-70) shall be provided within 24 hours of notice from the Contracting Officer or COR. A service request will be issued upon any failure which degrades system performance, whether it prevents systems operation and disrupts continued operation or not, requires service within 24 hours. Telephone response does not satisfy this requirement.
(b) Prior to and during the guarantee period, service at other than normal working hours (6:30 AM - 5:00 PM, excluding weekends and holidays), if at the request of the hospital, will be charged at an hourly rate which is the difference between current regular rate and overtime rate. Otherwise, all services shall be performed at no charge to the Government during this period.
CONFORMANCE STANDARDS:
All work shall be performed and equipment shall function in conformance with all VA safety standards, manufacturer's/industry standards, the latest published edition of NFPA99, FDA, OSHA, JCAHO, ISO 9000, UL and other applicable state, local, national and industry standards. Equipment shall meet EMS (Electromagnetic Compatibility) for EIC 601-1-2 CE, CSA, ETL Approved to U.L. 2601-1, second edition.
PRODUCT MODIFICATION, REMOVAL OR RECALL:
If any product awarded under this solicitation requires modification, is removed or recalled by the Contractor or manufacturer, or if any required modification, removal or recall is suggested or mandated by a regulatory or official agency, the following steps will immediately be taken by the Contractor or manufacturer:
a. Notify the Contracting Officer, in writing, by the most expeditious manner possible. Provide two copies of the notification which shall include, but not be limited to the following:
(1) Complete item description and/or identification, order numbers from customers and the contract number assigned as a result of an award on this solicitation.
(2) Reasons for modifications, removal or recall.
(3) Necessary instructions for return for credit, replacement or corrective action.
| b. | Provide the above information to all agencies and VA Facilities who purchased the product. The Contracting Officer shall be provided a copy of the notification in b. above, and a list of all agencies and/or VA facilities notified |
| c. | Contractor shall be responsible for any costs associated with the above. |
OPERATING/MAINTENANCE MANUALS:
In addition to the electronic copy of the operating/maintenance manual (if available), Contractor shall provide two (2) hard copies (written, spiral bound or ring binder) of the Operating and /or Maintenance manuals.
PERSONS AUTHORIZED TO MAKE CONTRACT CHANGES
The Contracting Officer is the ONLY individual authorized to approve any change in the contract which shall result in an increase or decrease of the contract price or which shall in any way change the terms or conditions of the contract.
TIME OF DELIVERY-INSTALLATION TIMEFRAME
a. Delivery of new equipment shall be made within 90 calendar days after award. The required delivery date will be annotated on the contract. Delivery dates specified may be adjusted by the contracting officer to coincide with the date the hospital will be ready to receive installation. The contracting officer shall advise the contractor of the new delivery date at least 45 days prior to the original or adjusted delivery dates.
b. All equipment must be installed within 30 days after delivery. The Phoenix, AZ laundry facility will not be closed for installation of the new equipment. The total period of performance is not to exceed 120 calendar days from notice of award to complete installation.
c. Truck Delivery:
Truck delivery is accepted 8:00 a.m. to 2:30 p.m., local time, Monday through Friday, excluding Federal holidays.
AVAILABILITY OF PARTS AND SERVICE
The contractor guarantees availability of servicing and replacement parts for a period of ten (10) years.
SERVICE BULLETINS (MAY 1995)
Two (2) copies of each service bulletin affecting safety or maintenance of equipment furnished under this contract will be forwarded to the receiving activity for a period of ten (10) years after date of delivery. In addition one copy will be furnished to each of the following:
| Frank Zacchigna, Chief, HTME Contracts Division |
| Frank.Zacchigna@va.gov |
| Steven Parrish, Program Manager, Textile Care |
| Steven.Parrish@va.gov |
GUARANTEED OPERATIONAL UPTIME
Unit must be operable and available for use 95% of the normal operational time. Operational time is considered 0600 to 1530. Repairs are to be made during normal work hours. Downtime will be computed from notification during normal work hours. Scheduled maintenance will be excluded from downtime. Normal work hours are 6:00 to 9:30, Monday through Friday, excluding national holidays. Failure to meet this requirement during any calendar month period will be cause for an extension of the guarantee by twice the down time. Failure to meet this requirement for three consecutive months will be grounds for default action.
Refusal of access to the equipment indicates that the unit is up and running and time will not be considered when determining downtime. Refusal of access to the equipment voids the service request.
36H79718R0011
Page 1 of Page 1 of
B.4 LIST OF DELIVERABLES
A. Provided Within 45 Days After Award The contractor is responsible for visiting the site of installation, surveying power and other utility requirements, room dimensions and other physical characteristics of the room necessary for proper room layout.
