About this file

This document is a solicitation for a construction contract to Construct Campus Perimeter Barrier for Physical Security at the Marion VA Medical Center in Illinois, Solicitation Number 36C25524R0105.

The key details are:

  • The Department of Veterans Affairs, Network Contracting Office 15 intends to award a firm-fixed-price construction contract for this project, which is being solicited as a Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside.
  • The work includes securing the entire perimeter of the campus with fencing, installing gates, and integrating video surveillance and lighting. The estimated construction value is between $2-$5 million.
  • The period of performance is 365 calendar days from the notice to proceed. Proposals are due by 2:00pm CDT on August 26, 2024.
  • Award will be made based on the lowest priced, technically acceptable offer. Offerors must submit documentation demonstrating relevant construction experience, project execution approach, qualifications of key personnel, past performance, and a safety plan.
  • Contractors must be registered in SAM.gov and SDVOSB/VOSB contractors must be certified in SBA VetCert by the proposal due date.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA-- Construct Campus Perimeter Barrier for Physical Security, 657A5-23-114, newest first.
File Type Posted
36C25524R0105 0003.docx DOCX document
36C25524R0105 0002.docx DOCX document
Floor Plans and Panels.pdf PDF
36C25524R0105 0001.docx DOCX document
Pre-Bid Site Visit Attendance Roster 657A5-23-114.pdf PDF
PAST PERFORMANCE QUESTIONNAIRE-PPQ.docx DOCX document
P09 2024-06-06 - 100 percent Final Drawings - 26 pages.pdf PDF
P09 657A5-23-114 - Specifications 958 PAGES.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25524R0105

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C25524R0105 X

TBD

657A5-23-114 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth

KS

66048 Y Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth

KS

66048

HOOVER, MARIA

913-946-1127 The Department of Veteran Affairs, NCO-15, intends to award a Construction Contract for project 657A5-23-114, Construct Campus Perimeter Barrier for Physical Security at Marion VA Medical Center in Marion Illinois.

This project is being solicited as a Service-Disabled Veteran Owned Small Business (SDVOSB) set aside.

Proposals received in response to this solicitation will be evaluated in accordance with the procedures outlined in the Federal Acquisition Regulation (FAR) Part 15.101-2, Best Value Lowest Price Technically Acceptable Source Selection Process. See Basis for Contract Award explanation in paragraph 3 of Proposal Submittal Instructions Those offerors not providing the documentation outlined in the "Instructions to Offerors" will be rated unacceptable to the terms of the solicitation. The NAICS code for this project is 236220 - Commercial and Institutional Building Construction, the size standard of $45.0 Million.

UNIQUE ENTITY IDENTIFIER NUMBER:

Estimate of the construction magnitude for this project is between $2,000,000.00 to $5,000,000.00 million.

There will be one site visit for this project. The site visit is scheduled for August 8, 2024 at 10:00 AM CT in Bldg 15 at Marion VA Medical Center, 2401 W. Main St., Marion, IL. All questions pertaining to this project are due by 12:00 PM CDT, August 13, 2024. All questions shall be e-mailed to maria.hoover@va.gov.

CONTRACTORS WILL BE REQUIRED TO ELECTRONICALLY SUBMIT PROPOSAL BY EMAIL TO THE CONTRACTING OFFICER, MARIA HOOVER.

Contracting Officer's email: maria.hoover@va.gov, phone 913-946-1127.

(CONTRACTOR WILL BE REQUIRED TO VERIFY THAT THE EMAIL HAS BEEN RECEIVED WITH ATTACHED PROPOSAL DOCUMENTS BY THE

CONTRACTING OFFICER).

Contractors working on this project are exempt from state sales tax, and a project tax exemption certificate will be issued upon award of this contract.

Bid Bond shall be included in emailed proposal and hard copy mailed to address in block 8 by proposal closing date.

Award will be made on item number 0001. However, should offer exceed the funds available, award will be made on item numbers 0002-0007 within the available funding limits. Period of Performance for this project is 365 calendar days.

All contractors and Joint Ventures must be registered in Sam.gov. All SDVOSB and VOSB contractors must also be certified in SBA VetCert by the proposal due date in order to be eligible for award.

NOTICE: Clause 52.222-37 Employment Reports on Disabled Veterans and Veterans is incorporated by reference in this solicitation. Public Law (P.L. 105-339), Section 1354 provides that no agency may enter into a contract with a contractor who has not filed a VETS-4212 report for the preceding fiscal year under TITLE 38 SECTION 4212 (d).

