This document contains responses to questions from contractors regarding Solicitation Number 36C25622R0092 to construct a three-sided Emergency Management and Preparedness Infrastructure (EMPI) structure at the Biloxi, Mississippi VA Medical Center. Key details include:
-
The scope of work involves constructing a 120' x 80' metal building structure on three sides with a standing seam roof and non-insulated metal wall panels. Electrical work includes installing a new transformer, panelboards, lighting fixtures, and receptacles. Site work comprises a 120' x 90' building slab and security fencing.
-
Contractors must follow the 2018 International Building Code's Exposure D, Risk Category IV wind load of 182 mph. Foundations will be dictated by the selected pre-engineered metal building system. No wall or roof insulation is required. Manual gate operation and Ameristar fencing specifications apply. The awarded contractor must provide engineered drawings.
-
The Department of Veterans Affairs is the contracting agency. Questions pertained to design parameters, materials, and clarifying scope items. Extended performance may be considered depending on material lead times. The solicitation number is for reference to publish the opportunity.
View the file
Other files for this federal contract opportunity
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFIs / QUESTIONS RECEIVED & RESPONSES THERETO 36C25622R0092 Project No. 520-22-177 Three-Sided EMPI Structure
RFIs / QUESTIONS RECEIVED GOVERNMENT RESPONSE
1. Is there a Geotechnical report available? No. There is not a Geotechnical report available.
2. Is there a required elevation for the top of slab? Top of the Slab is to be 24.50 FFE (MSL)
3. Can the Government specify and/or provide the location and linear footage of fence on the Site Drawing?
Please see SOW for approximate footage and route.
4. The SOW is calling for tie into building 26 for the electric service the EMPI building. How far from the outside of the building to the existing panel fed the EMPI Building?
Approximately 500 feet. Contractor to verify lengths.
5. Who is the manufacture and type of the existing panelboard feeding the EMPI building?
GE Spectra
6. Is a grounding counterpoise system requiring to be installed around the new metal structure and bonding jumper installed to the building steel?
Yes
7. The SOW is calling for a 480v feeder to be installed for the MDP. IS the new feeder 3ph 4wire or single-phase feeder?
3 phase 4 wire
8. The SOW is call for a 50kva dry type transformer. 50kva is a single-phase transformer. The panelboard being feed by the 50kva transformer is called out by the SOW to be 3 phase panelboards. Is the new transformer need to be 45kva 480v 3ph to 208v/120v 3ph 4wire?
The Transformer is to be 3 phase for 480v 3ph to 208v/120v 3ph 4wire
9. What is the primary and secondary voltage of the 50kva transformer?
Primary is 480 3 phase to 208/120v 3 phase
10. The SOW is calling for 80amp breaker to feed the need 50kva transformer. A 50KAV transformer has 104.2-line amps. Is the 80 breaker the correct size for feeding the 50kva transformer?
Yes
11. Will lightning protection be required to be installed on the new EMPI structure?
Yes
12. Is a surge suppressor required to be installed in the new MDP panelboard?
Yes
13. Which panelboard are the new light fixture to be feed from?
480 panel
14. The SOW is call for a 120v 60amp ranger receptacle to be installed. Range receptacle are all 60amp 120/250v 3 wire with ground or 120/208v wire with ground.
Range Receptacle – 50 Amp 120/250v 4 wire
15. The new structure feeder is over 225 feet the existing power source. There will need additional grounding electrode conductor installed and the new MDP. Will the additional grounding electrode conductor need to be installed?
Yes, but no floating ground
16. Please confirm that the feeder for the new MDP panel is being feed from one of the spare 400amp existing chiller disconnect?
Yes, ACC-1 225Amp GE C/B
17. Please confirm that the feeder for the new MDP panel is 3ph 3wire 480v with ground?
Yes, 4/0 AWG
18. It was mentioned at the site visit that the MDP, transformer and the second panelboard can all be installed on the inside of the structure center on the east wall of the new structure?
Yes, the MDP, Transformer, and DP2 can be installed in the center of the East wall.
19. Depending on the type of power require for the project. The transformer secondary can be either 240v/120v single phase or 208Y/120v 3ph 4wire. The RV typically don’t have any equipment that require 240v, very thing in the RV is 120v. 208Y/120v 3ph 4wire power offer the most flexibility for any additional power that may be require in the future. Does the owner want to use a 480v to208Y/120v 3ph 4wire transformer?
