About this file

36C25919Q0751 36C25919Q0751_2.docx

View the file

Other files for this federal contract opportunity

Other files attached to EXTEND DUE DATE OF QUOTES QUESTIONS AND ANSWERS ATTACHED ADD AV LAYOUT DESIGN, newest first.
File Type Posted
36C25919Q0751-004.pdf PDF
36C25919Q0751-002.docx DOCX document
36C25919Q0751-001.docx DOCX document
36C25919Q0751-000.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FedBizOpps Amendment to a Previous Combined Solicitation

CLASSIFICATION CODE

SUBJECT

CONTRACTING OFFICE'S

ZIP-CODE

SOLICITATION NUMBER

BASE NOTICE TYPE

RESPONSE DATE (MM-DD-YYYY)

ARCHIVE

DAYS AFTER THE RESPONSE DATE

RECOVERY ACT FUNDS

SET-ASIDE

NAICS CODE

CONTRACTING OFFICE

ADDRESS

POINT OF CONTACT

(POC Information Automatically Filled from User Profile Unless Entered)

DESCRIPTION

See Attachment

AGENCY'S URL

URL DESCRIPTION

AGENCY CONTACT'S EMAIL

ADDRESS

EMAIL DESCRIPTION

ADDRESS

POSTAL CODE

COUNTRY

ADDITIONAL INFORMATION

GENERAL INFORMATION

PLACE OF PERFORMANCE

* = Required Field FedBizOpps Amendment to a Previous Combined Solicitation Rev. March 2010

EXTEND DUE DATE OF QUOTES

QUESTIONS AND ANSWERS ATTACHED

ADD AV LAYOUT DESIGN

80111 36C25919Q0751

COMBINE

09-24-2019 N 541519 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 Kim Cooper (CO) Contracting Specialist 406-447-6730

DENVER

kim.cooper3@va.gov kim.cooper3@va.gov

QUESTIONS AND ANSWERS

1. Is Volume II – General Standards of Responsibility the same as a Technical Response to be supplied in the proposal? Technical response would include warranty, service and support.

2. Where are the detailed floor plans referenced in 4.2.1 of the General Conditions and Statement of Work? Attached to the amendment

3. Is the Project Management Plan to be provided with the proposal or upon award? With proposal so we can review.

4. Is there any control programming required for the installations? Only if their systems require it, but for base design of display that will connect to our system.

5. Can the Government grant an extension to Tuesday, 9/24. We are really cutting it close on timeframe for installation and operation, now every week and day counts for us.

Extension to close date to 24 September 2019, 12 pm Eastern

See attached document: SIM EQ008 AV System - AV Layout Design.