This notice describes a federal construction project solicitation for the modernization of five elevators at the Iowa City VA Medical Center. The project scope includes replacing or modifying elevator controllers, machines, cables, stations, phones, and finishes. The solicitation will be a Request for Proposal conducted according to FAR Parts 15, 19, and 36. It will be a total Service-Disabled Veteran-Owned Small Business set-aside with NAICS code 238210 and a size standard of $16.5 million. The Department of Veterans Affairs will issue the solicitation in late 2019 seeking a firm-fixed-price contract for a period of performance of approximately 323 days. The project magnitude is estimated between $2 million and $5 million.

36E77620R0006 36E77620R0006_1.docx

View the file

Other files for this federal contract opportunity

Other files attached to VISN 23 Project 636A8-17-001 "Modernize A Bank Elevators", newest first.
File Type Posted
36E77620R0006-0004000.docx DOCX document
36E77620R0006-0003001.doc DOC document
36E77620R0006-0003000.docx DOCX document
36E77620R0006-0003002.pdf PDF
36E77620R0006-0002001.pdf PDF
36E77620R0006-0002003.pdf PDF
36E77620R0006-0002000.docx DOCX document
36E77620R0006-0002004.docx DOCX document
36E77620R0006-0002002.pdf PDF
36E77620R0006-0002005.pdf PDF
36E77620R0006-0001000.docx DOCX document
36E77620R0006-008.docx DOCX document
36E77620R0006-002.docx DOCX document
36E77620R0006-003.pdf PDF
36E77620R0006-006.pdf PDF
36E77620R0006-009.docx DOCX document
36E77620R0006-004.pdf PDF
36E77620R0006-007.docx DOCX document
36E77620R0006-005.pdf PDF
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36E77620R0006

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36E77620R0006 X 11-27-2019 636A8-17-001

PCAC

Department of Veterans Affairs Program Contracting Activity Central 6150 Oak Tree Blvd, Suite 300 Independence OH 44131 Department of Veterans Affairs Program Contracting Activity Central 6150 Oak Tree Blvd, Suite 300 Independence OH 44131 William Henkel 216-447-8300 x49630 In accordance with 38 U.S.C. § 8127 (Public Law 109-461), this project is a competitive Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside.

The contractor shall provide all labor, equipment, materials and supervision necessary to perform all work required for the "Modernize A Bank Elevator" construction project, in accordance with the solicitation and the attached specifications, drawings and other documents.

The project is located at:

Iowa City VA Health Care System 601 Highway 6 W Iowa City, IA 50310

The period of performance is 323 days from the issuance of the Notice to Proceeed (NTP).

The VAAR Magnitude of Construction is between $2,000,000 and $5,000,000.

X X 52.211-10 X 10 (Ten)

4:30 PM EST

01-07-2020 X 90 (Ninety)

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

PCAC

Department of Veterans Affairs Program Contracting Activity Central 6150 Oak Tree Blvd, Suite 300 Independence OH 44131

VAFSC

Department of Veterans Affairs Financial Services Center Invoices to be Submitted Electronically www.ob10.com/us/en/veterans-affairs/ e-Invoice Setup Info Phone 877-489-6135 877-353-9791 512-460-5429