Yes, 480v to208Y/120v 3ph 4wire transformer is acceptable
20. What size transformer does the owner want? A 45kva 3phase transformer will provide a 125amp at 208 v or 75kv which will provide 208amp of power of 208v.
A 45 to 50 KVA 3 phase Transformer
21. Depending on which transformer the owner chose the breaker in the MPD will need to be change to and 70amp 3pole for the 45KVA transformer, 125amp 3pole for the 75kva transformer or 145-amp 2 pole for the 50kva single phase transformer. Which breaker does the owner want install in the MDP?
70 Amp 3 pole
22. Can the contractor size and install the conduit as per the NEC and long as the spare conduit are the same size?
Yes. That is the intention.
23. Are the is the new transformer need to be grounded to either building steel or a ¾’’x 10’ copper clad ground rod as per the NEC?
The NEC is to be followed.
24. In order to install the conduit from the existing disconnect to the underground conduits, it will be necessary to install exposed conduit on the existing concrete pads. Will the owner except this installation as long as the conduit is galvanized ridge conduit (GRC)?
Yes. That is acceptable. Anything above and into grade is GRC including 90’s to horizontal run PVC
25. If the new underground conduits are installed on the permitter of the new slab, do they need to be concrete encased?
No, the Conduit needs to be run a Minimum of 24” below ground, marked with metal tape, and embedded in sand.
26. Specifications call for submittals on Door, Windows, and Insulation. Statement of work does not indicate the requirement for doors, windows, or insulation. Please confirm that there are no personnel doors required, nor any windows or insulation.
The specifications for Doors, Windows, and Insulation are not Applicable. There will be no door, windows, or insulation.
27. Will ridge vents be required on the PEMB? No. Ridge Vents are not required.
28. I work for a General Contractor bidding the Construct Three-Sided EMPI Structure project.
The drawing the VA representative had with him was a layout of all the Emergency Management equipment laid out on the 120’ x 80’
I have an electrician asking about the drawings, I did realize that the site plan and site plan model large are the same. He believes that at the walk through the VA representative had a different drawing showing the proposed trailer locations as well as some written notes pertinent to the electrical work needed. Is that something that can be sent to us or uploaded to SAM.gov?
footprint. Nothing other than the scope of work and answers to these questions will be provided.
29. Are soil borings available for the EMPI Structure site? Can they be provided prior to bid?
No Soil Borings are available.
30. Will the awarded contractor be responsible for supplying a complete set of engineered/stamped drawings for this project?
Yes. A complete set of Drawings for paper / electronic for work completed.
31. From our initial calculations, maintaining an 18’ minimum clearance between the bottom side of the lowest beam and the floor (the haunch), coupled with a 120’ span, puts the eave height at approximately 23’ with a beam that is 4’8” at the haunch. If the requested design parameters are not achievable, please advise which dimension is most critical, 20’ eave height or 18’ minimum clearance at the haunch.
Note: Given a 1/2 on 12 pitch, the ridge height would be approximately 25’6”.
The critical elements of this structure is that any 18’ or lower vehicle / trailer can be stowed out of the elements. Depending on which Pre-Engineered Metal Structure Manufacturer, designs will vary.
Only 3 sides, no internal columns, and pitched roof for a 120’ x 80’ structure are needed.
32. Reference EMPI Specifications 13 34 19 1.4.A.2: From our research, IBC 2018 calls for Exposure D, Risk Category IV – 182 mph wind load. Referenced specification states 140 mph pressure wind load. Please advise preferred wind load for EMPI Structure.
Preferred Wind Load Required- IBC 2018 calls for Exposure D, Risk Category IV – 182 mph wind load.
33. Due to the location being in close proximity to bodies of water, would the Owner prefer the structure to have galvanized primary and secondary steel?
Yes
34. SOW only describes site concrete as 120’ x 90’ building slab. Is this the only concrete needed for site access? Are any additional driveways or sidewalks required?
120’ x 90’ slab and footers. No other driveways or sidewalks at this time.
35. What is the desired roof pitch? The Lowest Pitch possible without the roof being flat.
36. Would a screw down roof be acceptable or is a standing seam roof preferred as per spec?
Government requests a standing seam roof.
37. Can an approved primer and paint manufacturer be provided along with a more detailed paint spec?
Manufacturer recommended. Paint Specification is page 107 of EMPI Specs.
