This is a Request for Quote (RFQ) solicitation for boiler retubing services at the VA Illiana Health Care System in Danville, Illinois. The Department of Veterans Affairs, through the Great Lakes Acquisition Center, is seeking qualified contractors to completely re-tube nine fire tube boilers: two Cleaver Brooks 4WG-200-150-15ST models, one 4WG-200-125-15ST model, and six 4WG-200-100-15ST models. All repairs and materials must meet or exceed original specifications, with any proposed substitutions requiring written COR approval and documented comparison analysis. The contract is a firm fixed-price award with a base period of performance from June 1, 2026, through September 30, 2026, with work to commence no later than 30 days from award and completion required within 90 days of award. Quotes are due by May 21, 2026, at 6:00 AM CDT via email to derrick.paquette@va.gov, with a mandatory site visit scheduled for May 11, 2026, at 1:00 PM local time and a questions deadline of May 13, 2026, at noon.
The solicitation is a 100 percent small business set-aside under FAR Part 12 Acquisition of Commercial Items procedures, with the principal NAICS code 238220 (Plumbing, Heating, and Air-Conditioning Contractors) and a size standard of $19 million. Service Contract Labor Standards apply per Wage Determination 2015-5021, Revision 28, with specified wage rates for HVAC mechanics, laborers, and welders. Offerors must demonstrate technical capability through welder qualifications and welding details, provide three years of relevant experience, submit proof of current liability insurance, and evidence of ASME R-stamp certified technicians. Key requirements include developing a comprehensive work plan with safety and schedule details, performing chemical cleaning and hydrostatic testing per manufacturer specifications, ensuring N+1 boiler availability during work, completing all reconnection and disconnection activities, recommissioning boilers for operation on natural gas and fuel oil, and providing a five-year warranty on all welds and rolled seals. Contractors must comply with facility requirements including on-site policies, security screening (Special Agreement Check background investigation), VHA influenza vaccination or masking directives, OSHA regulations including confined space entry, proper waste disposal, and daily site cleanup. Payment will be made electronically through the Veterans Affairs Financial Services Center via Tungsten Network e-Invoicing, with invoices submitted monthly in arrears within ten days following service delivery.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25226Q0367 0001.docx | DOCX document | |
| S06 - Amendment Attachment.pdf | ||
| S02 - WD 2015-5021 R 28 3.30.26.pdf | ||
| 36C25226Q0367.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PAGE 1 OF
1. REQUISITION NO.
2. CONTRACT NO.
3. AWARD/EFFECTIVE DATE
4. ORDER NO.
5. SOLICITATION NUMBER
6. SOLICITATION ISSUE DATE
a. NAME
b. TELEPHONE NO. (No Collect Calls)
8. OFFER DUE DATE/LOCAL
TIME
9. ISSUED BY
CODE
10. THIS ACQUISITION IS
UNRESTRICTED OR
SET ASIDE:
% FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
8(A)
NAICS:
SIZE STANDARD:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
RFQ
IFB
RFP
15. DELIVER TO
CODE
16. ADMINISTERED BY
CODE
17a. CONTRACTOR/OFFEROR
CODE
FACILITY CODE
18a. PAYMENT WILL BE MADE BY
CODE
TELEPHONE NO.
UEI:
EFT:
PHONE:
FAX:
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED
SEE ADDENDUM
19.
20.
21.
22.
23.
24.
ITEM NO.
SCHEDULE OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only) 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________
29. AWARD OF CONTRACT: REF. ___________________________________ OFFER
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
DATED ________________________________. YOUR OFFER ON SOLICITATION
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) 30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
(REV. NOV 2021)
PREVIOUS EDITION IS NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.212
7. FOR SOLICITATION
INFORMATION CALL:
STANDARD FORM 1449
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
36C25226Q0367
Derrick Paquette 414-844-4800 05-21-2026
6:00 AM
CDT
Department of Veterans Affairs 36C252 115 South 84th Street, Suite 101
Milwaukee WI 53214-1476
X
238220 $19 Million
N/A
Department of Veterans Affairs VA Illiana Health Care System 1900 E. Main St.
Danville, IL 61832-5100
36C252 Great Lakes Acquisition Center - HC 115 South 84th Street, Suite 101 Milwaukee WI 53214-1476
Financial Services Center PO Box 149971 Austin TX 78714-9971
See CONTINUATION Page Boiler Retubing Services for the Danville VAMC in Danville, IL.
