629-18-114 Phase 1 RFI Register 07092024.docx

DOCX document 30 KB Posted

Attached to
Z1DZ--Project #629-18-114 Expand Distributed Antenna System (DB) Federal contract opportunity
Solicitation number
36C25624R0010
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16

About this file

This document is a Request for Information (RFI) regarding a federal contract opportunity numbered 36C25624R0010 to expand a Distributed Antenna System. The key details are:

The RFI provides responses to six questions related to the submission requirements for Factor 3 - Past Performance in the proposal. Regarding the past performance examples, the RFI clarifies that offerors can submit a combination of projects from the prime contractor and the A/E firm, with a maximum of 5 total projects. Past performance evaluations can be provided through CPARS or the Past Performance Questionnaire (PPQ) format, and these submissions will count towards the 30-page proposal limit. The minimum construction value for past performance examples is $10 million, and the minimum A/E design fee is $1 million, depending on the type of submission (Design/Build, A/E, or Construction). The government has indicated that it will not lower these minimum thresholds at this time.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DZ--Project #629-18-114 Expand Distributed Antenna System (DB), newest first.
File Type Posted
INTERSTITIAL LEVEL 4i AREA E2-Model.pdf PDF
INTERSTITIAL LEVEL 2i AREA F2-Model.pdf PDF
INTERSTITIAL LEVEL 4i AREA E1-Model.pdf PDF
INTERSTITIAL LEVEL 3i AREA D2-Model.pdf PDF
INTERSTITIAL LEVEL 3i AREA D1-Model.pdf PDF
INTERSTITIAL LEVEL 2I AREA G1.1-Model.pdf PDF
INTERSTITIAL LEVEL 3i AREA G1-Model.pdf PDF
06-M TRANSITIONAL - LVL.1 & 2-06.M.1-2 (1).pdf PDF
03.SUM.pdf PDF
02.DEFG.pdf PDF
09.Q.pdf PDF
07.N.pdf PDF
03-HJ OUTPATIENT - LVL.7 & 8-03.HJ.7-8.pdf PDF
SECOND FLOOR.pdf PDF
03-HJ OUTPATIENT - LVL.5 & 6-03.5-6B L.S..pdf PDF
00-A CONCOURSE - LVL.3-00.AX-3 L.S..pdf PDF
01-BC INPATIENT - LVL.4-01.BC.4.pdf PDF
03-HJ OUTPATIENT - LVL.3-03.HJ.3.pdf PDF
03-HJ OUTPATIENT - LVL.2-03.HJ.2.pdf PDF
09-Q ADMIN -.BASEMENT.pdf PDF
05-L VISITOR PARKING - LVL.7-05.L.7 L.S..pdf PDF
00-A CONCOURSE - LVL.4I-00.AX-4I L.S..pdf PDF
36C25624R0010 A0001 REVISED-3RD LEVEL -PATIENT GARAGE.pdf PDF
36C25624R0010 A0001 REVISED-1ST LEVEL -STAFF GARAGE.pdf PDF
36C25624R0010 A0001 NOR-CC-03AR.pdf PDF
36C25624R0010 A0001 NOR-CC-01AR.pdf PDF
36C25624R0010 A0001 NOR-10-01AR.pdf PDF
36C25624R0010 A0001 NOR-09-04AR.pdf PDF
36C25624R0010 A0001 NOR-08-03MZAR.pdf PDF
36C25624R0010 A0001 NOR-08-03AR.pdf PDF
36C25624R0010 A0001 NOR-07-04MZAR.pdf PDF
36C25624R0010 A0001 NOR-07-01MZAR.pdf PDF
36C25624R0010 A0001 NOR-06-0PAR.pdf PDF
36C25624R0010 A0001 NOR-03-06AR.pdf PDF
36C25624R0010 A0001 NOR-03-04AR.pdf PDF
36C25624R0010 A0001 NOR-01-06AR.pdf PDF
36C25624R0010 A0001 NOR-01-02AR.pdf PDF
36C25624R0010 A0001 REVISED-5TH LEVEL -PATIENT GARAGE.pdf PDF
Att 13 - DAS - Scope of Existing.docx DOCX document
Att 12 - DAS - Schedules.docx DOCX document
Att 2 - DAS - Construction Waste Mgmt.doc DOC document
36C25624R0010 SOW 629-18-114 06072024.docx DOCX document
36C25624R0010 EXHIBIT A.docx DOCX document
Att 4 - DAS - Distributed Antenna System Technical Specification.docx DOCX document
Att 3 - DAS - DAS Master Specification.docx DOCX document
36C25624R0010 WD LA20240041 Mod 0 01052024 .pdf PDF
36C25624R0010 EXHIBIT F.docx DOCX document
36C25624R0010 EXHIBIT E.docx DOCX document
36C25624R0010 EXHIBIT C.docx DOCX document
36C25624R0010_2.docx DOCX document
Show all 50

Z1DZ--Project #629-18-114 Expand Distributed Antenna System (DB) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOR OFFICIAL USE ONLY

Source Selection Sensitive Information—See FAR 2.101 & 3.104 Project No. 629-18-114; Expand Distributed Antenna System 36C25624R0010

Question
Answer

RFI #1 – On page 15, under “Submission Criteria” for Factor 3, it states: “If the contractor does not possess Design-Build (D-B) experience, provide a minimum of one (1) and a maximum of five (5) projects completed by the A-E firm…in addition to the one (1) to five (5) projects submitted for the prime contractor.” If the prime contractor does not possess Design/Build experience, is the offeror to submit up to 5 examples from the A/E firm along with up to 5 examples for the prime contractor for a potential maximum of 10 projects (5 design, 5 construction), or is it a combination of the two to get to a MAXIMUM of 5 projects total?

Phase 1 proposals shall not exceed 30 pages. It is on the offeror how they wish to present their proposals within the 30 page limitation.

RFI #2 – On page 15, under “Submission Criteria” for Factor 3, regarding Past Performance Evaluations, it states: “Separately provide any completed Past Performance Evaluations, if any...Offerors shall prepare and forward…Exhibit B (PPQ) for all the projects listed by contractor…” If the offeror has existing CPARS for submitted projects, can CPARS satisfy the criteria for Past Performance Evaluation, or must the Past Performance Questionnaire be submitted for each project example?

CPARS may be used to satisfy the past performance factor. Past Performance Questionnaires not received on behalf of the offer will not be penalized during the evaluation. The government reserves the right to review all sources of past performance history.

RFI #3 – Do Past Performance Evaluations, whether PPQ or CPARS (if allowed), count towards page limit?

If PPQs or CPARS are submitted with a given proposal, then the submitted information will be counted towards the page limitations. PPQs that are submitted by a third party will not count towards page limitations.

RFI #4 – For past performance examples, do the projects need to meet both the minimum construction value ($10,000,000) AND AE value ($1,000,000) to be considered acceptable? Or is it a

This answer depends based on the submission type –

a) Design/Build Submission: Both will need to be met.

b) AE Submission: AE firm design fee will need to be met.

c) Construction Submission: Construction firm will need to be met.

RFI #5 – 1) Regarding past performance, is the AE value of a project example considered the Design Fee of an AE firm for a construction project? 2) Or is it the value of the total project that the AE firm performed work?
1) It is the fee on an AE contract – all encompassing (as detailed in a SF330.

2) NA

RFI #6 – Would the government consider lowering the threshold for the minimum values for both Construction and AE for Factor 3?
No changes will be made to these figures at this time.