38. The current lead time for a pre-engineered metal building package from our supplier is approximately 36 weeks (252 days). Can the government extend the completion time in order to allow for the lead time on the building?
Possibly. Extended period of performance can be addressed after contract award depending on information received from manufacturer concerning production and delivery times, etc.
39. What exposure classification is the pre-engineered metal building; “B”, “C” or “D”.
Preferred Wind Load Required- IBC 2018 calls for Exposure D, Risk Category IV – 182 mph wind load.
40. Spec. section 13-34-19_2.2_D.: “Wall panels shall consist of an insulation core enclosed between (2) metal face sheets”. Is it the governments desire to have this insulated panel or just a non-insulated 26-gauge exterior wall panel?
The government’s desire is to have non-Insulated 26-gauge metal wall panels. Colors to be determined by interior designer with submittals.
41. The scope of work calls for a 6’ wide translucent panel at the top on the (3) enclosed sides. The standard panel width is 5’-6”. Is the 5’-6”’ wide panel acceptable?
The “Translucent” section will be 6’ from the eaves down. You can use whatever translucent panel width desired as long as the top 6’ is translucent.
42. Are liner panels required for the interior of the metal building? If required, please provide height.
No liner panels are required for this Contract.
43. Will wall and roof insulation be required for the metal building? If required, please provide specification.
No roof or wall insulation is to be included in the Contract.
44. Under the scope of work, page 6, the description of the building indicates a “lean to” structure with a single slope roof; 20’ eave height at the open side and 18’ eave height at the rear, enclosed side. At the pre-bid site meeting, attendees were given a schematic drawing which indicates a gable roof structure with a 21’ eave height. Are we to go by the schematic drawing or the description in the scope of work?
The schematic drawing was provided to illustrate an idea of a 3-sided Structure. Contractors are to go by Scope of Work.
45. There are no geotechnical reports, civil drawings indicating existing grades, proposed finish grades and finish floor elevation. How is a prime contractor to quote a stipulated sum for earthwork when the above information is not provided?
The Site Visit was to allow Contractors to see current conditions.
Contractor to use judgement in earthwork estimate.
46. Spec. section 31_20_00_1.2_I. states that the removal of unsuitable materials and its replacement as directed will be paid on the basis of conditions of the contract. Can the government provide a spec. section for changes in the work?
The Pre-Engineered Structure will dictate the footers and foundations. The Contracting Officer will have sole authority in authorizing any changes in the work.
47. There are no geotechnical reports clarifying the existing soil conditions nor are there any structural design drawings indicating the footing / foundation design for the metal building.
Without known soil conditions and design criteria, prime contractors will be “guessing” at the design and subsequent costs for the foundation. How is a prime contractor to quote a stipulated sum for the foundation when the design will not be determined until after proposals are received?
The Pre-Engineered Structure will dictate the footers and foundations.
48. Will the concrete slab have a “turndown” edge at the perimeter? If yes, please provide dimensions.
There will be no turndown edge.
49. What type and size of steel reinforcement is required for the concrete slab?
The Pre-Engineered Structure will dictate the footers and foundations.
50. What is the dimension for the concrete ribbon and associated steel reinforcing for the anti-climb fencing?
Please refer to the Ameristar Fencing Manufacturer Literature included with RFP for recommended information.
51. Are the dimensions of the proposed slide / roller gate the same as what is indicated on page 14 of the Ameristar Fence Products?
Is the gate to be electrically operated?
No. Typical data provided by Ameristar Fence Products. There will be only manual operation of the gate.
52. The plans call for a concrete ribbon for the fence but plans outlining the dimensions or specs for concrete ribbon are absent. What are the desired dimensions for the concrete ribbon?
Same as Question # 50
53. Please advise if specifications section 13 34 19.2.2.D and E are correct and the building is to have insulated wall panels and semirigid insulation on the inside face of the roof panels as the spec suggests given this is an open structure.
Please see RFI #26 – No insulation is required.
54. Please define what is meant by exposed steel which will require a primer coat prior to insulation and two finish coats after installation.
Do you mean any unfinished steel is to be painted or are we adding an additional three coats of paint to the entire building?
Depending on your Pre-Engineered Building Manufacturer, the structural steel may or may not come pre-primed. If it is not, a primer and topcoat is needed to protect it from the elements. If the structural steel comes with a primer coat prior to erecting, just a topcoat is required.