Service Contract Labor Standards Apply:
Wage Determination: 2015-5021 revision 28 dated 03/30/2026
Contracting Point of Contact: Derrick Paquette derrick.paquette@va.gov
See CONTINUATION Page
ONE
Derrick Paquette
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA (continuation from Standard Form 1449)
OFFERORS MUST COMPLETE AND RETURN ALL INFORMATION DESIGNATED HEREIN PRIOR TO THE TIME SPECIFIED IN BLOCK 8 OF SF 1449 IN ORDER TO BE CONSIDERED FOR AWARD.
ACKNOWLEDGMENT OF AMENDMENTS: The offeror acknowledges receipt of amendments to the Solicitation numbered and dated as follows:
| AMENDMENT NO | DATE | |
| ______________________________ | __________________________ | |
| ______________________________ | __________________________ | |
| ______________________________ | __________________________ |
1. CONTRACT ADMINISTRATION: All contract administration matters will be handled by the following individuals:
a. CONTRACTOR:
CONTRACTOR NAME _____________________________________
ADDRESS ________________________________________________
CITY-STATE-ZIP __________________________________________
POINT OF CONTACT/TITLE ________________________________
| PHONE NUMBER | ______________________________________ |
| FAX NUMBER | ______________________________________ |
| E-MAIL ADDRESS | ______________________________________ |
SAM UEI NO. ____________________________________________
CAGE CODE _____________________________________________
CONTRACTOR’S PAST PERFORMANCE POINT OF CONTACT
(IF DIFFERENT THAN ABOVE):
NAME: __________________________________________
EMAIL ADDRESS: _________________________________
b. GOVERNMENT:
CONTRACTING OFFICE CODE: 36C252
| DEPARTMENT OF VETERANS AFFAIRS |
| GREAT LAKES ACQUISITION CENTER |
| 115 S. 84TH ST., STE 100 |
MILWAUKEE WI 53214
2. ACQUISITION OF COMMERCIAL ITEMS:
This Request for Quote (RFQ) solicitation is issued under the authority of FAR Part 12 Acquisition of Commercial Items and FAR Part 13 Simplified Acquisition Procedures. FAR Part 15 will not be used. The procedures in Part 12 used in conjunction with Part 13 allow the Government to procure services resembling those in the commercial marketplace and streamline the procurement process. From this RFQ, the Government intends to award a firm fixed price contract where the contractor provides a price that is not subject to any adjustment on the basis of the contractor’s cost experience in performing the contract. (Note: The terms “offeror” and “quoter” are both used in this Solicitation. For the purposes of this Solicitation, these terms are interchangeable; there is no difference in meaning between the two.)
3. SET-ASIDE (If any): See box 10 of STANDARD FORM 1449
4. SOLICITATION TIMELINE SUMMARY:
A. SITE VISIT:
It is strongly suggested and expected that the offeror inspect the campus to be serviced to fully understand the nature of the work and the conditions under which the work is to be performed. In no case shall failure to inspect the campus constitute grounds for a claim after contract award.
Site Visit is scheduled for Monday May 11, 2026, at 1:00 PM Local time. All interested parties to meet COR Michael Miller (217) 799-0287. Proceed to Bldg. 102 police service to get a visitor badge then meet at Bldg. 64/72 RM 1B-72.
B. RFQ QUESTIONS:
In order to maintain integrity of this solicitation and subsequent award date, all offerors are advised that any question and answer requests must be submitted in a written form via e-mail to the Contracting Officer derrick.paquette@va.gov no later than Wednesday May 13th, at noon local time. Contracting will issue a consolidated response via solicitation amendment to https://sam.gov Contract Opportunities within 2 business days to all parties
C. SOLICITATION CLOSES/QUOTES DUE:
See box 8 of STANDARD FORM 1449 or most recent Amendment.
D. SUBMISSION OF QUOTE:
See 52.212-1 Instructions to Offerors—Commercial Products and Commercial Services and addendum for specific instructions to offerors.
5. CONTRACTING OFFICER AUTHORITY:
The Contracting Officer is the only person authorized to approve changes or modify any of the requirements under this contract. The Contractor shall communicate with the Contracting Officer on all matters pertaining to contract administration. Only the Contracting Officer is authorized to make commitment or issue changes that will affect price, quantity or quality of performance of this contract. In the event the Contractor effects any such change at the direction of any person other than the Contracting Officer, the change shall be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in cost incurred thereof.
