36C25618B0171-00003001.docx
DOCX document 17 KB Posted
- Attached to
- Project 598-18-111: CORRECT AIRFLOW DEFICIENCIES IN EXISTING OR9 Federal contract opportunity
- Solicitation number
- 36C25618B0171
About this file
36C25618B0171 00003 Airflow Control_Questions-Answers.docx
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25618B0171-00005000.docx | DOCX document | |
| 36C25618B0171-00004000.docx | DOCX document | |
| 36C25618B0171-00003000.docx | DOCX document | |
| 36C25618B0171-00002003.pdf | ||
| 36C25618B0171-00002001.pdf | ||
| 36C25618B0171-00002002.pdf | ||
| 36C25618B0171-00002000.docx | DOCX document | |
| 36C25618B0171-00001000.docx | DOCX document | |
| 36C25618B0171-001.docx | DOCX document | |
| 36C25618B0171-000.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25618B0171 Correct Airflow Deficiencies
QUESTIONS & ANSWERS
Question 1: Is this project tax exempt?
Answer 1: No.
Question 2: Please provide the project plan and specifications.
Answer 2: All is in the FBO solicitation
Question 3: Please provide the proposal requirements.
Answer 3: All is in the FBO solicitation
Question 4: Please confirm an offer guarantee is not required.
Answer 4: Offer Guarantee is required.
Question 5: Please provide the contractor staffing requirements for the project.
Answer 5: We do not dictate how the contractor performs the contract.
Question 6: I have seen a few questions concerning Specifications?
Answer 6: If it isn’t specified in the specs n drawings it is the industry standard for that location.