36C25719B0036-0001002.pdf

PDF Posted

Attached to
Modernize Elevator Controls Project No. 671-19-111 Federal contract opportunity
Solicitation number
36C25719B0036
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 17

About this file

36C25719B0036 0001 Revised Schedule B - Elevator Controls.pdf

View the file

Other files for this federal contract opportunity

Other files attached to Modernize Elevator Controls Project No. 671-19-111, newest first.
File Type Posted
36C25719C0231-000.docx DOCX document
36C25719B0036-0002000.docx DOCX document
36C25719B0036-0002001.pdf PDF
36C25719B0036-0002001.pdf PDF
36C25719B0036-0002000.docx DOCX document
36C25719B0036-0001001.pdf PDF
36C25719B0036-0001000.docx DOCX document
36C25719B0036-0001002.pdf PDF
36C25719B0036-0001000.docx DOCX document
36C25719B0036-0001001.pdf PDF
36C25719B0036-004.pdf PDF
36C25719B0036-003.pdf PDF
36C25719B0036-002.doc DOC document
36C25719B0036-001.docx DOCX document
36C25719B0036-002.doc DOC document
36C25719B0036-001.docx DOCX document
36C25719B0036-004.pdf PDF
36C25719B0036-003.pdf PDF
36C25719B0036-000.docx DOCX document
36C25719B0036-000.docx DOCX document
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REVISED

SECTION B – SCHDULE OF PRICES/DESCRIPTION

DESCRIPTION: Contractor shall provide all necessary labor, materials, equipment, and supervision to

Modernize Elevator Control located at the Audie L. Murphy 7400 Merton Minter, Texas, TX 78229. The work shall be in accordance with the provided specifications and drawings.

BID Item (s):

ITEM UNIT TOTAL

NO. DESCRIPTION OF SERVICE QTY UNIT PRICE AMOUNT

BID:

0001 PROVIDE ALL NECESSARY 1 JB $__________ $_________

LABOR, MATERIALS, AND EQUIPMENT

NECESSARY TO MODERNIZE ELEVATOR

CONTROLS PER THE PROVIDED

GR-SOW

(SEE GENERAL REQUIREMENT 1.4 STATEMENT

OF BID ITEMS)

0002 COST OF PERFORMANCE AND 1 EA $___________ $ _________

PAYMENT BONDS

**TOTAL PROJECT DURATION: 400 Calendar days from issuance of the Notice to Proceed to complete the project work.

Bid TOTAL (Line items 0001 & 0002) $___________