6. INVOICES:
a. All payments by the Government to the contractor will be made in accordance with: FAR 52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER – SYSTEM FOR AWARD MANAGEMENT (OCT 2018)
b. Invoices shall be submitted monthly in arrears in accordance with: 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)
c. Payments shall be made in arrears upon receipt of a properly prepared invoice
d. Facsimile, e-mail, and scanned documents are not acceptable forms of submission for payment requests.
e. The VA has mandated electronic invoice submission to the Veterans Affairs Financial Services Center (VAFSC). VAFSC has partnered with Tungsten Network e-Invoicing network, for submissions of all electronic invoices to VA. Tungsten Network electronic invoicing is free to all VA vendors. In order to submit electronic invoices, all VA vendors must register with Tungsten Network by submitting an email to VA.Registration@Tungsten-Network.com or calling 1-877-489-6135 for Enrollment.
f. Contractor shall submit an electronic invoice by the tenth (10th) of the following month services were performed to the Veterans Affairs Financial Services Center (VAFSC) e-Invoice through the website at https://portal.Tungsten-Network.com/Login.aspx. For questions regarding the submission of VA electronic invoices, Tungsten Network customer service may be contacted at 1-877-489-6135.
g. All invoices shall reference the vendor name and address, customer name, contract number, appropriate obligation/funding order number, description of services provided, quantity, unit price, and total invoice amount (any additional info). Invoices shall also include any payment discount terms.
h. VA’s Electronic Invoice Presentment and Payment System – The Veterans Affairs Financial Services Center (VAFSC) uses a third-party contractor, Tungsten Network e-Invoice, to transition vendors from paper to electronic invoice submission. Please go to this website: http://www.tungsten-network.com/customer-campaigns/veteransaffairs/ to begin submitting electronic invoices, free of charge.
i. As of July 1, 2020, the VA10091 form has been eliminated and the VAFSC is requiring our vendors to update and add their information in the Customer Engagement Portal (CEP) at https://www.cep.fsc.va.gov/. This is for new vendors being added to FMS only.
j. For assistance setting up e-Invoice, the below information is provided:
* Tungsten Network e-Invoice Setup Information: 1-877-489-6135
* Tungsten Network e-Invoice email: VA.Registration@Tungsten-Network.com
* FSC e-Invoice Contact Information: 1-877-353-9791
* FSC e-invoice email: vafsccshd@va.gov
7. FACILITY REQUIREMENTS: In addition to any other requirements set forth in this Contract, the Contractor, including its employees, agents, and subcontractors (collectively “the Contractor”), shall comply with the following facility requirements. Failure to comply with these requirements shall be considered a material breach of this Contract and may be a violation of Federal law resulting in charges answerable in the United States District Court.
a. Contractor is responsible to follow all on site facility policies
b. All VA property is considered Federal property and all Federal laws are applicable.
c. It is the responsibility of the Contractor to park in the appropriate designated parking areas. Information on parking is available from the VA Police Section. The VA will not invalidate or make reimbursement for parking violations of the Contractor under any conditions.
d. All VA facilities are drug free. Possession of drugs, to include Marijuana and all Marijuana bi-products are prohibited. Enclosed containers, including tool kits, shall be subject to search. Violations of VA regulations may result in citation answerable in the United States (Federal) District Court, not a local district, state, or municipal court.
e. All contractor personnel are required to adhere to all VA rules and regulations.
f. Smoking is prohibited on the entire campus, both inside and outside the VA Facility
g. Possession of weapons is prohibited. Enclosed containers, including tool kits, shall be subject to search. Violations of VA regulations may result in citation answerable in the United States (Federal) District Court, not a local district, state, or municipal court.
h. VHA DIRECTIVE 1192: This Veterans Health Administration (VHA) directive establishes policy and provides guidance for the prevention of seasonal influenza in VHA facilities through the vaccination or masking of health care personnel (HCP). AUTHORITY: Title 38 United States Code (U.S.C.) 7301(b), 7318(b). Contractor is responsible in ensuring that all aspects of this directive are implemented, including providing face masks and influenza vaccines for all employees working at a VA facility.
8. SECURITY & PRIVACY CONTROL:
Contractors, contractor personnel, subcontractors, and subcontractor personnel will be subject to the same federal laws, regulations, standards, VA directives and handbooks, as VA personnel regarding information and information system security and privacy.