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS5
1.1 PROPOSAL MATERIAL:5
1.2 BID GUARANTEE:5
1.3 PAYMENT & PERFORMANCE BONDS:5
1.4 DESCRIPTION OF WORK:5
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS6
2.1 AVAILABILITY OF SOLICITATION DOCUMENTS:6
2.2 REQUEST FOR PROPOSAL:6
2.3 SDVOSB SET-ASIDE:6
2.4 TECHNICAL QUESTIONS:6
2.5 AMENDMENTS:6
2.6 PREPARATION OF PROPOSALS:6
2.7 PROPOSAL REQUIREMENTS:6
2.8 DETERMINATION OF RESPONSIBILITY:13
2.9 VETS 4212:13
2.10 SYSTEM FOR AWARD MANAGEMENT (SAM):13
2.11 BACKGROUND INVESTIGATIONS AND SPECIAL AGREEMENT CHECKS:13
2.12 REVIEW REQUIRED REGISTRATION WITH CONTRACTOR PERFORMANCE ASSESSMENT SYSTEM (CPARS):13
2.13 REFERENCES TO VA ENGINEER, RESIDENT ENGINEER OR PROJECT MANAGER:14
2.14 52.216-1 TYPE OF CONTRACT (APR 1984)14
2.15 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)14
2.16 52.223-20 AEROSOLS (JUN 2016)14
2.17 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)15
2.18 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)16
2.19 52.233-2 SERVICE OF PROTEST (SEP 2006)17
2.20 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)18
2.21 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)18
2.22 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)18
2.23 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)19
2.24 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)19
REPRESENTATIONS AND CERTIFICATIONS21
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (OCT 2018)21
3.2 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)24
3.3 52.209-13 VIOLATION OF ARMS CONTROLS TREATIES OR AGREEMENTS—CERTIFICATION (JUN 2018)26
GENERAL CONDITIONS28
4.1 52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011)28
4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)28
4.3 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013)28
4.4 52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA-DESIGNATED ITEMS (MAY 2008)30
4.5 52.223-21 FOAMS (JUN 2016)30
4.6 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)31
4.7 SUPPLEMENTAL INSURANCE REQUIREMENTS34
4.8 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997) ALTERNATE II (APR 1984)34
4.9 52.244-2 SUBCONTRACTS (OCT 2010)36
4.10 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)38
4.11 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)41
4.12 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION)41
4.13 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018)43
4.14 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)44
4.15 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)44
4.16 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)47
4.17 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)48
4.18 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)48
4.19 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)49
4.20 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (APR 2019)49
4.21 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)50
4.22 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)51

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

1.1 PROPOSAL MATERIAL:

Proposal materials consisting of drawings, specifications, and contract forms are included and/or attached as part of this Request For Proposal. The VA will not provide printed copies of drawings or specifications. It is the responsibility of the offeror to obtain the proposal materials in a time and manner sufficient to respond to this solicitation by the specified due date.

1.2 BID GUARANTEE:

A Bid Guarantee, SF 24, is required and shall be 20% or a maximum of 3,000,000.00. Failure to furnish the required bid (proposal) guarantee in the proper form and amount, by the time set for receipt of proposals, may result in the rejection of the proposal. Copies of the SF 24 may be obtained from http://www.gsa.gov/portal/forms/type/TOP.

1.3 PAYMENT & PERFORMANCE BONDS:

The offeror to whom award is made will be required to furnish two bonds, a Payment Bond, SF 25A, and a Performance Bond, SF 25, each in the penal sum of the Solicitation. Copies of SFs 25 and 25A may be obtained from http://www.gsa.gov/portal/forms/type/TOP.

1.4 DESCRIPTION OF WORK:

Refer to ATTACHMENT 1 - SOW – Iowa City Modernize A Bank Elevators

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 AVAILABILITY OF SOLICITATION DOCUMENTS:

All solicitation related documents will be published to https://beta.sam.gov/

2.2 REQUEST FOR PROPOSAL:

This is a Request For Proposal (RFP) in accordance with FAR Part 15. Award will be made to the offeror whose proposal represents the “best value” to the Government utilizing the Lowest Price Technically Acceptable (LPTA) method of evaluation. Offerors shall submit proposal information in two (2) Volumes. Volume I shall include information to satisfy the requirements of the three (3) non-price evaluation factors (schedule, past performance, and key personnel). Volume II will contain price proposal information only to satisfy the criteria outlined in volume II, factor 4, price. No pricing information shall be submitted in volume I. To receive consideration for award, a rating of ACCEPTABLE must be achieved for all non-price factors to include schedule, past performance, and key personnel. A responsibility determination will be made in accordance with FAR 9.1.

All proposals shall be subject to evaluation by a team of Government personnel. The Government reserves the right to award without discussions based upon the initial evaluation of the proposals.

