36C25719Q0330-0001001.docx

DOCX document 14 KB Posted

Attached to
New - CTX Elevator Service and Maintenance Federal contract opportunity
Solicitation number
36C25719Q0330
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 17

About this file

36C25719Q0330 0001 Solicitation 36C25719Q0330 - Questions and Answers.docx

View the file

Other files for this federal contract opportunity

Other files attached to New - CTX Elevator Service and Maintenance, newest first.
File Type Posted
-16699.docx DOCX document
36C25719Q0330-0002000.docx DOCX document
36C25719Q0330-0001002.docx DOCX document
36C25719Q0330-0001004.docx DOCX document
36C25719Q0330-0001003.docx DOCX document
36C25719Q0330-0001000.docx DOCX document
36C25719Q0330-003.docx DOCX document
36C25719Q0330-007.docx DOCX document
36C25719Q0330-001.pdf PDF
36C25719Q0330-002.docx DOCX document
36C25719Q0330-006.docx DOCX document
36C25719Q0330-000.docx DOCX document
36C25719Q0330-005.docx DOCX document
36C25719Q0330-004.docx DOCX document
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation 36C25719Q0330 – CTX Elevator Maintenance, Repair and Inspection Questions

1. Request elimination of first sentence, paragraph B.3 Licensing and Supervision requiring contractor to be “licensed by the State of Texas”.

Answer: Yes, may be removed

2. Request clarification or removal of paragraphs one and four of Section B.3 “Contractor Experience and/or requirements”

· Contract employees shall be factory trained and certified at installing and repairing Gigaman data circuits. The CO or COR may request proof of this certification prior to authorizing contract employees to service the equipment.

· Contractor must furnish maintain the most current and updated maintenance and/or repair manuals for the data circuit in question.

Answer: Yes, may be removed

3. Request consideration of adding a local presence requirement by offeror to ensure effective/timely response to emergency calls within allotted times.

Answer: Not required. Contractor must meet all required timeframes throughout the Statement of Work.

4. Clarify the requirement for “semi-annual” and “annual” testing (pages 20-21). Do you require the contractor to provide personnel for the semi-annual visit or can we provide an alternate to remove the semi-annual requirement? Will VA be bringing in a third-party inspector mid-term? Will the inspector coordinate with the contractor in order to maintain situational awareness and to coordinate the facilities of tasks being performed?

Answer: Yes, there will be a semi-annual inspection. The vendor conducting the inspections usually coordinates with the contractor. Contractor is responsible for hiring the third party inspector IAW CLIN’s 0005, 0012, 1005, 1012, 2005, 2012, 3005, 3012, 4005, 4012.

5. Request confirmation of Temple and Waco elevator schedules (Attachments 1 and 2 of solicitation) as the elevator scheduled published appear slightly different from the current state of elevators on the campuses.

Answer: P1 and P2 can be removed from Waco Building 1. “Dirty” “Clean” “DW2” and “Emergency Car” will be added to Building 163 in Temple.

Attachments 1 “Temple Elevator List” and Attachment 2 “Waco Elevator List” are removed in their entirely and replaced with attachments in this amendment.

6. Current contractor:

Answer: Task Order #36C25718F1262 Contractor: Thyssenkrupp Elevator Corporation

File details come from the government source that posted it.