Non-PIV Card
Applies to unsupervised, logical and/or physical access for less than 6 months OR less than 180 aggregate days in a one-year period
Defined in VA Directive 0735 as: “Non-PIV Credential: A VA ID card containing a photograph issued to persons who do not require a PIV Credential but need unaccompanied, infrequent access to VA facilities or information systems for a period not to exceed six (6) months.”
All contractor employees are subject to the same level of investigation as VA employees who have access to VA Sensitive Information. The level of background investigation commensurate with the level of access needed to perform in accordance with the statement of work is: Special Agreement Check (SAC). This requirement is applicable to all subcontractor personnel requiring the same access.
A SAC is an automated records check conducted by the Federal Bureau of Investigation in collaboration with the Office of Personnel Management.
9. Records Management:
A. Applicability This clause applies to all Contractors whose employees create, work with, or otherwise handle Federal records, as defined in Section B, regardless of the medium in which the record exists.
B. Definitions “Federal record” as defined in 44 U.S.C. § 3301, includes all recorded information, regardless of form or characteristics, made or received by a Federal agency under Federal law or in connection with the transaction of public business and preserved or appropriate for preservation by that agency or its legitimate successor as evidence of the organization, functions, policies, decisions, procedures, operations, or other activities of the United States Government or because of the informational value of data in them.
The term Federal record:
1. includes [Agency] records;
2. does not include personal materials;
3. applies to records created, received, or maintained by Contractors pursuant to their [Agency] contract;
4. may include deliverables and documentation associated with deliverables.
C. Requirements
1. Contractor shall comply with all applicable records management laws and regulations, as well as National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C. chs. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.
2. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.
3. In accordance with 36 CFR 1222.32, Contractor shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.
4. [Agency] and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of [Agency] or destroyed except for in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting Activity. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, Contractor must report to [Agency]. The agency must report promptly to NARA in accordance with 36 CFR 1230.
5. The Contractor shall immediately notify the appropriate Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records, or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the [contract vehicle]. The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records and/or equipment is properly protected. The Contractor shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government’s behalf, without the express written permission of the Head of the Contracting Activity. When information, data, documentary material, records and/or equipment is no longer required, it shall be returned to [Agency] control or the Contractor must hold it until otherwise directed. Items returned to the Government shall be hand carried, mailed, emailed, or securely electronically transmitted to the Contracting Officer or address prescribed in the [contract vehicle]. Destruction of records is EXPRESSLY PROHIBITED unless in accordance with Paragraph (4).
6. The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, contracts. The Contractor (and any sub-contractor) is required to abide by Government and [Agency] guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.
7. The Contractor shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with [Agency] policy.
8. The Contractor shall not create or maintain any records containing any non-public [Agency] information that are not specifically tied to or authorized by the contract.
9. The Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.
10. The [Agency] owns the rights to all data and records produced as part of this contract. All deliverables under the contract are the property of the U.S. Government for which [Agency] shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest. Any Contractor rights in the data or deliverables must be identified as required by FAR 52.227-11 through FAR 52.227-20.
11. Training. All Contractor employees assigned to this contract who create, work with, or otherwise handle records are required to take [Agency]-provided records management training. The Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training. [Note: To the extent an agency requires contractors to complete records management training, the agency must provide the training to the contractor.] D. Flow down of requirements to subcontractors
1. The Contractor shall incorporate the substance of this clause, its terms and requirements including this paragraph, in all subcontracts under this [contract vehicle], and require written subcontractor acknowledgment of same
2. Violation by a subcontractor of any provision set forth in this clause will be attributed to the Contractor.
B.2 Statement of Work
1. SCOPE OF WORK
The contractor shall provide all personnel, labor, equipment, tools, materials, supervision and any other items and/or services necessary to completely re-tube the 9 boilers. This includes 2 cleaver Brooks 4WG-200-150-15ST fire tube boilers. 1 Cleaver Brooks 4WG-200-125-15ST fire tube boiler. 6 Cleaver Brooks 4WG-200-100-15ST fire tube boilers.
The contractor shall ensure all repairs and materials meet or exceed original specifications. Any changes to the original materials used or recommended changes by the contractor shall be included in the offer with cost and a narrative as to why the changes are required or recommended.