2.3 SDVOSB SET-ASIDE:

This procurement is 100% set-aside for Service-Disabled Veteran-Owned Small Business concerns. Offers received from other than Service-Disabled Veteran-Owned Small Business concerns will not be considered. All Service-Disabled Veteran-Owned Small Businesses must be listed as verified by the VA’s Center for Veterans Enterprises (CVE) (http://www.vetbiz.gov). Offerors must be verified by CVE and visible in the Vendor Information Portal (VIP) database at TIME OF SUBMISSION OF OFFERS AND TIME OF AWARD. Failure to be BOTH visible and verified at the time of proposal submission and award will result in the offeror’s proposal being deemed unacceptable and ineligible for award.

2.4 TECHNICAL QUESTIONS:

Questions of a technical nature must be provided in writing and shall be submitted by the prospective offerors to William Henkel. Questions shall be submitted only via e-mail to: William.henkel@va.gov. The subject line must read: Iowa City - Modernize A Bank Elevators – Technical Questions. Oral questions of a technical nature are not acceptable. THE CUT-OFF DATE AND TIME FOR RECEIPT OF QUESTIONS IS December 13th, 2019 at 4:30 PM (ET).

2.5 AMENDMENTS:

Amendments to this solicitation will be posted at https://beta.sam.gov/ .Paper copies of the amendments will NOT be individually mailed. No other notification of amendments will be provided. Potential Offerors are advised that they are responsible for obtaining and acknowledging any amendments to the solicitation. Failure to acknowledge an amendment may result in your proposal being considered unacceptable.

2.6 PREPARATION OF PROPOSALS:

The Government will not pay for any costs incurred in preparation and submission of proposals.

2.7 PROPOSAL REQUIREMENTS:

A. General:

a. Proposals shall be based on solicitation document issued for RFP number 36E77620R0006. Proposals will be in the format stipulated in this document.

b. Proposals shall be received on or before the date and time specified in Block 13 of the SF 1442. There will be no public opening of the proposals.

c. Submit proposals via email to:

1. William.henkel@va.gov AND Megan.dohm@va.gov
2. Emails are limited to five (5) MB.

d. Submit the original of the Bid Guarantee by mail to:

1. US Postal Service Deliveries:

William Henkel Veterans Health Administration Program Contracting Activity Central (VHA-PCAC) 6150 Oaktree Blvd., Suite 300 Independence, OH 44131

2. Commercial Delivery Services / Hand Carry (Monday- Friday, 8:00 AM to 4:30 PM (EDT)) William Henkel Veterans Health Administration Program Contracting Activity Central (VHA-PCAC) 6150 Oaktree Blvd., Suite 300 Independence, OH 44131

3. Failure to furnish the required bid guarantee in the proper form and amount, by the time specified in Block 13 of SF 1442, may result in rejection of the proposal. SEE FAR Provision 52.228-1, Bid Guarantee, of this Solicitation.

B. Proposal Format:

a. Non-Price, Price and Administrative sections of the Offerors proposals will be evaluated independently; therefore, the Offeror shall submit the proposal in three (3) Volumes: Volume I Non-price, Volume II Price and Volume III Administrative. In order that the Volume I Non-price may be evaluated strictly on the merit of the material submitted, the contractor shall include NO price information in Volume I. Offeror shall separate Volumes I, II and III. Each volume must be labeled with the Offeror's organization, business address, and VA Solicitation Number. The volumes shall be submitted in electronic format as searchable PDF documents. The proposal, in its entirety, shall not exceed three (3) emails (one email for each volume) of 5MB each. Include page numbers and the company name in the header or footer of each page.

b. Volume I Non-price: Offerors shall format the Volume I Non-Price proposal as listed below. The specific evaluation criteria and methodology for Volume I is contained in Sections D and F.

1. The offer, including title page, detailed table of contents, preface, for Volume I Non-Price shall not exceed a total of TWENTY (20) pages in Microsoft Arial size 12 font. Use graphic presentations where such use will contribute to the compactness and clarity of the proposal.

2. A page is defined as each face of an 8.5 X 11-inch sheet of paper containing information. Note, submission of the draft project schedule only, can be submitted by utilizing larger paper (11 X 17 inch). All information (except for document numbers, page numbers, etc.) shall be provided in an image area of 7 X 9 inches. Note, this does not apply for the submission of the draft project schedule. The background color of each page of the submission shall be white or ivory stock only. Excess pages will not be evaluated. Text lines will be single-spaced. A smaller font size for any graphics presented in a proposal is permitted as long as the information is legible to the human eye. Fonts other than Arial are permissible in the presentation of graphic material only.

3. The Offeror’s responses shall clearly address each evaluation factor listed in this solicitation. Failure to submit in the format required and clearly address those factors may result in this offer being rated unacceptable.

c. Volume II Price: Offerors shall format the Volume II Price proposal as listed below. The specific evaluation criteria and methodology for Volume II is contained in Sections E and F.

1. Volume II Price shall not exceed a total of TEN (10) pages in Arial size 12 font.

2. Offerors shall ensure the Signed Standard Form (SF) 1442 is provided. Offerors shall acknowledge receiving amendments by filling out section 19 of the SF 1442.

3. The Offeror’s signature on the SF 1442 must be a hand signature and not an electronic signature.

d. Volume III Administrative Information: Offerors shall include the following in Volume III. All of the below information must be provided. An Offeror may be considered unacceptable if these items are not provided in the proposal.

1. Offeror shall return a signed copy of the amendment(s) that are acknowledged in section 19 of the SF 1442.

2. Offeror shall provide their Representations and Certifications or their response to FAR 52.204-8 (2) (i) or (ii) Annual Representations and Certifications.

3. Offeror shall provide their response to FAR 52.209-7 (b) Information Regarding Responsibility Matters.

4. Offeror shall provide their response to FAR 52.209-13 (b) (1) or (2) Violation of Arms Controls Treaties or Agreements.

5. Offeror shall provide their response to FAR 52.219-28 (g) Post-Award Small Business Program Representations.

6. Offeror shall include the Safety or Environmental Violations and Experience Modification Rating Information, including filling out ATTACHMENT 7.

1. All Offerors shall submit information pertaining to their past Safety and Environmental record. The information must contain a certification that the Offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years. If such certification cannot be made, an Offeror shall explain why and submit as much information as possible regarding the circumstances of its past safety and environmental record, including the number of EPA violations and/or the number of serious, repeat, and/or willful OSHA violations, along with a detailed description of those violations.

2. All Offerors shall submit information regarding their current Experience Modification Rate (EMR). This information shall be obtained from the Offeror’s insurance carrier and be furnished on the insurance carrier’s letterhead. If an Offeror’s EMR is above 1.0, Offeror must submit a written explanation of the EMR from its insurance carrier furnished on the insurance carrier’s letterhead, describing the reasons for the elevated EMR and the anticipated date the EMR may be reduced to 1.0 or below.

3. Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state run worker’s compensation insurance rating bureau.

4. If the NCCI cannot issue an EMR because the Offeror lacks insurance history, Offeror shall submit a letter indicating so from its insurance carrier furnished on the insurance carrier’s letterhead, and include a letter from the NCCI indicating that is has assigned Offeror a Unity Rating of 1.0.

5. The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases, will be used to make an initial Determination of Responsibility.

6. This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.

*If the EMR rating for the subcontracting tiers cannot be provided at time of proposal submission, the prime contractor shall acknowledge this and provide as a submittal with the insurance and bonding requirements.

7. Failure to provide the ATTACHMENT 7 containing the above information, may result in a determination that an Offeror is not responsible and therefore ineligible for award.

C. Final Proposal Revisions

a. If determined to be necessary, proposal revisions will be requested from the proposals received. The CO will identify those Offerors, whose proposals are within the competitive range, considering the selection criteria identified in this section. Discussions may be conducted with those Offerors falling within the competitive range, after which proposal revisions will be requested. Sealed proposal revisions will be submitted as per Section 2.7(A), above, except as noted below and will be due at a time and place to be determined.

b. Offerors submitting proposal revisions will not be requested to re-submit any documents which are unchanged from their initial proposals. They should provide necessary changes to individual paragraphs, as briefly as possible, together with a table of contents, which clarifies where within the initial proposal the additional information or changed documents would be placed. Proposal revisions shall include a completed SF 1442 that acknowledges receiving all amendments, by number. A new bid bond shall be submitted only if the final proposal revisions Offeror’s price proposal is greater than its initial price proposal.

*Note this section 2.7(C) only applies if discussions are conducted.

D. Evaluation Factors – Evaluation Factors in Volume I Non-price factors and Volume II is price. Evaluation. Evaluation Factors include Project Schedule, Past Performance, and Key Personnel.

1. Volume I (non-price), Factor 1, Project Schedule:

Prepare and submit a practicable construction schedule showing all necessary work elements to complete the project identified in the specifications and drawings. This schedule must be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the performance period. The submitted schedule must be developed using project scheduling software such as MS Project, Primavera, or any other comparable form.

Each Offeror's construction schedule must address the following:

•Order of work elements to include project phasing
•Number of days for each work element
•Identification of long lead time materials
•Identification of separate work elements

The proposed schedule must include the activities which are consistent with those described within the project specifications and drawings and must not exceed the Government's maximum allowable performance period, as noted in Block 11 of the SF 1442. The project will start at the issuance of the Notice to Proceed.

2. Volume I, Factor 2 Past Performance:

Submit a minimum of three (3) and a maximum of six (6) construction projects for the Offeror that best demonstrates your experience on relevant projects that are similar in size, scope, and complexity to the RFP. For purposes of this evaluation, a relevant project is further defined as “construction or alteration of elevators and related equipment, similar in size and scope to this project”. The projects must demonstrate an offeror’s construction experience as a prime construction contractor directly responsible to the owner and managing multiple subcontractors.

For purposes of this evaluation, a relevant project is further defined as “new construction or remodeling of an elevator in an active medical environment or related space, similar in size and scope to this project.” Project(s) shall have a minimum value of $1,000,000.00. Projects submitted for the Offeror shall be 100% completed within the past five (5) years of the date of issuance of this RFP.

Minimum requirements are defined as the offeror’s past performance is recent/relevant, and has demonstrated satisfactory or better performance ratings

A project is defined as a construction project performed under a single task order or contract. For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project; rather Offerors shall submit the work performed under a task order as a project.
Offeror’s submission should include at a minimum:
•Provide the Project Title and Description, Project Location (Physical Address); Contract Type (Example: Design Build, Design Bid Build).
•Provide the project owner name and telephone number of the owner’s contact person.
•Provide a description of the scope of work, to include the work performed by the prime contractor.
•Provide project statistics including start and completion dates (original vs actual) and project cost (original vs actual. If original vs actual completion dates and project cost differ, please explanation as to why they differ.

If a completed past performance evaluation is available in CPARS, it shall be submitted with the proposal for each project referenced for Past Performance. If there is not a completed past performance evaluation available in CPARS, then the Offeror shall submit a Past Performance Questionnaire (PPQ) (reference ATTACHMENT 8) for each project referenced for Past Performance. The Offeror shall notify their client that the PPQ shall be submitted via email to the Government’s point of contact, William.henkel@va.gov. If the Offeror is unable to obtain a completed PPQ from a client for a project before proposal closing date, the Offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project.

If the Offeror is a Joint Venture (JV), relevant past performance should be submitted for projects completed by the Joint Venture entity. If the Joint Venture does not have shared experience, projects to demonstrate past performance shall be submitted for each Joint Venture partner.

3. Volume I, Factor 3, Key Personnel:

The Offeror shall provide a resume for each of the following key personnel: Project Manager, Superintendent, and Lead Engineer. The Offeror shall also provide information on personnel structure in the form of an organizational chart including any subcontractors.
For each resume, include company name; name of individual; relevant listing of experience and past projects; qualifications such as specialized training, education, years’ experience, etc.

E. Volume II, Factor 4, Price Proposal Requirements

a. Carefully follow “Instructions, Conditions, and Notices to Offerors”. Standard form (SF) 1442 Solicitation, Offer and Award (Construction, Alteration, or Repair) and the pricing schedule when submitting price offers. Submit a bid guarantee as stipulated in the solicitation.

b. In addition to the pricing schedule, Offerors shall submit a complete Breakdown of the Division Pricing for CLIN 0001.

c. The prices shall be Firm Fixed Price. The Offeror shall take care not to include remarks that take exception to the Government’s Specifications/Drawings or pricing requirements or otherwise preclude the Government from evaluating the offer or render the offer as unacceptable.

d. If the Offeror communicates in its proposal any qualifications, exceptions, exclusions, or conditions to the proposed prices not provided for in the Offerors proposal documents, the Contracting Officer may reject the proposal and exclude the Offeror from further discussions.

F. Evaluation of Offers

a. Offerors will be required to submit the information on Non-Price Factors including project schedule, past performance, and key personnel. Information submitted will be reviewed to determine if the offeror’s technical rating is ACCEPTABLE or UNACCEPTABLE.

Acceptable is defined as the Offeror demonstrated the ability to meet all of the Government’s minimum requirements as identified in the solicitation. Unacceptable is defined as the Offeror failed to demonstrate the ability to meet all of the Government’s minimum requirements as identified in the solicitation.

1. Volume I Factor 1 Project Schedule: Will be evaluated and used as an aid to help determine that the offeror understands and can perform all the required elements of the project in the time frame specified with limited impact, to the greatest extent possible, to the Medical Center. (The draft schedule submitted with the offer should not be construed as the agreed upon schedule as per FAR 52.236-15, the contractor shall, within twenty-one (21) Calendar days after receiving the Notice to Proceed, submit an interim project schedule which will supersede the draft project schedule. The interim project schedule will be subject to VA approval and must show the project being accomplished within the time frame specified on the SF 1442.

2. Volume I Factor 2 Past Performance: Will be evaluated to determine if the offeror’s past performance is ACCEPTABLE or UNACCEPTABLE. For Past Performance, acceptable is defined as based on the Offeror’s performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror’s performance record is unknown. Unacceptable is defined as based on the offeror’s performance record, the Government does not have a reasonable expectation that the offeror will be able to successfully perform the required effort.

3. Volume I Factor 3 Key Personnel: Will be evaluated on technical personnel and their qualifications to provide the required planning, implantation, and completion of the project. This shall include, Project Manager’s qualifications and past projects, Site Superintendent’s qualifications and past projects, and Lead Engineers qualifications and past projects, and any relevant certifications.

A rating of acceptable is achieved by including all information required on each resume submitted. The resumes must demonstrate a reasonable expectation of success based on experience on projects in similar size, scope, and complexity or possessing qualifications to perform on such projects. An organizational chart shall be submitted documenting each team members role as either a prime or subcontractor

4 Volume II Factor 4, Price: The total evaluated price will be determined by the Offeror's price for CLIN 0001, (Item I). The price breakdown will be used as an aid to determine price reasonableness, if necessary and shall be submitted with the offer.

2.8 DETERMINATION OF RESPONSIBILITY:

A Determination of Responsibility will be conducted for the apparent “awardee” prior to award of the project. The required information from the proposal, along with other information obtained from Government systems, such as, but not limited to the OSHA and EPA online inspection history databases, as well as any other information the Contracting Officer has determined to be valid, will be used to make the Determination of Responsibility. Failure to affirm being within the guidelines in the proposal may result in a determination of “Non-Responsible” for the Offeror. NOTE: Any information received by the Government that would cause for a negative Determination of Responsibility may make the Offeror ineligible for award.

2.9 VETS 4212:

Title 38, USC Section 4212(d), codified at 41 CFR Section 61-300, requires that federal contractors report, at least annually, the number and category of veterans who are within their workforce. Submission of the VETS-4212 reporting information can be done electronically at: http://www.dol.gov/vets/vets4212.htm. Award cannot be made unless the awardee has filed their VETS-4212 report. Therefore, all Offerors are encouraged to file every year. The Contracting Officer may request a copy of the email confirmation of receipt notification, prior to awarding the project.

2.10 SYSTEM FOR AWARD MANAGEMENT (SAM):

Federal Acquisition Regulations require that federal contractors register in the System for Award Management (SAM) database at http://www.sam.gov and enter all mandatory information into the system. Offerors are required to be registered in SAM at the time an offer is submitted in order to comply with the annual representations and certifications requirements. The Offeror shall also be registered at time of award.

2.11 BACKGROUND INVESTIGATIONS AND SPECIAL AGREEMENT CHECKS:

All contractor employees are subject to the same level of investigation as VA employees who have access to VA Sensitive Information. The level of background investigation commensurate with the level of access needed to perform the statement of work is: Low Risk. This requirement is applicable to all subcontractor personnel requiring the same access. As per VA Directive 0710, costs of background investigations will be borne by the contractor.

2.12 REVIEW REQUIRED REGISTRATION WITH CONTRACTOR PERFORMANCE ASSESSMENT SYSTEM (CPARS):

As prescribed in Federal Acquisition Regulation (FAR) Part 42.1502(e), the Department of Veterans Affairs (VA) evaluates contractor past performance on all construction contracts that exceed $700,000, and shares those evaluations with other Federal Government contract specialists and procurement officials. The FAR requires that the contractor be provided an opportunity to comment on past performance evaluations prior to each report closing. To fulfill this requirement VA uses an online database, CPARS, which is maintained by the Naval Seal Logistics Center in Portsmouth, Virginia.

Each contractor whose contract award is estimated to exceed $700,000 is required to register with CPARS database at the following web address: http://www.cpars.gov/. Help in registering can be obtained by contacting Customer Support Desk @ DSN: 684-1690 or COMM: 207- 438-1690. Registration should occur no later than thirty days after contract award, and must be kept current should there be any change to the contractor’s registered representative.

For contracts with a period of one year or less, the contracting officer will perform a single evaluation when the contract is complete. For contracts exceeding one year, the contracting officer will evaluate the contractor’s performance annually. Interim reports will be filed each year until the last year of the contract, when the final report will be completed. The report shall be assigned in CPARS to the contractor’s designated representative for comment. The contractor representative will have thirty days to submit any comments and re-assign the report to the VA contracting officer.

Failure to have a current registration in the CPARS database, or to re-assign the report to the VA contracting officer within those thirty days, will result in the Government’s evaluation being placed on file in the database with a statement that the contractor failed to respond.

2.13 REFERENCES TO VA ENGINEER, RESIDENT ENGINEER OR PROJECT MANAGER:

Any reference contained within the solicitation/contract specifications and/or drawings to the “VA Engineer,” “Resident Engineer,” or “Project Manager” or their abbreviations shall be replaced with “Contracting Officer’s Representative (COR).”

2.14 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

2.15 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

2.16 52.223-20 AEROSOLS (JUN 2016)

(a) Definitions. As used in this clause— Global warming potential means how much a given mass of a chemical contributes to global warming over a given time period compared to the same mass of carbon dioxide. Carbon dioxide's global warming potential is defined as 1.0.

High global warming potential hydrofluorocarbons means any hydrofluorocarbons in a particular end use for which EPA's Significant New Alternatives Policy (SNAP) program has identified other acceptable alternatives that have lower global warming potential. The SNAP list of alternatives is found at 40 CFR part 82, subpart G, with supplemental tables of alternatives available at (http://www.epa.gov/snap/).

Hydrofluorocarbons means compounds that contain only hydrogen, fluorine, and carbon.

(b) Unless otherwise specified in the contract, the Contractor shall reduce its use, release, or emissions of high global warming potential hydrofluorocarbons, when feasible, from aerosol propellants or solvents under this contract. When determining feasibility of using a particular alternative, the Contractor shall consider environmental, technical, and economic factors such as—

(1) In-use emission rates, energy efficiency;

(2) Safety, such as flammability or toxicity;

(3) Ability to meet technical performance requirements; and

(4) Commercial availability at a reasonable cost.

(c) The Contractor shall refer to EPA's SNAP program to identify alternatives. The SNAP list of alternatives is found at 40 CFR part 82, subpart G, with supplemental tables available at http://www.epa.gov/snap/.

2.17 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade
Goals for female participation for each trade
.5 %
6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is

2.18 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

2.19 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Megan Dohm Contracting Officer Hand-Carried Address:

Megan Dohm Department of Veterans Affairs Program Contracting Activity Central 6150 Oak Tree Blvd, Suite 300 Independence OH 44131 Mailing Address:

Megan Dohm Department of Veterans Affairs Program Contracting Activity Central 6150 Oak Tree Blvd, Suite 300 Independence OH 44131

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

2.20 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for Tuesday December 11, 2020 10:00AM CENTRAL Time

(c) Participants will meet at Iowa City VA Medical Center Building 2 Conference Room 204A 601 Highway 6 West, 138C Iowa City, IA 52246

2.21 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/

FAR Number
Title
Date
52.204-7
SYSTEM FOR AWARD MANAGEMENT
OCT 2018
52.204-16
COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING
JUL 2016
52.204-22
ALTERNATIVE LINE ITEM PROPOSAL
JAN 2017
52.215-1
INSTRUCTIONS TO OFFERORS—COMPETITIVE ACQUISITION
JAN 2017
52.236-28
PREPARATION OF PROPOSALS—CONSTRUCTION
OCT 1997

2.22 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) Prime contractors are encouraged to assist service-disabled veteran-owned and veteran-owned small business potential subcontractors in obtaining bonding, when required. Mentor firms are encouraged to assist protégé firms under VA's Mentor-Protégé Program in obtaining acceptable bid, payment, and performance bonds, when required, as a prime contractor under a solicitation or contract and in obtaining any required bonds under subcontracts.

2.23 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)

(a) Any protest filed by an interested party shall—

(1) Include the name, address, fax number, email and telephone number of the protester;

(2) Identify the solicitation and/or contract number;

(3) Include an original signed by the protester or the protester’s representative and at least one copy;

(4) Set forth a detailed statement of the legal and factual grounds of the protest, including a description of resulting prejudice to the protester, and provide copies of relevant documents;

(5) Specifically request a ruling of the individual upon whom the protest is served;

(6) State the form of relief requested; and

(7) Provide all information establishing the timeliness of the protest.

(b) Failure to comply with the above may result in dismissal of the protest without further consideration.

(c) Bidders/offerors and Contracting Officers are encouraged to use alternative dispute resolution (ADR) procedures to resolve protests at any stage in the protest process. If ADR is used, the Department of Veterans Affairs will not furnish any documentation in an ADR proceeding beyond what is allowed by the Federal Acquisition Regulation.

2.24 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)

(a) As an alternative to filing a protest with the Contracting Officer, an interested party may file a protest by mail or electronically with: Executive Director, Office of Acquisition and Logistics, Risk Management and Compliance Service (003A2C), Department of Veterans Affairs, 810 Vermont Avenue NW, Washington, DC 20420 or Email: EDProtests@va.gov.

(b) The protest will not be considered if the interested party has a protest on the same or similar issue(s) pending with the Contracting Officer.

(End of Provision) PLEASE NOTE: The correct mailing information for filing alternate protests is as follows:

Deputy Assistant Secretary for Acquisition and Logistics,
Risk Management Team, Department of Veterans Affairs
810 Vermont Avenue, N.W.
Washington, DC 20420

Or for solicitations issued by the Office of Construction and Facilities Management:

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .