36E77619R0091-0002021.docx
DOCX document 34 KB Posted
- Attached to
- Abate Asbestos Crawlspace 523-19-123 Federal contract opportunity
- Solicitation number
- 36E77619R0091
About this file
This federal contract opportunity solicitation seeks asbestos abatement services for a crawlspace at the Jamaica Plain campus of the Boston VA Healthcare System. The Department of Veterans Affairs requires removal of approximately 270 cubic yards of debris including soil, rock, and scrap materials from 40,000 square feet of crawlspace. Bidders must price removal on a per cubic yard basis to account for potential quantity variations. The abatement work also includes applying 175 cubic yards of shotcrete encapsulation. Proposals are due by November 7, 2019 and the contract will be awarded using lowest price, technically acceptable criteria. The solicitation includes specifications for traditional asbestos abatement and glovebag removal methods.
36E77619R0091 0002 36E77619R0091 0002.docx
View the file
Other files for this federal contract opportunity
Show all 50
Abate Asbestos Crawlspace 523-19-123 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 10-30-2019 523-19-123
PCAC
Shardae Webb Department of Veterans Affairs Program Contracting Activity Central 6150 Oak Tree Blvd, Suite 300 Independence
OH
44131
PCAC
Shardae Webb Department of Veterans Affairs Program Contracting Activity Central 6150 Oak Tree Blvd, Suite 300 Independence
OH
44131 To all Offerors/Bidders
36E77619R0091
X X X
X Please see attached document that lists the purposes of this amendment.
Shardae Webb Andrew Neiss Contracting Officer
VA-VHA-SAOC-2017-FKFF9F8D
The purpose of this amendment is as follows:
1. To provide a copy of the site visit sign-in sheet;
2. To provide answers to technical questions submitted;
3. To revise the SOW (Attachment 1), which provides estimated quantities;
4. To revise the Price Schedule, which indicates the estimated quantities, and requires contractors to fill in a price/cubic yard for variations in the estimated quantity;
5. To add the Traditional Asbestos Abatement Specification (section 02 82 11) to Attachment 2 (Specifications);
6. To update the Glovebag Asbestos Abatement Specification (section 02 82 13.13), part of Attachment 2 (Specifications) in order to clarify the extent of work (section 1.1.2);
7. To provide Attachment 10 – JP Sub-Basement Photos. These photos provide some examples of miscellaneous debris that may be encountered.
8. To remove the following clauses:
52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (OCT 2016) ALTERNATE I (MAY 2014)
9. To add the following Federal Acquisition Regulation (FAR) and Veteran Affairs Acquisition Regulation (VAAR) clauses:
52.211-18 VARIATION IN ESTIMATED QUANTITY (APR 1984)
52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (OCT 2019)
VAAR 852.223-71 SAFETY AND HEALTH (SEP 2019)
All other terms and conditions remain the same.
See attached document: S04 - SITE VISIT SIGN IN SHEET 10-23-2019.
SOLICITATION 36E77619R0091 ASBESTOS ABATEMENT BOSTON JAMAICA PLAN VA HEALTH CARE SYSTEM (VAHCS) - TECHNICAL QUESTIONS AND VA RESPONSE TRACKING SHEET
ITEM
NO.
| DATE QUESTION RECEIVED |
| DATE QUESTION ANSWERED |
| QUESTION |
| GOVERNMENT RESPONSE |
| 1. |
| 10-10-2019 |
| 10-10-2019 |
| The Solicitation identifies two separate small business standards – $20.5 Million in revenue and 750 employees. The multiple activities for this project as described scope of work would appear to reflect criteria for the 750 employee standard. We have not seen a Federal procurement listing more than one of these two criteria. Please clarify which one applies to this solicitation? |
| See Amendment 0001, which addresses this issue. |
| 1. |
| 10-10-2019 |
| 10-10-2019 |
| Will the Veteran Administration’s LPTA evaluation take into consideration experience with abatement/remediation of asbestos-contaminated soil in accordance with current and unique Massachusetts Contingency Plan regulations that will apply to this project? |
| See Amendment 0001, which provides the submission requirements under each evaluation factor and element. Projects of similar size, scope and complexity will be taken into consideration under the specialized experience element. |
| 1. |
| 10-10-2019 |
| 10-10-2019 |
| The Solicitation mentions this will be an LPTA evaluation to select a contractor providing Best Value to the Government. From an evaluation standpoint as defined by the FARs, “Best Value” has a very different meaning than “LPTA.” Please clarify whether the VA evaluate proposals for this project on an LPTA or Best Value basis. |
| The goal of any source selection approach is to obtain best value. Please refer to FAR 15.101 for the Best Value Continuum. Under this continuum, agencies can use tradeoffs, LPTA or any combination of these approaches to obtain best value. For this particular solicitation, the LPTA source selection process will be used in accordance with FAR 15.101-2. |
| 1. |
| 10-21-2019 |
| 10-25-2019 |
| Will there be any other documents posted prior to the walk thru for the Jamaica Plains Crawl Space? Based on the information provided in the documents, we can only come up with roughly 20K SQ FT of area, there’s no information on pipe quantities for pipe insulation within the crawl space. |
See revised SOW for additional details regarding estimated quantities. No pipe or pipe insulation removal is included as part of the scope of this project.