DRAWING AND ROOM PREPARATION INSTRUCTIONS
| 1. | Contractor bears all responsibility for all new utility connections. These documents shall fully define and illustrate all proposed changes to (e.g., loads, designated/rated operation of all computer equipment, etc.); utility connections, chases and conduits to include communications and other changes to the characteristics of the existing physical building necessary for the contractor to install a fully operational system. Offeror shall make maximum use of existing structures (i.e., wall/ceiling mounts, junction boxes, raceways and conduits) in preparation of drawings. Power line recommendations shall conform to NEMA Standard XR2-2000. |
| 2. | If the physical structure must be modified to permit transport of the equipment to the installation site, the offeror shall be fully responsible for the modifications. |
| 3. | The contractor shall identify a responsible and knowledgeable representative to explain the drawings and make any necessary changes. |
B. Provided at the Time of Equipment Delivery:
1. The contractor shall supply two operation/service (maintenance) manuals and 2 CD copies with each piece of equipment. As a minimum, the manual shall be bound and identical to the manual provided to the manufacturer's designated field service representative as well as comply with all the requirements in paragraphs (b) through (i) of this section. Sections, headings and section sequence identified in (b) through (i) of this clause are typical and may vary between manufacturers. Variances in the sections, headings and section sequence, however, do not relieve the manufacturer of his/her responsibility in supplying the technical data called for therein.
a. Title Page and Front Matter. The title page shall include the equipment nomenclature, model number, effective date of the manual and the manufacturer's name and address. If the manual applies to a particular version of the equipment only, the title page shall also list that equipment's serial number. Front matter shall consist of the Table of Contents, List of Tables, List of Illustrations and a frontispiece (photograph or line drawing) depicting the equipment.
b. Section I, General Description. This section shall provide a generalized description of the equipment or devices and shall describe its purpose or intended use. Included in this section will be a table listing all pertinent equipment specifications, power requirements, environmental limitations and physical dimensions.
c. Section II, Installation. Section II shall provide pertinent installation information. It shall list all input and output connectors using applicable reference designators and functional names as they appear on the equipment. Included in this listing will be a brief description of the function of each connector along with the connector type. Instructions shall be provided as to the recommended method of repacking the equipment for shipment (packing material, labeling, etc.)
d. Section III, Operation. Section III shall fully describe the operation of the equipment and shall include a listing of each control with a brief description of its function and step-by-step procedures for each operating mode. Procedures shall use the control nomenclature as it appears on the equipment and shall be keyed to one or more illustrations of the equipment. Operating procedures shall include any preoperational checks, calibration adjustments and operation tests. Notes, cautions and warnings shall be set off from the text body so they may easily be recognizable and will draw the attention of the reader. Illustrations should be used wherever possible depicting equipment connections for test, calibration, monitoring and measurements. For large, complex and/or highly versatile equipment capable of many operating modes and in other instances where the Operation Section is quite large, operational information may be bound separately in the form of an Operators Manual. The providing of a separate Operators manual does not relieve the supplier of his responsibility for providing the minimum acceptable maintenance data specified herein.
Where applicable, flow charts and narrative descriptions of software shall be provided. If programming is either built-in and/or user modifiable, a complete software listing shall be supplied. Equipment items with software packages shall also include diagnostic routines and sample outputs. Submission information shall be given in the Maintenance Section to identify equipment malfunctions which are software related.
e. Section IV, Principles of Operation. This section shall describe in narrative form the principles of operation of the equipment. Circuitry shall be discussed in sufficient detail to be understood by technicians and engineers who possess a working knowledge of electronics and a general familiarity with the overall application of the devices. The circuit descriptions should start at the overall equipment level and proceed to more detailed circuit descriptions. The overall description shall be keyed to a functional block diagram of the equipment. Circuit descriptions shall be keyed to schematic diagrams discussed in paragraph (i) below. It is recommended that for complex or special circuits, simplified schematics should be included in this section.
f. Section V, Maintenance. The maintenance section shall contain a list of recommended test equipment, special tools, preventive maintenance instructions, including calibration procedures and tools, and corrective information. The list of test equipment shall be that recommended by the manufacturer and shall be designated by manufacturer and model number. Special tools are those items not commercially available or those that are designed specifically for the equipment being supplied. Sufficient data shall be provided to enable their purchase by VA. Preventive maintenance instructions shall consist of those recommended by the manufacturer to preclude unnecessary failures. Procedures and the recommended frequency of performance shall be included for visual inspection, cleaning, lubricating, mechanical adjustments and circuit calibration. Corrective maintenance shall consist of the data necessary to troubleshoot and rectify a problem and shall include procedures for realigning and testing the equipment. Troubleshooting shall include either a list of test points with the applicable voltage levels or waveforms that would be present under a certain prescribed set of conditions, a troubleshooting chart listing the symptom, probable cause and remedy, or a narrative containing sufficient data to enable a test technician or electronics engineer to determine and locate the probable cause of malfunction. Where applicable, program information shall be provided/backup discs provided so that equipment programming can be reprogrammed or reloaded as needed. Data shall also be provided describing the preferred method of repairing or replacing discrete components mounted on printed circuit boards or located in areas where special steps must be followed to disassemble the equipment. Procedures shall be included to realign and test the equipment at the completion of repairs and to restore it to its original operating condition. These procedures shall be supported by the necessary waveforms and voltage levels, and data for selecting matched components. Diagrams, either photographic or line, shall show the location of printed circuit board mounted components.
g. Section VI, Replacement Parts List. The replacement parts list shall list, in alphanumeric order, all electrical/electronic, mechanical and pneumatic components, their description, value and tolerance, true manufacturer and manufacturers' part number.
h. Section VII, Drawings. All wiring and schematic diagrams shall be included. The drawings shall depict the circuitry using standard symbols and shall include the reference designations and component values or type designators. Drawings shall be clear and legible and shall not be engineering or production’s sketches.
C. Provided at the Time of Installation:
1. The contractor shall submit a listing of consumables used by the equipment by part number and quantity to the COR after installation.
2. The contractor shall submit a list of the training materials and training video’s to be provided to the COR prior to commencement of training.
1. Provided at the Time of the Initial Inspection:
1. The contractor shall include two (2) copies of the equipment manufacturer’s written procedures for lock-out and tag-out and Permit Required Confined Space (PRCS) requirements for all industrial equipment offered. As a minimum, the procedures shall be bound in a book/binder for the manager’s use in training maintenance employees.
1. The contractor shall supply a lockable lock-out/tag-out cabinet with devices for each piece of equipment offered. All lock-out / tag-out and locations shall be marked and identified on the machine with instructions on lock-out procedures for the equipment offered. These instructions/procedures shall be permanently mounted on each piece of equipment. Lock-out / tag-out procedures include all sources of stored energy, including but not limited to: electrical, gas, water, steam, air, hydraulic etc. Relief valves shall be installed for lock-out / tag-out locations to relieve residual air etc.
1. Number and nomenclature will separately identify all equipment with no less than 2-inch numbers and letters. Each piece of equipment will be separately identified. Example: Dryer Number 1; Dryer Number 2. The equipment offered shall be made compatible to meet production requirements specified in performance specifications. Connections to VA supplied utilities shall be successful offeror’s responsibility. Penetrations in floors, walls and ceilings not utilized will be filled with existing floor; wall and ceiling like material. All braces, pipes, conduit and duct work that will not be reutilized shall be removed back to the source.
1. Technical certificates of compliance (applicable to the item of equipment furnished) shall be submitted at the time and place of inspection.
Note: As applicable, the textile care processing system will be performance tested in accordance with the referenced specifications, codes, standards and VA performance/production testing requirements specified in "Technical Specifications". Performance and production testing will be conducted by VA after installation and a contractor’s 30 workday shakedown of the equipment is completed. The shakedown occurs after all equipment has been installed. At this time, the contractor ensures the facility staff understands the operations of the equipment and that it is running properly. This occurs within 30 days of equipment installation. Inspection will be conducted by VA after installation and shakedown is completed.
1. The contractor shall submit a list of preventive maintenance for the system offered which shall be performed during the guarantee period. The contractor shall describe the frequency and duration of downtime required for scheduled preventive maintenance to the COR after installation.
1. The contractor shall supply the VA site personnel with a list of recommended spare parts for each and every piece of equipment plus expendables for one (1) month’s operation at acceptance.
Page 1 of Page 1 of
SECTION C - CONTRACT CLAUSES
C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL ITEMS (JAN 2017)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights—
(1) Within a reasonable time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(g) Invoice.
(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include—
(i) Name and address of the Contractor;
(ii) Invoice date and number;
(iii) Contract number, line item number and, if applicable, the order number;
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(vi) Terms of any discount for prompt payment offered;
(vii) Name and address of official to whom payment is to be sent;
(viii) Name, title, and phone number of person to notify in event of defective invoice; and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer—Other Than System for Award Management), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payment.—
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.
(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.
(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(6) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if—
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in 32.608-2 of the Federal Acquisition Regulation in effect on the date of this contract.
(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.
(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.
(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.
(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.
(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.
(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 41 U.S.C. 4712 and 10 U.S.C. 2409 relating to whistleblower protections; 49 U.S.C. 40118, Fly American; and 41 U.S.C. chapter 21 relating to procurement integrity.
(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:
(1) The schedule of supplies/services.
(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;
(3) The clause at 52.212-5.
(4) Addenda to this solicitation or contract, including any license agreements for computer software.
(5) Solicitation provisions if this is a solicitation.
(6) Other paragraphs of this clause.
(7) The Standard Form 1449.
(8) Other documents, exhibits, and attachments
(9) The specification.
(t) System for Award Management (SAM).
(1) Unless exempted by an addendum to this contract, the Contractor is responsible during performance and through final payment of any contract for the accuracy and completeness of the data within the SAM database, and for any liability resulting from the Government's reliance on inaccurate or incomplete data. To remain registered in the SAM database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the SAM database to ensure it is current, accurate and complete. Updating information in the SAM does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.
(2)(i) If a Contractor has legally changed its business name, "doing business as" name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in FAR subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day's written notification of its intention to (A) change the name in the SAM database; (B) comply with the requirements of subpart 42.12; and (C) agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.
(ii) If the Contractor fails to comply with the requirements of paragraph (t)(2)(i) of this clause, or fails to perform the agreement at paragraph (t)(2)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the SAM information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the "Suspension of Payment" paragraph of the electronic funds transfer (EFT) clause of this contract.
(3) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the SAM record to reflect an assignee for the purpose of assignment of claims (see Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the SAM database. Information provided to the Contractor's SAM record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the "Suspension of payment" paragraph of the EFT clause of this contract.
(4) Offerors and Contractors may obtain information on registration and annual confirmation requirements via SAM accessed through https://www.acquisition.gov.
(u) Unauthorized Obligations.
(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:
(i) Any such clause is unenforceable against the Government.
(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an “I agree” click box or other comparable mechanism (e.g., “click-wrap” or “browse-wrap” agreements), execution does not bind the Government or any Government authorized end user to such clause.
(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.
(2) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.
(v) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
(End of Clause)
C.2 LIMITATIONS ON SUBCONTRACTING-- MONITORING AND COMPLIANCE (JUN 2011)
This solicitation includes FAR 52.219-14 Limitations on Subcontracting. Accordingly, any contract resulting from this solicitation will include this clause. The contractor is advised in performing contract administration functions, the CO may use the services of a support contractor(s) retained by VA to assist in assessing the contractor's compliance with the limitations on subcontracting or percentage of work performance requirements specified in the clause. To that end, the support contractor(s) may require access to contractor's offices where the contractor's business records or other proprietary data are retained and to review such business records regarding the contractor's compliance with this requirement. All support contractors conducting this review on behalf of VA will be required to sign an “Information Protection and Non-Disclosure and Disclosure of Conflicts of Interest Agreement” to ensure the contractor's business records or other proprietary data reviewed or obtained in the course of assisting the CO in assessing the contractor for compliance are protected to ensure information or data is not improperly disclosed or other impropriety occurs. Furthermore, if VA determines any services the support contractor(s) will perform in assessing compliance are advisory and assistance services as defined in FAR 2.101, Definitions, the support contractor(s) must also enter into an agreement with the contractor to protect proprietary information as required by FAR 9.505-4, obtaining access to proprietary information, paragraph (b). The contractor is required to cooperate fully and make available any records as may be required to enable the CO to assess the contractor's compliance with the limitations on subcontracting or percentage of work performance requirement.
C.3 52.203-99 PROHIBITION ON CONTRACTING WITH ENTITIES THAT REQUIRE CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS (DEVIATION) (FEB 2015)
(a) The Contractor shall not require employees or contractors seeking to report fraud, waste, or abuse to sign or comply with internal confidentiality agreements or statements prohibiting or otherwise restricting such employees or subcontractors from lawfully reporting such waste, fraud, or abuse to a designated investigative or law enforcement representative of a Federal department or agency authorized to receive such information.
(b) The contractor shall notify employees that the prohibitions and restrictions of any internal confidentiality agreements covered by this clause are no longer in effect.
(c) The prohibition in paragraph (a) of this clause does not contravene requirements applicable to Standard Form 312, Form 4414, or any other form issued by a Federal department or agency governing the nondisclosure of classified information.
(d)(1) In accordance with section 743 of Division E, Title VII, of the Consolidated and Further Continuing Resolution Appropriations Act, 2015…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.