X X 52.211-10 X Zero

2:00 PM

CDT

08-26-2024 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(see specification section 01 00 00, para 1.3) Price to be submitted on pages 4 - 7 of this solicitation.

36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth

KS

66048 36C255 Department of Veterans Affairs Financial Services Center http://www.fsc.va.gov/einvoice.asp Austin

TX

877-353-9791 512-460-5429 X Maria Hoover Contracting Officer

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
A.3 PRICE/COST SCHEDULE5
ITEM INFORMATION5
A.4 STATEMENT OF WORK7
Statement of Work:8
Performance Period:8
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS9
1.1 INSTRUCTIONS TO OFFERORS9
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS21
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)21
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)21
2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)21
2.4 52.233-2 SERVICE OF PROTEST (SEP 2006)23
2.5 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)23
2.6 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)24
2.7 VAAR 852.223-70 INSTRUCTIONS TO OFFERORS—SUSTAINABLE ACQUISITION PLAN (SEP 2019)24
2.8 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)24
2.9 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)25
REPRESENTATIONS AND CERTIFICATIONS26
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2024)26
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)30
3.3 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)33
3.4 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)34
GENERAL CONDITIONS37
4.1 52.204-14 SERVICE CONTRACT REPORTING REQUIREMENTS (OCT 2016)37
4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB COVERED ENTITIES (DEC 2023)38
4.3 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)40
4.4 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984)41
4.5 52.219-14 LIMITATIONS ON SUBCONTRACTING (OCT 2022)41
4.6 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (FEB 2024)43
4.7 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)47
4.8 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010)47
4.9 52.223-21 FOAMS (MAY 2024)49
4.10 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)49
4.11 SUPPLEMENTAL INSURANCE REQUIREMENTS54
4.12 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)56
4.13 VAAR 852.215-71 EVALUATION FACTOR COMMITMENTS (OCT 2019)56
4.14 VAAR 852.215-70 SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESS EVALUATION FACTORS (JAN 2023) (DEVIATION)57
4.15 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION)57
4.16 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)59
4.17 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)59
4.18 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)59
4.19 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)62
4.20 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)63
4.21 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 2019)64
4.22 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)65
4.23 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)65
4.24 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)66
4.25 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)67
4.26 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)67
4.27 List of Attachments114

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1.00
JB
__________________
__________________

BID ITEM I, GENERAL CONSTRUCTION: Work includes securing the entire perimeter of campus with sections of Historic and Non-Historic fencing with 2 vehicular gates at primary and secondary entrances as well as pedestrian gates at both entrances. Video surveillance and illumination of the perimeter fence/gates are also included in this project. Approximately 6,000 linear feet of 6 foot high chain link fence installed on the western, southern and southeastern perimeters of campus must be removed.

Construction Duration: 365 calendar days.

Final Period of Performance to be determined when Notice to Proceed (NTP) is issued. NTP to be issued at Pre-construction meeting after payment and performance bonds are received.

PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Z2DA - Repair or Alteration of Hospitals and Infirmaries

1.00
JB
__________________
__________________

BID ITEM II (DBA NO.1): All the work in Bid Item I above except REPLACE ALL BLACK COATED VINYL STEEL NON-HISTORIC FENCE WITH NON-COATED GALVANIZED STEEL FENCE.

Construction Duration: 365 calendar days.

Final Period of Performance to be determined when Notice to Proceed (NTP) is issued. NTP to be issued at Pre-construction meeting after payment and performance bonds are received.

1.00
JB
__________________
__________________

BID ITEM III (DBA NO.2): All the work in Bid Item II above except REPLACE PORTION OF HISTORIC FENCE WITH NON-HISTORIC FENCE ON THE NORTH SOUTH SEGMENT OF FENCE EAST OF BUILDING 81. SEE

DRAWING CI-100.

Construction Duration: 365 calendar days.

Final Period of Performance to be determined when Notice to Proceed (NTP) is issued. NTP to be issued at Pre-construction meeting after payment and performance bonds are received.

1.00
JB
__________________
__________________

BID ITEM IV (DBA NO.3): All the work in Bid Item III above except REPLACE SPECIFIED HISTORIC FENCE PICKETS 2 ¾”x1”x .078” WITH 2 ¾”x 3/4”x .078” PICKETS.

Final Period of Performance to be determined when Notice to Proceed (NTP) is issued. NTP to be issued at Pre-construction meeting after payment and performance bonds are received.

1.00
JB
__________________
__________________

BID ITEM V (DBA NO.4): All the work in Bid Item IV above except REMOVE ALL TRENCHING, UNDERGROUND CONDUIT BANKS, EQUIPMENT, DEVICES, AND ALL CONDUCTORS SOUTH OF PULLBOXES LOCATED EAST OF BUILDING 15. SEE DRAWINGS TY-100, TY102, ES-100, AND ES103.

Construction Duration: 365 calendar days.

Final Period of Performance to be determined when Notice to Proceed (NTP) is issued. NTP to be issued at Pre-construction meeting after payment and performance bonds are received.

1.00
JB
__________________
__________________

BID ITEM VI (DBA NO.5): All the work in Bid Item IV above except REMOVE ROLLERS FROM ALL NONHISTORIC FENCE.

Final Period of Performance to be determined when Notice to Proceed (NTP) is issued. NTP to be issued at Pre-construction meeting after payment and performance bonds are received

1.00
JB
__________________
__________________

BID ITEM VII (DBA NO.6): All the work in Bid Item IV above except REMOVE ALL WORK ASSOCIATED WITH NON-HISTORIC FENCE ON THE EAST SIDE OF THE CAMPUS. SEE DRAWING CI-100.

Final Period of Performance to be determined when Notice to Proceed (NTP) is issued. NTP to be issued at Pre-construction meeting after payment and performance bonds are received.

GRAND TOTAL
__________________

A.4 STATEMENT OF WORK

Construct Campus Perimeter Barrier for Physical Security Marion VA Medical Center ‐ VISN 15 ‐ Marion, IL VA Project No. 657A5‐23‐114 Statement of Work:

The subject project includes tasking to remove, replace and expand the existing perimeter fence with multiple VA Physical Security compliant fencing solutions at the Marion, IL VAMC campus. Tasking also includes installation and integration of lighting and surveillance equipment, installation of vehicular and pedestrian gates (2 each) and necessary electrical infrastructure to accommodate security equipment requirements.

Currently, there is approximately 6,000 linear feet of 6‐foot‐high chain link fence installed on the western, southern, and southeastern perimeters of campus. The northern and northeastern boundaries of campus do not possess a barrier of any kind.

This is a multi‐phased project requiring detailed coordination with the assigned Contracting Officer’s Representative (COR) and VA staff to effectively retain the integrity of campus security during construction. Coordination will also be necessary to effectively complete all tasking within the project duration indicated.

The contractor shall provide all labor, materials, equipment, and expertise necessary to meet the requirements described in the construction documents. All work will be performed in accordance with the SOW, all local, state, and federal codes, the approved construction documentation, manufacturer specifications and all VA requirements.

Performance Period:

The contractor shall complete the work required in this Statement of Work (SOW) within three hundred and sixty‐five (365) calendar days from Notice to Proceed (NTP), unless otherwise directed by the Contracting Officer. If the contractor proposes an earlier completion date, and the Government accepts the contractor’s proposal, the contractor’s proposed completion date shall prevail. Work is to be performed during normal working hours (7:00 am to 4:30 pm, Monday‐Friday) unless otherwise stated or required. Work at the government site shall not take place on Federal holidays unless directed by the Contracting Officer. General Contractor’s employees shall not enter the project site without an appropriate badge.

Page 1 of Page 1 of

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

1.1 INSTRUCTIONS TO OFFERORS

PROPOSAL SUBMITTAL INSTRUCTIONS

FOR LOWEST PRICE TECHNICALLY ACCEPTABLE (LPTA) SOURCE SELECTION PROCESS

SOLICITATION: 36C25524R0105

PROJECT: Construct Campus Perimeter Barrier for Physical Security, Project # 657A5-23-114 LOCATION: Marion VA Medical Center, Illinois

1. PREPARATION AND SUBMITTAL OF PROPOSALS

a. GENERAL INFORMATION.

Selection of an offeror for contract award will be made on the basis of an assessment of each offeror’s response to the Request for Proposal (RFP). As a Request for Proposal (RFP) based on Lowest Price Technically Acceptable (LPTA) Source Selection Process, in accordance with Federal Acquisition Regulation (FAR) Part 15.101-2, the VA will make the award based on the lowest evaluated price of proposals meeting or exceeding the acceptability standards for non-price factors. The five (5) evaluation factors for determination of technical acceptability consist of:

1. Relevant Construction Experience of the Prime Contractor (Non-Price)

2. Project Execution (Non-Price)

3. Technical Qualifications and Experience of Proposed Staffing (Non-Price)

4. Past Performance (Non-Price)

5. Prime Contractor’s Safety Plan (Non-Price)

NOTE: Failure to comply with the RFP requirements may be grounds to eliminate the proposal from further consideration for contract award. A rating of Unacceptable for any factor makes the offeror ineligible for award.

b. THE OFFER.

The submission of the documentation specified below will constitute the Offeror’s acceptance of the terms and conditions of the RFP, including the Plans & Specifications for the construction of this project. These instructions prescribe the format for the proposal and describe the approach for the development and presentation of proposal data. These instructions are designed to ensure the submission of necessary information to provide for the understanding and comprehensive evaluation of proposals.

c. AWARD BASED ON INITIAL OFFERS.

Pursuant to clause 52.215-1 (included by reference), the Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a price, and technical qualifications standpoint. The VA reserves the right to conduct discussions if the Contracting Officer later determines such discussions to be necessary.

d. NUMBER OF COPIES TO SUBMIT. OFFERORS WILL BE REQUIRED TO ELECTRONICALLY SUBMIT PROPOSAL BY EMAIL TO THE CONTRACTING OFFICER, MARIA HOOVER. Documents must be submitted as pdf attachments to the email.

Contracting Officer email: maria.hoover@va.gov (CONTRACTOR WILL BE REQUIRED TO VERIFY THAT THE EMAIL HAS BEEN RECEIVED WITH ATTACHED PROPOSAL DOCUMENTS BY THE CONTRACTING OFFICER AT 913-946-1127.)

Submit one pdf document for Volume 1 Technical Proposal , One pdf document for Volume 2 Price Proposal and one pdf document for Volume 3 Bid Bond.

Marked: ORIGINAL - RESPONSE TO RFP – 36C25524R0105 Project # 657A5-23-114, Construct Campus Perimeter Barrier for Physical Security These documents are to contain the signed original copy of the documents listed below;

2. DOCUMENTS TO SUBMIT.

The original documents to be included in the document identified above consist of:

a.VOLUME 1-STANDARD FORM 1442. Submit the SF 1442 issued under this solicitation, with Blocks 10 (DUNS Number) and Blocks 14 through 20 properly filled-out by the Offeror. Include acknowledgment of any and all Amendments that may have been issued, either by: (1) listing them in Block 19 of the SF 1442, or (2) including copies of the Amendment document(s) (Standard Form 30) with Blocks 8 and 15 filled in and signed, or (3) including signed acknowledgement in the form of a separate letter that includes a reference to the solicitation and amendment numbers. NOTE: Failure to acknowledge any and all Amendments issued pursuant to this solicitation may be cause for rejection of your offer.
b.VOLUME 2-PRICE PROPOSAL. Appendix 1- Price Breakdown Calculation of Self Performed and Subcontracted work for each bid item shall be included in volume 2. Appendix 2- Safety or Environmental Violation and Experience Modification Rate document shall be included in volume 2.
c.VOLUME 3-OFFER GUARANTEE (BID BOND). In accordance with solicitation provision 52.228-1, Bid Guarantee, failure to furnish a bid guarantee, in the proper form and amount, by the deadline established for submitting offers, may be cause for rejection of the offer.
d.DOCUMENTATION OF TECHNICAL ACCEPTABILITY. Proposals received in response to this solicitation will be evaluated in accordance with procedures outlined in Federal Acquisition Regulations (FAR) Part 15.101-2 for the Lowest Price Technically Acceptable (LPTA) Offer.

The following significant Evaluation Factors will be used as the basis for determining Technical Acceptability:

1. Relevant Construction Experience of the Prime Contractor (Non-Price)

2. Project Execution (Non-Price)

3. Technical Qualifications and Experience of Proposed Staffing (Non-Price)

4. Past Performance (Non-Price)

5. Prime Contractor’s Safety Plan (Non-Price)

NOTE: There is a realistic possibility that some offerors may choose to submit the same construction project as a qualifying example for both the past performance and the technical experience evaluation factors. This is not prohibited, but the supporting documentation must demonstrate that the submitted projects absolutely do comply with the specific minimal requirements, identified below, for each separate evaluation factor.

FACTOR 1: RELEVANT CONSTRUCTION EXPERIENCE OF PRIME CONTRACTOR.

To be evaluated under this factor, Offerors shall submit a minimum of two (2) and maximum of five (5) construction project examples for the Prime Contractor that best demonstrates recent and relevant experience by the Prime Contractor on projects that are similar in size, scope, and complexity to the RFP requirements. Subcontractor work cannot be substituted and shall not be accepted. The projects must demonstrate an Offeror’s construction experience as a prime construction contractor directly responsible to the project owner and managing multiple subcontractors.

The offeror shall provide a short description of the project and state what work fulfilled the relevant experience areas for construction of new buildings including but not limited to: modification and relocation of the site utilities, new building construction and additions to existing buildings, modifications to existing utilities, physical security construction, storm drain and sewer updates, phased construction, fire alarm and sprinkler system updates with integration into existing systems, updating of controls and auxiliary systems, updating communications, and electrical service to multiple hospital or commercial buildings.

Project(s) shall have a minimum value of $2,000,000.00.

Projects submitted by the Offeror shall be completed within the past five (5) years from the date of issuance of this RFP. If the contract/work is incomplete or was completed more than five years prior to the date of submitting this proposal, it will not be deemed relevant and shall not be considered. Projects which are similar in size, scope, and complexity and were at an active Hospital, Medical Center, or project site with 24-hour day operations are preferred and will be rated higher.

A project is defined as a construction project performed under a single task order or contract. For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project; rather Offerors shall submit the work performed under a task order as a project.

Offeror’s submission should include at a minimum:

· Provide the Project Title and Description, Project Location (Physical Address); Contract Type (Example: Design Build, Design Bid Build).

· Provide the project owner name, and telephone number and email of the owner’s contact person.

· Provide a description of the scope of work, to include the work performed by the prime contractor. Scope of work includes information on subcontractors managed during the project.

· Provide project statistics that include start and completion dates (original and actual) and project cost (original and actual). If original and actual completion dates and project cost differ, provide an explanation as to why they differ.

If the Offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the Joint Venture entity. If the Joint Venture does not have shared experience, projects shall be submitted for each Joint Venture partner. Offerors who fail to submit experience for all Joint Venture partners may be rated lower.

(Note: Proposals submitted by teaming arrangements other than VA SDVOSB Joint Ventures will not be considered.)

FACTOR 2: PROJECT EXECUTION.

To be evaluated under this factor, offerors must:

Provide a Draft Project Schedule:

Prepare and submit a practicable construction schedule showing all necessary work elements to complete the project identified under this solicitation within the time frame specified on the SF1442. The schedule must be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the performance period. The submitted schedule must be developed using project scheduling software such as MS Project, Primavera, or any other comparable form.

Each Offeror's construction schedule must address the following:

· Order of work elements to include project phasing, Submittals, Mobilization, Demolition, Construction, Equipment Deliveries and Lead Time, Installation of new Equipment, Punch List, De-Mobilization.

· Number of days for each work element

· Identification of long lead time materials

· Identification of separate work elements

· The VA’s review and approval of RFI’s, Submittals and other pertinent documents.

· Interruption of VA Facilities utilities, delivery of Government furnished equipment, rough-in drawings, project phasing and any other specification requirements.

The proposed schedule must include the activities which are consistent with those described within the project specifications and drawings and must not exceed the Government's maximum allowable performance period, as noted in Block 11 of the SF 1442. The project will start at the issuance of the Notice to Proceed. For scheduling purposes, assume the Notice to Proceed will be issued less than fifteen (15) calendar days after the award date. (Note that there is no guarantee the Notice to Proceed will be issued within this timeframe.)

*The schedule submitted with the offer shall not be construed as the agreed upon schedule as per FAR 52.236-15. The awarded contractor shall, within five (5) days after receiving the Notice to Proceed, submit a revised schedule which will supersede the proposed schedule. The revised schedule will be subject to VA approval and must show the project being accomplished within the time frame specified on the SF 1442.

Provide Narrative for Project Challenges:

Describe in a written narrative, the challenges identified for this project and a plan for addressing these challenges. This plan shall include contractor’s plan to minimize the disruption of patient care to the greatest extent possible.

FACTOR 3. TECHNICAL QUALIFICATIONS OF PROPOSED STAFFING.

To be evaluated under this factor, qualified offerors must submit a detailed resume of each key individual on the Prime contractor’s staff for his project. To promote maximum continuity on this project, key staffing positions must not to be subcontracted out. This factor will be evaluated to determine if contractor’s key personnel have the appropriate technical training and or previous construction experience to meet the technical requirements of the key staffing positions for a project of this nature.

Note: No one individual can perform more than two of the key staffing positions below. The project manager and superintendent cannot be the same person. If references cannot be verified for any of the key personnel you identify, then Factor 3 will receive a rating that is less than acceptable (i.e., marginal if one reference can’t be verified and unacceptable if more than one reference can’t be verified). It is the offeror’s responsibility to make sure the references provided know that they may be contacted by VA for a reference and that if the reference doesn’t timely respond to VA, that it may have an adverse impact on the offeror’s rating under this factor.

a) Project Manager – Must have a minimum of 5 years of experience as a project manager must provide a minimum of 3 projects with similar scope to this project. Provide the name of the construction contract, and the contract ID number; The name of the contracting agency or organization the contract was awarded by; The date of the construction contract award and the contract award amount in dollars; The date of the construction contract completion, and the final contract amount, in dollars; A brief description of the construction contract scope of work; Identification of at least one point-of-contact at the organization that awarded the submitted contract, including: the name of the point-of-contact; their current mailing address; phone number; and email address (if applicable). Project Manager will be required to attend weekly project meetings in person at the station facilities office. If references cannot be verified, then Factor 3 will receive a rating less than acceptable.

(b) On-Site Superintendent – Must have a minimum of 5 years of experience as a site superintendent and must have OSHA 30 training (Must provide certificate). Provide at least 3 projects as a site superintendent with similar scope of this project. Provide the name of the construction contract, and the contract ID number; The name of the contracting agency or organization the contract was awarded by; The date of the construction contract award and the contract award amount in dollars; The date of the construction contract completion, and the final contract amount, in dollars; A brief description of the construction contract scope of work; and Identification of at least one point-of-contact at the organization that awarded the submitted contract, including: the name of the point-of-contact; their current mailing address; phone number; and email address (if applicable). Superintendent will be required to attend weekly project meetings in person at the station facilities office.

If references cannot be verified, then Factor 3 will receive a rating less than acceptable.

(c) Quality Control Manager – Must have a minimum of 5 years of experience as a project manager. Provide a minimum of 2 projects with similar scope of this project that they have acted as the QC manager. Provide the name of the construction contract, and the contract ID number; the name of the contracting agency or organization the contract was awarded by; and the date of the construction contract award. A brief description of the construction contract scope of work and the QC program that was implemented.; Identify at least one point-of-contact at the organization that awarded the submitted contract, including: the name of the point-of-contact; their current mailing address; phone number; and email address (if applicable).

To be considered for evaluation, the 2 projects must have been performed within the last five years and valid contact information must be provided.

If references cannot be verified, then Factor 3 will receive a rating less than acceptable.

(d) Safety Officer – Must have a minimum of 5 years of experience as a safety Officer Must provide an OSHA 30 Certificate and a list of safety training that at a minimum includes “life safety, excavation safety, scaffold safety, fall protection training, crane/rigging safety”. Provide references (that can be contacted) for a minimum of 2 projects with similar scope to this project. Provide the name of the construction contract, and the contract ID number; The name of the contracting agency or organization the contract was awarded by; Provide a brief description of the construction contract scope of work and how the safety program was implemented; Identify at least one point-of-contact at the organization that awarded the submitted contract, including: the name of the point-of-contact; their current mailing address; phone number; and email address (if applicable).

To be considered for evaluation the 2 projects must have been performed within the last five years and valid contact information must be provided.

If references cannot be verified, then Factor 3 will receive a rating less than acceptable.

Special Note 1: Only submit information for personnel that will perform on a resulting contract. Any substitutions after award must be determined equally or more qualified by the Contracting Officer.

Special Note 2: During the period of performance of the Contract, the Contractor shall make NO substitutions of the Staffing unless the substitution is necessitated by illness, death, or termination of employment. The contractor shall notify the contracting officer and Contracting Officer’s Representative (COR), in writing within five (5) calendar days after the occurrence of any of these events. Any replacement of Staffing shall have equal or better qualifications, subject to the approval by the contracting officer.

FACTOR 4: PAST PERFORMANCE

To be evaluated under this factor, Prime Contractor shall provide current and relevant information regarding the Prime Contractor’s actions under previously awarded contracts referenced under Factor 1, “RELEVANT EXPERIENCE OF THE PRIME CONTRACTOR”. If a completed past performance evaluation is available in CPARS, it shall be submitted with the proposal for each project referenced in Factor 1, “RELEVANT EXPERIENCE OF THE PRIME CONTRACTOR”. If there is not a completed past performance evaluation available in CPARS, then the Prime Contractor shall submit Past Performance Questionnaires (PPQ) (reference ATTACHMENT 5) for each project referenced in Factor 1, Construction Experience. The Prime Contractor shall notify their client/reference that the PPQ shall be submitted by the reference via email to the Government’s point of contact maria.hoover@va.gov. If the Prime Contractor is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Prime Contractor shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information. However, Offerors should follow-up with clients/references to help ensure timely submittal of questionnaires.

The Government reserves the right to contact references for verification or additional information.

SPECIAL NOTE 1: For Prime Contractors That May Lack Past Performance Information: In accordance with FAR Part 15.305(a)(2), in the case of a Prime Contractor that is without a record of relevant past performance, or for whom information on past performance is not available, the offeror may not be evaluated favorably or unfavorably on past performance. Such offerors may submit relevant past performance information regarding: predecessor companies; key personnel who have relevant experience; or subcontractors that will be performing major or critical aspects of this requirement; provided that such information is relevant to the construction in this solicitation.

SPECIAL NOTE 2: For Prime Contractors that have Past Performance: Prime Contractors may provide information on problems encountered on the identified contracts and the offeror’s corrective actions. The government also reserves the right to consider past performance information from all available sources, in addition to any information submitted by offerors.

FACTOR 5: PRIME CONTRACTOR SAFETY PLAN

To be evaluated under this factor, the Prime Contractor shall provide a construction safety plan that is deemed acceptable, at a minimum, and meets the following requirements:

a. The contractor's Safety Plan shall be evaluated for their compliance with local/State/Federal rules and regulations and the company's consideration of safety of its employees and the general public. The contractor's Safety Plan at the minimum shall address their safety policy, commitment to safety, detailed disciplinary action to be taken with respect to employees violating safety requirements, personnel safety responsibilities, personnel safety training, personal protective equipment, accident / incident reporting procedure and investigations, emergency procedures guidelines.

b. The contractor’s Safety Plan shall address their plan for completing all contract work on and around an active hospital without impacting patient care and completing all work in accordance with all construction documents and all local/State/Federal rules and regulations.

If the safety plan does not address the requirements listed above (a and b), the proposal will be deemed unacceptable and not receive further consideration for award.

e.PRICE PROPOSAL.
Price is to be submitted in Volume 2. Offerors must provide a price that is fair and reasonable for all bid items. In addition, offerors shall include a breakdown of material and labor costs, by specification division for the bid items. Overhead, profit and bond costs shall be added after a subtotal of materials and labor costs has been calculated, see Appendix 1. Your proposal will be rejected if there is not an Appendix 1 for all bid items in the proposal package submitted.

3. BASIS OF AWARD.

VA will make the award based on the lowest evaluated price of proposals meeting or exceeding the acceptability standards for non-price factors. Note that the offers which are not technically acceptable cannot be selected, regardless of price.

4. SPECIAL CONTRACT REQUIREMENTS.

A. SUBSTITUTIONS OF SUBCONTRACTORS AND / OR KEY PERSONNEL

(1) When an offeror submits its proposal in response to this Request for Proposals, and key personnel who are proposed to work on the project are required to be submitted, those personnel who are offered must be the same personnel who will actually perform on the project. If, during performance of the contract, it becomes necessary for the contractor to substitute personnel for one of those whose qualifications were the basis for evaluation of the offer and award of the contract, the contractor shall submit to the Contracting Officer the same information that was required in the initial proposal regarding the proposed substitute employee. The Contracting Officer shall have the right to review the qualifications of the proposed substitute employee and to approve or disapprove his or her qualifications. If the proposed substitute employee's qualifications are disapproved by the Contracting Officer, the contractor will propose another employee who does possess equivalent qualifications.

(2). When an offeror submits its proposal in response to this Request for Proposals, and the name and experience of a specific subcontractor is a required evaluation factor, then that subcontractor who is offered must be the same subcontractor who will actually perform the specified work on the project. If, during performance of the contract, it becomes necessary for the contractor to substitute a subcontractor for one of those whose qualifications were the basis for evaluation of the offer and award of the contract, the contractor shall submit to the Contracting Officer the same information that was required in the initial proposal regarding the proposed substitute subcontractor. The Contracting Officer shall have the right to review the qualifications of the proposed substitute subcontractor and to approve or disapprove its qualifications. If the proposed substitute subcontractor's qualifications are disapproved by the Contracting Officer, the contractor will propose another subcontractor who does possess equivalent qualifications.

5. PRIME CONTRACTOR SAFETY OR ENVIRONMENTAL VIOLATIONS AND EXPERIENCE MODIFICATION RATE

1.) All Bidders/Offerors shall submit the required information pertaining to their past Safety and Environmental record, see Appendix 2. The information shall contain, at a minimum, a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.

2.) All Bidders/Offerors shall submit information documenting that their current Experience Modification Rate (EMR) is equal to or less than 1.0. This information shall be obtained from the bidder’s/offeror’s insurance company and be furnished on the insurance carrier’s letterhead. Bidders/Offerors with an EMR greater than 1.0 will be considered “Unacceptable” Failure to affirm being within these guidelines or submit this information will result in a determination of unacceptability and the Bidder/Offeror will be ineligible for award.

3.) Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state-run worker’s compensation insurance rating bureau.

This requirement is applicable to all subcontracting tiers. Prospective prime contractors are responsible for determining the acceptability/compliance of their prospective subcontractors related to the EMR requirements of this solicitation.

END OF PROPOSAL SUBMITTAL INSTRUCTIONS.

PRICE BREAKDOWN AND CALCULATION OF SELF-PERFORMED/SUBCONTRACTED WORK - Appendix 1

Offerors for General Construction (NAICS code 236220) must provide at least 15 percent (25% for NAICS codes 238210 & 238220) of the cost of the contract performance incurred for personnel will be spent on the concern's employees or the employees of other eligible service-disabled veteran owned-small business concerns. Provide a breakdown of material and personnel costs, by specification division listed for the project. Home Office overhead, profit/fee and bond costs shall be added after a subtotal of personnel and material/Equipment costs has been calculated. Clearly identify the personnel costs you will be performing, and the personnel costs of other eligible service-disabled veteran owned-small business concerns. Below is the required format.

(THIS DOCUMENT MUST BE COMPLETED FOR EACH BID ITEM.)

Specification Division
SDVOSB Vendor (Y or N)
Personnel Cost
Material/Equipment Costs
TOTAL COSTS

Division 01

$
$

Division 02

$
$

Division 03

$
$

Division 05

$
$

Division 06

$
$

Division 07

$
$

Division 08

$
$

Division 09

$
$

Division 10

$
$

Division 11

$
$

Division 14

$
$

Division 21

$
$

Division 22

$
$

Division 23

$
$

Division 26

$
$

Division 27

$
$

Division 28

$
$
$
$
Sub Total (Personnel Costs, Material/Equipment Costs)
$
$
Profit
$
Home Office Overhead
$
Bond
$
Grand Total
$

Calculation of self-performed personnel costs:

1. Total personnel costs ** both prime and all subcontractors: $________________

2. Subtract all subcontractor personnel costs** that are not SDVOSB companies that will perform work on this contract: $________________

3. Remainder is ‘Total amount of work to be self-performed under the Contract’: $________________

4. Self-performed work = Line 3/Line 1 x 100 = __________%

I certify the above representations are true and correct to the best of my knowledge.

___Signature____________________________________________
(Typed Name of Authorized Representative)Date

(Title of Authorized Representative)

APPENDIX 2 - Pre-Award Contractor Safety and Environmental Record Evaluation Form

Information provided below is current and applicable to Solicitation 36C25524R0105:

Company Name: ______________________________________________ Address: _____________________________________________________ Telephone: ______________________ Fax: ________________________ Email: _______________________________________________________ Contact: ______________________________________________________

1. Utilizing your OSHA 300 Forms, please complete the following information:

Category
2021
2022
2023
2024

Number of man hours (jobsite and office).

Number of cases involving days away from work, restricted activity, or both (Column H and I of OSHA 300).

Days away, restricted, or transferred rate (# of days away, restricted, or transferred cases x 200,000/# of man hours) (DART Rate).

Number of serious, willful, or repeat violations from OSHA within the last 3 years. Please attach explanation for any violations.

Please attach copies of the following documents: OSHA 300 and 300a Forms. These forms can be accessed through the OSHA publications search page: http://www.osha.gov/pls/publications/publication.html.

2. Provide six-digit North American Industrial Classification System (NAICS) Code for this acquisition: __________________________________

3. Who administers your company’s Safety and Health Program? ____________________________

4. Company’s Insurance Experience Modification Rate (EMR): ____________________________

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

FAR Number
Title
Date
52.204-7
SYSTEM FOR AWARD MANAGEMENT
OCT 2018
52.204-16
COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING
AUG 2020
52.204-22
ALTERNATIVE LINE ITEM PROPOSAL
JAN 2017
52.215-1
INSTRUCTIONS TO OFFERORS—COMPETITIVE ACQUISITION
NOV 2021

2.1 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

FAR Number
Title
Date
52.222-23
NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION
FEB 1999

2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of…