| 1. |
| 10-21-2019 |
There’s a specification for shotcrete in the documents. What is the intent of having that in there?
Several areas have fractured rock and exposed mix soil that needs to be stabilized and sealed.
| 1. |
| 10-21-2019 |
Will the encapsulation after the removal of soil and abatement be EPDM rubber membrane or the Shotcrete?
Shotcrete. No EPDM due to smoke hazard.
| 1. |
| 10-24-2019 |
Can you identify a designated area for contractors to stage roll-off boxes/dumpsters/vac trucks at the Site? If so, what are the dimensions of this area so we can identify sizes / number of containers/trucks that can be on-site?
Potential staging areas are available, typically ranging from 1,250 square feet to 2,000 square feet. However, the VA cannot guarantee permanent space will be available throughout the duration of the project.
| 1. |
| 10-24-2019 |
| Can you confirm access points that will be available to contractors for entering/exiting the crawl-space work areas? |
| Walkthrough Identified possible access points from subbasement such as service elevators C-Wing, B-Wing, A-Core and E-Wing for ventilation or means and methods. |
| 1. |
| 10-24-2019 |
Does the scope include abatement of all horizontal surfaces (pipes, conduit, support beams, etc.) in the crawl space areas above the floor?
No
| 1. |
| 10-24-2019 |
Is work limited to normal operating hours identified in SOW? Can work nights or weekends?
Contractors must obtain written permission from the Contracting Officer at least four (4) working days prior to any work outside normal business hours, as identified in the SOW.
| 1. |
| 10-24-2019 |
Can you provide an estimate of the volume of debris (soil, rock, cinder blocks, scrap steel, etc.) that needs to be removed from the crawlspace areas? This is critical so all contractors are bidding a uniform scope/quantity.
Estimated volume is 270 cubic yards.
| 1. |
| 10-24-2019 |
| Can you specify the depth of soil that needs to be removed from the crawl space areas? |
| Approximately 6-8” |
| 1. |
| 10-24-2019 |
Can you provide an estimate of the area requiring shotcrete installation vs. painting? This is critical so all contractors are bidding on a uniform scope.
Estimated volume is 175 cubic yards for shotcrete.
| 1. |
| 10-24-2019 |
Can you specify the area (square footage) of crawl space requiring abatement? SOW says approximately 40,000 square feet, but yellow areas on provided map (Attachment 3) equal approximately 18,759 square feet. This is critical so all contractors are bidding a uniform scope/quantity.
The Building 1 subbasement/crawlspace area is approximately 40,000 SF, of which the VA estimates an area of approximately 26,000 SF that will require some level of asbestos abatement related services and encapsulation.
| 1. |
| 10-22-2019 |
| 10-22-2019 |
| Will you be providing a Traditional Asbestos Abatement Spec? It would seem that this project would require full containments to perform this type of work. |
Traditional Asbestos Abatement (Section 02 82 11) has been added to Attachment 2 (Specifications).
| 1. |
| 10-22-2019 |
| 10-22-2019 |
| The scope of work is not very specific and could be open to interpretation. Can you please address the following: |
What is the total quantity of soils to be removed?
Estimated volume is 270 cubic yards of debris (soil, rock, etc.).
| 1. |
| 10-22-2019 |
| 10-22-2019 |
| Are all soils to be removed to bedrock? If not, what it the depth of soil across the 40,000 sf to be removed? |
6-8”
| 1. |
| 10-23-2019 |
| 10-23-2019 |
| What is to be encapsulated once the abatement takes place? |
All unimproved surfaces, all loose unexcavated substrate including fractured rock to hardpan soil or stable substrate surface.
| 1. |
| 10-23-2019 |
| 10-23-2019 |
| Since a shotcrete specification section has been included, are we to assume the government wants shotcrete utilized to encapsulate the 40,000 sf of area once abatement takes place? |
An estimated 175 cubic yards of shotcrete will be required.
| 1. |
| 10-23-2019 |
| 10-23-2019 |
| Only a “Glovebag Asbestos Abatement” section 028213.13 has been included which lists “pipe and/or pipe fitting insulation, where encountered during selective demolition within wall and ceiling chases. |
| Traditional Asbestos Abatement (Section 02 82 11) has been added. The Glovebag Asbestos Abatement (Section 02 82 13.13) specification has been updated to clarify that the majority of the work is expected to fall under the Traditional Asbestos Abatement specification. |
| 1. |
| 10-23-2019 |
| 10-23-2019 |
| Is there wall and ceiling demolition within the crawlspace? |
| No |
| 1. |
| 10-23-2019 |
| 10-23-2019 |
| What is the quantity of pipe insulation to be abated and reinsulated? |
None
| 1. |
| 10-23-2019 |
| 10-23-2019 |
| Will you be including a reinsulation spec? |
| No |
| 1. |
| 10-23-2019 |
| 10-23-2019 |
| Is there any uninsulated pipe which will require reinsulation? If so, what is the quantity? |
| No |
| 1. |
| 20-23-2019 |
| 10-23-2019 |
| The Bid Date is listed in the Solicitation is listed as 11-07-2019 at 2:00 pm. On FBO is it listed as 11-15-19. Can you please clarify which is the correct due date and time? |
| -The Bid date is 11-07-2019 at 2pm EST. |
| 1. |
| 10-23-2019 |
| 10-23-2019 |
| The Bid Guarantee Language identifies “Phase I Proposals”. Can you clarify what “Phase I” means? |
| Phase I Proposals are the when all proposals are due which is 11-07-2019 at 2pm. There will be no following Phases for this project. |
| 1. |
| 10-23-2019 |
| 10-23-2019 |
| The cutoff date listed in the solicitation for RFIs is Wednesday October 25, 2019 at 1:00 pm. Can you please clarify the correct date and time? |
| The site visit was scheduled for October 23, 2019. Technical questions were due October 25, 2019. All bids are due November 7, 2019 at 2pm EST. |
| 1. |
| 10-23-2019 |
| 10-23-2019 |
| The solicitation calls for the response to be provided in Times New Roman and later calls for Arial. Can you please clarify which font is required? |
| Responses should be submitted in 12pt Times New Roman font |
See attached document: Attachment 1 - Revised SOW - Boston Abate Asbestos Hazards Crawlspace.
See attached document: Revised PRICE SCHEDULE.
See attached document: Section 02 82 11 - Traditional Asbestos Abatement.
See attached document: Section 02 82 13.13 - Glovebag Asbestos Abatement - REVISED.
See attached document: Attachment 10 - JP Sub-Basement Photos.
A.1 52.211-18 VARIATION IN ESTIMATED QUANTITY (APR 1984)
If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgment of the Contracting Officer, is justified.
(End of Clause) A.2 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (OCT 2019)
(a) Definitions. As used in this clause— "Caribbean Basin country construction material" means a construction material that—
(1) Is wholly the growth, product, or manufacture of a Caribbean Basin country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a Caribbean Basin country into a new and different construction material distinct from the materials from which it was transformed.
"Commercially available off-the-shelf (COTS) item"— (1) Means any item of supply (including construction material) that is—
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Component" means an article, material, or supply incorporated directly into a construction material.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
"Cost of components" means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
"Designated country" means any of the following countries:
(1) A World Trade Organization Government Procurement Agreement (WTO GPA) country (Armenia, Aruba, Australia, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Moldova, Montenegro, Netherlands, New Zealand, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan, Ukraine, or United Kingdom);
(2) A Free Trade Agreement (FTA) country (Australia, Bahrain, Canada, Chile, Colombia, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Oman, Panama, Peru, or Singapore);
(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or
(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, Bonaire, British Virgin Islands, Curacao, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Saba, St. Kitts and Nevis, St. Lucia, St. Vincent and the Grenadines, Sint Eustatius, Sint Maarten, or Trinidad and Tobago).
"Designated country construction material" means a construction material that is a WTO GPA country construction material, an FTA country construction material, a least developed country construction material, or a Caribbean Basin country construction material.
"Domestic construction material" means—
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if—
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
"Foreign construction material" means a construction material other than a domestic construction material.
"Free Trade Agreement country construction material" means a construction material that—
(1) Is wholly the growth, product, or manufacture of a Free Trade Agreement (FTA) country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a FTA country into a new and different construction material distinct from the materials from which it was transformed.
"Least developed country construction material" means a construction material that—
(1) Is wholly the growth, product, or manufacture of a least developed country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a least developed country into a new and different construction material distinct from the materials from which it was transformed.
"United States" means the 50 States, the District of Columbia, and outlying areas.
"WTO GPA country construction material" means a construction material that—
(1) Is wholly the growth, product, or manufacture of a WTO GPA country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a WTO GPA country into a new and different construction material distinct from the materials from which it was transformed.
(b) Construction materials.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). In addition, the Contracting Officer has determined that the WTO GPA and Free Trade Agreements (FTAs) apply to this acquisition. Therefore, the Buy American restrictions are waived for designated country construction materials.
(2) The Contractor shall use only domestic or designated country construction material in performing this contract, except as provided in paragraphs (b)(3) and (b)(4) of this clause.
(3) The requirement in paragraph (b)(2) of this clause does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
(4) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(3) of this clause if the Government determines that—
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the restrictions of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(4) of this clause shall include adequate information for Government evaluation of the request, including—
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(4)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
| Construction Material Description |
| Unit of Measure |
| Quantity |
| Price (Dollars)* |
Item 1:
Foreign Construction Material
Domestic Construction Material
Item 2:
Foreign Construction Material
Domestic Construction Material
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.] [* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).] (End of Clause)
A.3 VAAR 852.223-71 SAFETY AND HEALTH (SEP 2019)
(a) To help ensure the protection of the life and health of all persons, and to help prevent damage to property, the Contractor shall comply with all Federal, State, and local laws and regulations applicable to the work being performed under this contract. These laws are implemented or enforced by the Environmental Protection Agency (EPA), Occupational Safety and Health Administration (OSHA) and other regulatory/enforcement agencies at the Federal, State, and local levels.
(1) Additionally, the Contractor shall comply with the following regulations when developing and implementing health and safety operating procedures and practices for both personnel and facilities involving the use or handling of hazardous materials and the conduct of research, development, or test projects:
(i) 29 CFR 1910.1030, Bloodborne pathogens; 29 CFR 1910.1450, Occupational exposure to hazardous chemicals in laboratories. These regulations are available at https://www.osha.gov/.
(ii) Nuclear Regulatory Commission Standards and Regulations, pursuant to the Energy Reorganization Act of 1974 (42 U.S.C. 5801 et seq.) Copies are available from the U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001.
(2) The following Government guidelines are recommended for developing and implementing health and safety operating procedures and practices for both personnel and facilities:
(i) Biosafety in Microbiological and Biomedical Laboratories, Centers for Disease Control and Prevention (CDC), available at http://www.cdc.gov/biosafety/publications/index.htm.
(ii) Prudent Practices in the Laboratory, National Research Council, National Academy Press, Washington, DC 20001, available at http://www.nap.edu.
(b)(1) The Contractor shall maintain an accurate record of, and promptly report to the Contracting Officer, all accidents or incidents resulting in the exposure of persons to toxic substances, hazardous materials; the injury or death of any person; or damage to property incidental to work performed under the contract resulting from toxic or hazardous materials and resulting in any or all violations for which the Contractor has been cited by any Federal, State or local regulatory/enforcement agency.
(2) The report shall include a copy of the notice of violation and the findings of any inquiry or inspection, and an analysis addressing the impact these violations may have on the work remaining to be performed. The report shall also state the required action(s), if any, to be taken to correct any violation(s) noted by the Federal, State, or local regulatory/enforcement agency and the time frame allowed by the agency to accomplish the necessary corrective action.
(c) If the Contractor fails or refuses to comply with the Federal, State or local regulatory/enforcement agency's directive(s) regarding any violation(s) and prescribed corrective action(s), the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action (as approved by the Federal, State, or local regulatory/enforcement agencies) has been taken and documented to the Contracting Officer. No part of the time lost due to any such stop work order shall form the basis for a request for extension or costs or damages by the Contractor.
(d) The Contractor shall insert this clause in each subcontract involving toxic substances or hazardous materials. The Contractor is responsible for the compliance of its subcontractors with the provisions of this clause.
(End of Clause)
File details come from the government source that posted it. Updated .