2. PERIOD OF PERFORMANCE
The contractor shall begin work no later than 30 days from the date of award. All work to include all testing and certification to return the boilers to full operation shall be complete no later than 90 days from the date of award.
Tube replacement shall be scheduled in a manner to always maintain N+1 in each plant. Contractor shall only work on one boiler per plant at a time. That boiler will need to be fully operable before beginning work on the next.
3. SPECIFIC REQUIREMENTS
The Contractor shall:
· Develop and submit a work plan including details on materials and methods planned, a safety plan and schedule. This shall include data on welding and tube materials and workers’ qualifications and certifications.
· Disassemble and reassemble boiler accessories, attaching hardware deemed necessary to successfully complete this project.
· The contractor shall be responsible for supplying all equipment, labor, and materials to complete the boil out (chemical cleaning) of the tubes before returning to service, in accordance with manufacturer specifications. In accordance with directions given by the current water treatment representative and environmental engineer at VA Illiana VAMC. The contractor shall be responsible for all connections and disconnections.
· Prepare for pressure testing of the completed work and pressurization for inspection. The contractor shall conduct the hydrostatic test at 1.3 times the Maximum Allowable Working Pressure (MAWP) of the vessel. The contractor shall verify all devices are capable of that pressure or remove them and ensure all outlets and inlets are secured to accommodate the test. Perform a hydrostatic test in accordance with industry standards and verified by VA staff.
· Ensure tube material and thickness shall remain unchanged from what is shown on the original drawings and/or specifications. Substitutions shall be permitted only if approved in writing by the COR and only if the originally specified tube types are no longer available and with the concurrence of a licensed engineer with experience in boiler design or the manufacturers’ approval. The substitution’s quality must be equal to or greater than the original design, and it shall be the contractor's responsibility to provide a side-by-side comparison of tube specifications between the original and proposed substitutions.
· At the completion of this project the boilers shall be recommissioned. To include at a minimum tuning and or putting in air, gas, and oil curves as needed. and demonstrated to be fully operational on both natural gas and fuel oil throughout the firing range.
· The contractor shall set and test all level controls, and boiler safeties, (electrical and mechanical controls that are affected by the project). All The boiler safety devices shall be fully tested per Veterans Health Administration Safety Device Testing Manual (VHA SDTM). Those that were removed during the work shall be reinstalled and tested by qualified technicians.
· The tubes shall be reinstalled in the same fashion as the original design (i.e., rolled or welded). Tubes that are required to be rolled that are damaged during installation shall be removed and replaced. Seal welding is only permitted if required as part of the original design to return the boiler to factory condition. Seal welding that was not part of the original design to address leaks or fit up issues is prohibited.
· Provide all seals, gaskets, nuts & bolts.
· Provide the following proper storage of tubes and other materials from the weather. The contractor may be required to store the new tubes off site and truck in weekly or as needed because of the limited storage area at VA Illiana VAMC. The COR or designee shall have the authority to approve what, if any, materials the Contractor is allowed to store on-site.
· The contractor shall be responsible for returning the boiler to a fully operational state before turning back over to VA Illiana VAMC.
· Warranty all welds and rolls for a term of no less than five (5) years.
· Remove and ensure proper disposal of all materials removed from the boiler retubing. All waste generated because of contractor work is the property of the contractor except items defined as "salvage" by the Government. The contractor is responsible for the removal of their waste and shall not use government owned or controlled equipment to contain, store, or otherwise handle his trash or debris. The contractor shall provide sufficient containers to remove all the waste created by his operations and remove it from the job site as soon as practicable. The contractor is responsible for assuring that all waste from Government work is disposed of only through a facility that has been certified by the appropriate state or local agency for waste management, or by the Environmental Protection Agency.
4. Safety
· Contractor shall provide all safety equipment and systems necessary such as Lock-out/Tag-out (LOTO) of equipment being worked on, protection from weld flash and ventilation in work area.
· The contractor shall provide a roaming fire watch when welding is occurring (30min after hot work has completed.) and the contractor shall be responsible for protecting all equipment, flooring with welding blankets, plywood, fiberboard, or other VA Illiana VAMC approved fire-retardant insulation in the surrounding area/perimeter.
· Daily clean up. The building is an active boiler plant; the contractor shall be responsible for keeping a reasonably clean and free of debris working environment and leaving the area in a broom swept condition at the end of each day.
· The contractor shall ensure the work area has all debris and materials removed and cleaned to match the areas around the other boilers at the end of the project.
· The contractor shall inform employees of the working conditions and the possible safety implications. The contractor shall ensure that employees are trained in and follow all OSHA regulations to include Confined Space Entry for the work environment, and the contractor shall ensure sound engineering methods in the repairs of these areas. It is the responsibility of the contractor to ensure all tools and equipment used to make the repairs meet or surpass all OSHA safety regulations.
5. Hours of Operations
· The Medical Center maintains operations 24 hours a day, 7 days a week. Therefore, any interruption in operations shall be scheduled in advance and coordinated with the COR to ensure that no lapses in operations occur. It is the Contractor’s responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
· The contractor or employees of the contractor shall check in daily with VA Illiana VAMC engineering and maintenance personnel upon arrival at the Central Heating Plant and before any work can begin. The contactor will also check out with VA Illiana VAMC engineering and maintenance once work is completed and before leaving the Central Heating Plant.
· The contractor shall submit a proposed workplan, safety plan and schedule to the VA within 30 days of award. The VA shall have seven (7) calendar days to review after which time the contractor shall have seven (7) calendar days to make corrections to the schedule noted by VA Illiana VA. Schedules should be updated weekly.
· Normal work hours for VA staff are from 7:30 am until 4:00 pm, Monday through Friday. Work outside of normal business hours or weekends is at the discretion of the contractor but shall be approved in advance by the COR.
· Federal Holidays
| New Year’s Day |
| Juneteenth |
| Veterans Day |
| Martin Luther King’s Birthday |
| Independence Day |
| Thanksgiving Day |
| Washington’s Birthday |
| Labor Day |
| Christmas Day |
| Memorial Day |
| Columbus Day |
6. Reporting:
· The contractor shall document all work and reference and quote the code that applies to that repair and certify the repair adheres to said code.
· Complete documentation of the work including at a minimum all mill specifications on new materials welding materials and purchase information, welder’s certifications, testing information and rating
· Tube Data Report/useful life survey shall be obtained through VA Illiana VAMC. However, because of continued maintenance of this boiler and the possibility of modifications not being recorded or documented no drawings obtained from the VA Illiana VAMC shall be considered as “AS BUILT DRAWING" and shall be verified by the contractor. Contractor shall notify Contracting Officer Representative (COR) of any discrepancies.
· The contractor will provide a summary report by both electronic and paper copy to the engineering and maintenance department within one week of the completion of work.
· Contractor shall provide VA Illiana VAMC with documentation of complete boiler tube replacement work electronically within three (3) weeks after completion of project.
8. Compliance
· Contractors shall have technicians that demonstrate familiarity with and ready access to the current versions of the following references: NFPA85, Boiler and Combustion Systems Hazards Code, and VHA Boiler Safety Device Testing Manual [Latest] Edition.
· All work shall comply with the National Board Inspection Codes (NBIC) and ASME Codes (American Society of Mechanical Engineers).
9. TECHNICAL QUALIFICATIONS
· Contractor shall meet or exceed these qualifications at the time of award and throughout the contract period.
· Have staff with experience in boiler repair and ASME R stamp certified. The VAMC facility manager/engineer may define and accept equivalent qualifications.
· Be a current representative/agent of an industrial burner or boiler manufacture.
· The contractor shall provide the VA Illiana VAMC with copies of all R Stamp National Board Certifications for the welders working on this project.
B.3 PRICE SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 2.00 |
| JB |
| __________________ |
| __________________ |
The contractor shall provide all personnel, labor, equipment, tools, materials, supervision and any other items and services necessary to completely re-tube the Cleaver Brooks 4WG-200-150-15ST fire tube boiler as defined in the Statement of Work (SOW).
Contract Period: Base POP Begin: 06-01-2026 POP End: 09-30-2026 PRINCIPAL NAICS CODE: 238220 - Plumbing, Heating, and Air-Conditioning Contractors PRODUCT/SERVICE CODE: J044 - Maintenance, Repair, and Rebuilding of Equipment - Furnace, Steam Plant, and Drying Equipment; Nuclear Reactors
| 1.00 |
| JB |
| __________________ |
| __________________ |
The contractor shall provide all personnel, labor, equipment, tools, materials, supervision and any other items and services necessary to completely re-tube the cleaver Brooks 4WG-200-125-15ST fire tube boiler as defined in the Statement of Work (SOW).
POP Begin: 06-01-2026 POP End: 09-30-2026 PRINCIPAL NAICS CODE: 238220 - Plumbing, Heating, and Air-Conditioning Contractors PRODUCT/SERVICE CODE: J044 - Maintenance, Repair, and Rebuilding of Equipment - Furnace, Steam Plant, and Drying Equipment; Nuclear Reactors
| 6.00 |
| JB |
| __________________ |
| __________________ |
The contractor shall provide all personnel, labor, equipment, tools, materials, supervision and any other items and services necessary to completely re-tube the Cleaver Brooks 4WG-200-100-15ST fire tube boiler as defined in the Statement of Work (SOW).
POP Begin: 06-01-2026 POP End: 09-30-2026 PRINCIPAL NAICS CODE: 238220 - Plumbing, Heating, and Air-Conditioning Contractors PRODUCT/SERVICE CODE: J044 - Maintenance, Repair, and Rebuilding of Equipment - Furnace, Steam Plant, and Drying Equipment; Nuclear Reactors
| GRAND TOTAL |
| __________________ |
SECTION C - CONTRACT CLAUSES
C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2023)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights—
(1) Within a reasonable time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at Federal Acquisition Regulation (FAR) 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(g) Invoice.
(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include—
(i) Name and address of the Contractor;
(ii) Invoice date and number;
(iii) Contract number, line item number and, if applicable, the order number;
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(vi) Terms of any discount for prompt payment offered;
(vii) Name and address of official to whom payment is to be sent;
(viii) Name, title, and phone number of person to notify in event of defective invoice; and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer—Other Than System for Award Management), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payment.—
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.
(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.
(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(6) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if—
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in FAR 32.608-2 in effect on the date of this contract.
(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.
(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.
(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.
(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.
(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.
(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 49 U.S.C. 40118, Fly American; and 41 U.S.C. chapter 21 relating to procurement integrity.
(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:
(1) The schedule of supplies/services.
(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;
(3) The clause at 52.212-5.
(4) Addenda to this solicitation or contract, including any license agreements for computer software.
(5) Solicitation provisions if this is a solicitation.
(6) Other paragraphs of this clause.
(7) The Standard Form 1449.
(8) Other documents, exhibits, and attachments
(9) The specification.
(t) [Reserved]
(u) Unauthorized Obligations.
(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:
(i) Any such clause is unenforceable against the Government.
(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an “I agree” click box or other comparable mechanism (e.g., “click-wrap” or “browse-wrap” agreements), execution does not bind the Government or any Government authorized end user to such clause.
(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.
(2) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.
(v) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
(End of Clause) ADDENDUM to FAR 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES Clauses that are incorporated by reference (by Citation Number, Title, and Date), have the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available.
The following clauses are incorporated into 52.212-4 as an addendum to this contract:
C.2 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
https://www.acquisition.gov/browse/index/far https://www.va.gov/oal/library/vaar/
(End of Clause)
| FAR Number |
| Title |
| Date |
| 52.204-9 |
| PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL |
| JAN 2011 |
| 52.204-13 |
| SYSTEM FOR AWARD MANAGEMENT—MAINTENANCE (DEVIATION) |
| NOV 2025 |
| 52.204-18 |
| COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE |
| AUG 2020 |
| 52.223-5 |
| POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION |
| MAY 2024 |
| 52.237-2 |
| PROTECTION OF GOVERNMENT BUILDINGS, EQUIPMENT, AND VEGETATION |
| APR 1984 |
| 852.201-70 |
| CONTRACTING OFFICER'S REPRESENTATIVE |
| DEC 2022 |
| 852.203-70 |
| COMMERCIAL ADVERTISING |
| MAY 2018 |
| 852.204-70 |
| PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (DEVIATION) |
| MAR 2026 |
| 852.215-70 |
| SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESS EVALUATION FACTORS (DEVIATION) |
| JAN 2023 |
| 852.215-71 |
| EVALUATION FACTOR COMMITMENTS |
| OCT 2019 |
| 852.232-72 |
| ELECTRONIC SUBMISSION OF PAYMENT REQUESTS |
| NOV 2018 |
C.3 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)
The Contracting Officer reserves the right to designate an Administrative Contracting Officer (ACO) for the purpose of performing certain tasks/duties in the administration of the contract.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .