36C25219B0021-000.docx

DOCX document 131 KB Posted

Attached to
Install Pressure Sensors Project 537-18-129B Federal contract opportunity
Solicitation number
36C25219B0021
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12

About this file

36C25219B0021 36C25219B0021_1.docx

View the file

Other files for this federal contract opportunity

Other files attached to Install Pressure Sensors Project 537-18-129B, newest first.
File Type Posted
36C25219C0116-000.docx DOCX document
36C25219B0021-0001005.docx DOCX document
36C25219B0021-001.pdf PDF
36C25219B0021-002.pdf PDF
36C25219B0021.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25219B0021

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C25219B0021 X 02-01-2019 537-18-129B 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee WI 53214-1476 Great Lakes Acquisition Center (GLAC) Department of Veteran Affairs 115 S 84th Street, Suite 101 Milwaukee WI 53214-1476 Angella Sterling 224-610-3650 Project 537-18-129B: Install Various Type Sensors at Jesse Brown VA Medical Center (JBVAMC), Chicago, IL 60612

The Department of Veterans Affairs (VA) Veterans Health Administration (VHA) Great Lakes Acquisition Center (GLAC/NCO12) requires a Contractor to provide labor, materials, tools, equipment, transportation, and qualified supervision to execute work on Project 537-18-129B, Install Various Type Sensors.

This procurement is a 100% set-aside for CVE-verified Service Disabled Veteran-Owned Small Business (SDVOSB) firms per the authority of U.S.C. 8127 (Public Law 109-461). In accordance with VAAR 819.7003(b), at the time of bid submission, the bidder must represent that it is a SDVOSB concern, a small business concern under the NAICS code assigned to the acquisition, and is CVE-verified for eligibility in the Vendor Information Pages (VIP) database.

Project Magnitude Range: Between $250,000.00 and $500,000.00 NAICS Code: 238210 - Electrical Contractors and Other Wiring Installation Contractors SBA Size Standard: $15 Million

See 52.236-27 SITE VISIT for information on organized site visit.

Davis-Bacon Wage Rate Requirements as outlined in IL180009 apply to this solicitation.

If submitting a joint venture, offerors must include a copy of the joint venture agreement with their bid.

All bidders are responsible for monitoring and downloading any amendments from the FedBizOpps website at https://www.fbo.gov.

Award will be made to the responsible bidder who submits the lowest responsive bid. A single award will be made.

X x 52.211-10 X

3:00 PM, CST

03-04-2019 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

Base Bid $________________________________ 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 3001 Green Bay Road Building 1, Room 329 North Chicago IL 60064-3048 Department of Veterans Affairs Financial Services Center PO Box 149971 Austin TX 78714-9971 877-353-9791 512-460-5540

STATEMENT OF WORK

Project Name:Install Various Type Sensors
Project Number:537-18-129B
Place of Performance:Buildings 1, 32, and 40
Jesse Brown VA Medical Center
820 S. Damen Ave

Chicago IL 60612 The Certification and Accreditation (C&A) requirements do not apply, and a Security Accreditation Package is not required.

Part 1: Project Scope of Work Overview:

Contractor shall provide all tools, materials, components, labor and supervision to install and startup a pressure monitors and associated equipment in the rooms listed in the accompanying room pressure list (spreadsheet). A typical bundle will include an electronic pressure monitor, a pressure sensor, an individual room temperature sensor, an individual room humidity sensor, and a door switch or door position monitor. The referenced room equipment will be connected to the existing Building Automation System.

Approximately 60% rooms on this contract are connected to the Johnson Controls (JCI) Building Automation System (BAS) and the remaining 17% is connected to an Auto Matrix BAS, and the remaining ten (10) are likely connected to the JCI BAS without current individual temperature or humidity monitoring. Some rooms already have either individual temperature monitoring, humidity monitoring, or both. For these rooms the contractor only needs to add the missing monitor needed to provide full monitoring for the space.

The Facility currently has both Setra and TCI monitors installed and the Contractor should choose one of these brands to provide consistency of Facility equipment and meet the requirements of this contract.

Some connections or configurations may vary dependent on the selection of equipment; however, the Government reserves the right to approve or reject deviations from the standard connections to the BAS if deemed to increase the risk of failure. For instance, if a room monitor can monitor 2 rooms with external pressure transducer. Or if the temperature and/or humidity sensor can be connected directly to the pressure monitor, then the Facility may allow it if it’s considered a better configuration or it the standard configuration is not possible. For spaces where there is no functioning BAS connection at the time of construction then simply provide connection to or for BACnet BAS system.

None of the rooms to be monitored are in Building 32 or Building 40. These 2 buildings are mentioned in this scope because the BAS servers are in these buildings and the Contractor may have to enter the buildings for programing purposes.

Part 2: Detailed Project Scope of Work:

The contractor shall

· Refer to the exhibit Room Pressure List (spreadsheet) for the summary of rooms.

· Per the spreadsheet provide BACnet compatible Temperature Sensor, Humidity Sensor, Pressure Differential Sensor.

· All devices shall be flush wall mounted. Temperature sensors and humidity sensors can be wall or ceiling mounted.

· BACnet cable shall be plenum rated above the ceiling and walls without the use of conduit. Use existing wire management, do not connect to HVAC, sprinkler, ceiling grid or ceiling hangers. Connect the BACnet cable to the (nearest) BACnet compatible Building Automation Terminal Unit. All Devices shall be BACnet and provide homeruns as required. (use BACnet open network protocol without any non-BACnet compliant components)

· All devices shall be BACnet programmed to alarm and show status on the BAS graphic annunciator.

· Include programming 30% of the rooms listed to control a respective box, exhaust or damper.

· Do not use: LON, American Automatics or Metisys proprietary protocol. Provide BACnet conversion and connections as required.

· Pressure Sensors have additional requirements other than connecting the BACnet. Typical steps are listed below to be used as a guideline, however manufacturers will typical provide installation instructions which can be used in conjunction with the standard electric codes. These steps are just listed to ensure that all requirement for a fully functional pressure differential system are included in this contract.

· Mount the Pressure Sensor to the wall (outside portion of the room), penetrate wall for pitot tube, install plate on opposite side of wall and connect the plate inside the room with a tube to the Pressor Monitor that is on the outside of the room. The exact position to be coordinated with the COR and not exceed 6 feet from the door to the room.

· Connect Pressure Sensor electric power. The nearest power is up to 75 pipe feet. Coordinate with the COR for the connection point. Electric power source should come from an emergency power source (low power draw, can tap into emergency exit light circuit). If emergency power is not within the allowed length, coordinate with the COR to connect to the nearest power outlet circuit. Update all panel schedules

· Provide and install a door contact switch. This contact allows the Pressure Sensor not to immediately alarm when the doors are opened under normal use.

Special Acceptance Criteria for the work shall be:

· Inspection of each unit and verification that the unit is performing and reporting to the BAS correctly, by the Contractor with the VA COR

Part 3: Period of Performance (POP) and Project Construction Cost Magnitude Complete all work including submittals, reviews and quality control within the calendar days from Notice to Proceed (NTP) as shown below.

PERIOD OF PERFORMANCE CHART (IN CALENDAR DAYS AFTER NTP)

Level Complete
Calendar Days for the Work
VA Review
Resubmit if Comments
Total days after NTP
Part 4.1 Kick-Off Meeting with Documentation
14
0
0
14
Part 4.2 Shop Drawings and Product Submittals
21
7
7
49
Part 4.3 Mobilization On-Site including Performance of the Work
150
Part 4.4 Acceptance and Close Out
21
7
7
234

Accommodate the Period of Performance by including accelerated equipment delivery costs as well as adjusting crew sizes.

The Contractor shall provide mitigating activities as outlined in the CONSTRUCTION SAFETY PRECAUTIONS and CONSTRUCTION INFECTION CONTROL RISK ASSESSMENT / DUST CONTROL PRECAUTIONS. Because there are multiple locations, including but not less than the following:

a. Fire extinguishers, cart mounted at the area of work

b. Walk off dust mats, inside and outside all entry / exit points to the workspace, or on the floor next to containment carts, changed not less than daily or more as required by the construction or COR.

c. Provide mini-containment plastic dust tight temporary construction barrier or premanufactured system to isolate the area of work.

i. Containment is required for all wall and above ceiling work. Do not access above the ceiling without containment.

ii. All containment shall have HEPA filter negative air system

iii. The VA will move furniture if required.

d. No trash, used packaging or construction spoils shall be stored on site. Remove each day using covered gondolas.

e. HEPA vacuum the work area at the end of each day.

No work during the business day. All work shall be after 5 pm on weekdays through midnight to 5 am, any time Saturdays and Sundays. No Federal Holidays or related holiday weekends. Because this work requires acceptance Infection Control before the room can be reactivated for patient care, the Contractor shall coordinate with the COR and present an installation schedule 4 week look ahead. The Period of Performance accommodates the VA adjusting proposed install dates because of Patient Care, emergencies or other operational limitations.

Construction Progress Meetings: The Contractor’s Project Manager and Field Supervisor shall provide weekly on-site construction progress meetings with the COR for the entire period of performance. Include minutes of the meeting and issue past minutes not later than 3 days after the meeting. Construction Progress Meetings Minutes shall contain: list of attendees, list any issues or concerns, indicate days remaining per the contract, detail any safety incidents, RFI log, Shop Drawing Log, detailed two-week look ahead and shutdown schedule.

Daily Report: The Contractor shall provide a Daily Report in compliance with VAAR 852.236-79 DAILY REPORT OF WORKERS AND MATERIAL. The Daily Report shall contain: list any issues or concerns, indicate days remaining per the contract, detail any safety incidents, detail daily construction safety inspections including items checked and corrective actions taken, and include relevant construction progress photo(s). Email the Daily Report to the COR not later than 9 am the next working day.

Part 4: Submittals and Milestone Deliverables:

1. KICK-OFF MEETING with DOCUMENTATION

a. The Contractor Project Manager and Field Supervisor shall attend a Preconstruction Safety Meeting, to discuss the project details.

b. Submit: Provide a FULLY LOADED COST SCHEDULE meeting the requirements of the VAAR 852.236-84 SCHEDULE OF WORK PROGRESS. Not less than 1 item per subcontractor. In addition, include any expected system shutdowns and off hours work.

c. Submit: LIST OF ALL CONTRACTORS AND SUBCONTRACTORS: company names, office address and main point of contact name with telephone number

d. Submit: CONSTRUCTION SAFETY PRECAUTIONS with project specific procedures, processes, analysis and details including but not limited to:

i. CONSTRUCTION SAFETY PLAN, LOCK OUT TAG OUT (LOTO), PERSONAL FALL ARREST SYSTEM, CONFINED SPACE PLAN

ii. ACCIDENT PREVENTION PLAN (APP) project specific

iii. ACTIVITY HAZARD ANALYSIS (AHA) project specific

e. Submit: CONSTRUCTION INFECTION CONTROL RISK ASSESSMENT / DUST CONTROL PRECAUTIONS including:

i. Utilize project specific details and assist the COR in completing the VA’s Infection Control Risk Assessment documentation

f. Submit: SHOP DRAWINGS AND PRODUCT LOG:

i. List all shop drawings and products in the submittal log.

g. Submit: Scanned copy of all workers OSHA Construction Safety Training certificates.

2. SHOP DRAWINGS AND PRODUCT SUBMITTALS

a. The Contractor shall provide all shop drawings and product submittals by email to the COR.

b. Allow 14 days for VA review.

3. MOBILIZATION ON SITE INCLUDING PERFORMANCE OF THE WORK

a. Contractor shall not mobilize on site until all KICK-OFF MEETING AND DOCUMENTATION and SHOP DRAWINGS AND PRODUCT SUBMITTALS are reviewed and accepted by the VA.

b. Approval to mobilize shall be in writing by the COR.

c. Post and maintain emergency contact information, VA’s Infection Control Risk Assessment and other information required by the COR, on the wall at all entry points to the worksite

4. ACCEPTANCE AND CLOSE OUT

a. Acceptance Criteria for the work:

i. Demonstrate the operation of the system

ii. Provide factory startup and certification of all systems.

iii. Newly installed piping and distribution system components shall be flushed and disinfected prior to being placed in service. Include documenting completion

iv. Schedule the demonstration with the COR 21 days in advance.

b. Factory Training

i. Provide factory personnel for training for all equipment

ii. Provide 4 sessions of 1 hour each

iii. Schedule the factory training with the COR not less than 21 days in advance.

c. Close Out Records: provide three printed sets and three compact discs with electronic files of the following:

i. Plan as built record drawings of the installed condition: As built plans and risers are to be CAD drawn. Floor plan CAD files are available from the VA

ii. Approved shop drawings

iii. Operations and Maintenance Manuals

iv. Spare parts listing Part 5: Applicable Performance Standards

2. All work shall comply with

a. All VA Policies including and not limited to: VA Construction Safety and VA Infection Control Policies.

b. Codes, Standards and Executive Orders (Topic 1) found http://www.cfm.va.gov/til/cPro.asp

3. All persons including subcontractors shall have completed the 30 Hour OSHA Construction Safety Training program.

4. The Prime Contractor shall have a Competent Supervisory Person on site at all times when any worker(s) or sub-contractors are present.

5. All persons working on any electrical systems rated 50 volts or more shall have the minimum qualification as a State Licensed Master Electrician or Registered Journeyman Electrician, all activities shall follow the safe work practices in compliance with NFPA 70E Electrical Safety in the Workplace.

6. All work will be provided with 1-year parts and labor guarantee from date of acceptance by the VA.

Part 6: Jesse Brown VAMC Additional Requirements

1. Project number and the contract number in the subject line of all emails

2. Comply with all Jesse Brown VAMC site specific requirements and SOPs including and not limited to: Key Policy, Badging Policy, Rules of Behavior, and Smoking Policy.

3. The Contractor shall check in (in person) with the Administrative Officer of the Day (AOD) which is located in Patient Admitting for any work between 6:00 pm through midnight to 6:00 am or any time on weekends. Provide the name and cell number of the on-site supervisor to the AOD. At the completion of the work, check out with the AOD.

4. All building systems will be maintained in full operation at all times:

a. Request system shutdowns in writing not less than 21 calendar days in advance.

b. Shutdown work shall be during low patient time and performed between Saturday 6 pm through midnight concluding by 6 pm on the following Sunday.

5. Fire-seal all penetrations through any wall or floor with Listed fire rated assembly.

6. Deliveries, Parking, Elevators:

a. Deliveries only at the Polk Street dock, and coordinated with the COR. At time of delivery: provide vehicle information to the VA Police and remove the vehicle as soon as delivery is complete. Move materials in public corridors during low patient time and performed between 6 pm through midnight concluding by 6 am on the following day.

b. No on-site parking. Utilize street parking or park in the Cook County Juvenile Parking Garage at their daily rate. The existing JB VAMC parking garage is at capacity and reserved for patients and staff.

c. Contractor shall use Freight Elevators. Do not move materials and employees in passenger elevators unless written approval by COR.

7. Space for a construction dumpster is limited and should be coordinated with the COR if required. The Contractor must still comply with the Facility’s disposal policies and provide recycling and receipts from the salvage/deposal service in compliance with JBVAMC’s GEMS Policy.

8. No on-site office or on-site storage / office container shall be allowed. Provide ‘just in time delivery and pickup’. Coordinate with COR for staging within the area of work.

9. No music radios. Two-way communications radios are allowed where broadcast frequency is approved by COR.

10. All work in the crawl spaces shall be planned and carried out as OSHA Permit Required Confined Space.

11. Immediately stop work and notify the COR if asbestos is noticed or suspected activities in the area of work.

Exhibit: Project 537-18-129B Room Pressure List

CONTRACT ADMINISTRATION DATA

1. CONTRACT ADMINISTRATION: All contract administration matters will be handled by the following individual(s):

a. CONTRACTOR:___________________________________ ___________________________________ ___________________________________ ___________________________________
GSA / FSS Agreement #:_____________________

Contact Person: _____________________ Telephone #: _____________________ Fax #: _____________________ e-Mail Address: ___________________ Tax Identification Number: _____________________ DUNS Number: _____________________

b. GOVERNMENT: Contracting Officer (36C252/90C) Department of Veterans Affairs, Great Lakes Acquisition Center (NCO 12) Capt. James A. Lovell Federal Health Care Center 3001 Green Bay Rd., Bldg. 1, Rm 329 North Chicago, IL 60064-3048

2. CONTRACTOR REMITTANCE ADDRESS: Effective January 1, 1999 all payments by the Government to the contractor will be made in accordance with Federal Acquisition Regulation (FAR) Clause 52.232-34, Payment by Electronic Funds Transfer. Contractor must be registered in the System for Award Management (SAM) database in accordance with FAR Clause 52.212-1(k).

3. INVOICES: Invoices shall be submitted within ten (10) business days after performance and acceptance of services and must include the VA Contract Number, Project Number, Purchase Obligation Number and Detailed description of the services provided. Payment for services provided under the terms of this contract will be made in arrears, within thirty (30) calendar days, upon receipt of properly executed invoice(s) in accordance with:

· 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2012)

· UPON ACCEPTANCE OF SERVICES

· In order to comply with the Improper Payment Elimination and Recovery Act of 2010 (IPERA), the VA has mandated electronic invoice submission to the Veterans Affairs Financial Services Center (VAFSC). VAFSC has partnered with OB10 e-Invoicing network, for submissions of all electronic invoices to VA. OB10 electronic invoicing is free to all VA vendors. In order to submit electronic invoices, all VA vendors must register with OB10 by submitting an email to VA.Registration@ob10.com or calling 1-877-752-0900 option 2 for Enrollment.

· Contractor shall submit an electronic invoice within ten (10) business days after performance and acceptance of services to the Veterans Affairs Financial Services Center (VAFSC) e-Invoice through the website at https://portal.tungsten-network.com/Login.aspxhttps://portal.tungsten-network.com/Login.aspx. For questions regarding the submission of VA electronic invoices, OB10 customer service may be contacted at 1-877-489-6135.

· All invoices shall reference the vendor name and address, customer name, contract number, appropriate obligation/funding order number, description of services provided, quantity provided, unit price, and total invoice amount (any additional info). Invoices shall also include any payment discount terms.

· For questions regarding invoice receipt or payment, please call VAFSC directly at 1-877-353-9791 or email vafsccshd@va.gov

4. GOVERNMENT INVOICE ADDRESS: All invoices from the Contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 “Electronic Submission of Payment Requests.” to the following web address: http://www.ob10.com/us/en/#&panel1-1.

FACSIMILE, E-MAIL, AND SCANNED DOCUMENTS ARE NOT ACCEPTABLE FORMS OF SUBMISSION FOR PAYMENT REQUESTS.

For assistance setting up e-Invoice, the below information is provided:

* Tungsten Network e-Invoice Setup Information: 1-877-489-6135

* Tungsten Network e-Invoice email: VA.Registration@ob10.com <http://VA.Registration@ob10.com/>

* FSC e-Invoice Contact Information: 1-877-353-9791

* FSC e-invoice email: vafsccshd@va.gov <http://va.gov/>

5. CONTRACT AUTHORITY: The Contracting Officer is the only person authorized to approve changes or modify any of the requirements of this request. The Contractor shall communicate with the Contracting Officer on all matters pertaining to Contract Administration. Only the Contracting Officer is authorized to make commitments or issue changes that affect pricing, quantities or quality of performance of this contract.

6. SUBMITTAL OF OFFERS: All bids/offers must be submitted to the attention of the Contracting Officer identified No Later Than the date/time specified. Bids/Offers will be received at: Contracting Officer – (36C252/90C), Department of Veterans Affairs, Great Lakes Acquisition Center (NCO 12), Capt. James A. Lovell Federal Health Care Center, 3001 Green Bay Rd., Bldg. 1, Rm 329, North Chicago, IL 60064-3048 until the date and time specified.

NO FAX/ FACSIMILE SUBMITTED BIDS WILL BE ACCEPTED.

All transmittal envelopes or other packaging shall be clearly marked with the solicitation number, offeror’s company name and return address. All offers shall be subject to all terms and conditions of this solicitation.

7. QUESTIONS: Requests for Information (RFI) to solicitation documents should be submitted in writing to the Contract Specialist at: angella.sterling@va.gov by February 19, 2019 by 5:00 pm, CST. No telephone responses will be accepted. NOTE: All questions must reference in the Header or Opening Statement the Project #, the IFB #, and the Description of the project.

8. All offers must be submitted to the attention of the Contracting Officer identified and listed on the Standard Form 1442, Block 9a and to the address identified on the Standard Form 1442, Block 13.

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

1.1 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of Provision)

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade
Goals for female participation for each trade
19.6 %
6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is

(End of Provision)

2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.5 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Hand-Carried Address:

Department of Veteran Affairs

GLAC/NCO 12 (36C252)

3001 Green Bay Road Building 1, Room 329 North Chicago IL 60064-3048

Mailing Address:

Department of Veterans Affairs

GLAC/NCO 12 (36C252)

3001 Green Bay Road Building 1, Room 329 North Chicago IL 60064-3048

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of Provision)

2.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for— February 13, 2019 at 10:00 a.m.

(c) Participants will meet at— Department of Veterans Affairs Jesse Brown VA Medical Center 820 S. Damen Avenue Taylor Street Elevator Entrance Conference Room 3295 – Engineering Suite

(End of Provision)

2.7 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/

(End of Provision)

FAR Number
Title
Date
52.204-7
SYSTEM FOR AWARD MANAGEMENT
OCT 2018
52.204-16
COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING
JUL 2016
52.204-22
ALTERNATIVE LINE ITEM PROPOSAL
JAN 2017
52.214-3
AMENDMENTS TO INVITATIONS FOR BIDS
DEC 2016
52.214-4
FALSE STATEMENTS IN BIDS
APR 1984
52.214-5
SUBMISSION OF BIDS
DEC 2016
52.214-6
EXPLANATION TO PROSPECTIVE BIDDERS
APR 1984
52.214-7
LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS
NOV 1999
52.214-18
PREPARATION OF BIDS—CONSTRUCTION
APR 1984
52.214-19
CONTRACT AWARD—SEALED BIDDING—CONSTRUCTION
AUG 1996
52.214-34
SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE
APR 1991
52.214-35
SUBMISSION OF OFFERS IN U.S. CURRENCY
APR 1991

2.8 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) Prime contractors are encouraged to assist service-disabled veteran-owned and veteran-owned small business potential subcontractors in obtaining bonding, when required. Mentor firms are encouraged to assist protégé firms under VA's Mentor-Protégé Program in obtaining acceptable bid, payment, and performance bonds, when required, as a prime contractor under a solicitation or contract and in obtaining any required bonds under subcontracts.

(End of Clause)

2.9 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)

The Contractor shall not make reference in its commercial advertising to Department of Veterans Affairs contracts in a manner that states or implies the Department of Veterans Affairs approves or endorses the Contractor’s products or services or considers the Contractor’s products or services superior to other products or services.

(End of Clause)

2.10 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (SEP 2018)

(a) Any protest filed by an interested party shall—

(1) Include the name, address, fax number, email and telephone number of the protester;

(2) Identify the solicitation and/or contract number;

(3) Include an original signed by the protester or the protester’s representative and at least one copy;

(4) Set forth a detailed statement of the legal and factual grounds of the protest, including a description of resulting prejudice to the protester, and provide copies of relevant documents;

(5) Specifically request a ruling of the individual upon whom the protest is served;

(6) State the form of relief requested; and

(7) Provide all information establishing the timeliness of the protest.

(b) Failure to comply with the above may result in dismissal of the protest without further consideration.

(c) Bidders/offerors and Contracting Officers are encouraged to use alternative dispute resolution (ADR) procedures to resolve protests at any stage in the protest process. If ADR is used, the Department of Veterans Affairs will not furnish any documentation in an ADR proceeding beyond what is allowed by the Federal Acquisition Regulation.

(End of Provision)

2.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (SEP 2018)

(a) As an alternative to filing a protest with the Contracting Officer, an interested party may file a protest by mail or electronically with: Executive Director, Office of Acquisition and Logistics, Risk Management and Compliance Service (003A2C), Department of Veterans Affairs, 810 Vermont Avenue NW, Washington, DC 20420 or Email: EDProtests@va.gov.

(b) The protest will not be considered if the interested party has a protest on the same or similar issue(s) pending with the Contracting Officer.

PLEASE NOTE: The correct mailing information for filing alternate protests is as follows:

Deputy Assistant Secretary for Acquisition and Logistics,
Risk Management Team, Department of Veterans Affairs
810 Vermont Avenue, N.W.
Washington, DC 20420

Or for solicitations issued by the Office of Construction and Facilities Management:

Director, Office of Construction and Facilities Management
811 Vermont Avenue, N.W.
Washington, DC 20420

(End of Provision)

2.12 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)

The contracting officer reserves the right to designate representatives to act for him/her in furnishing technical guidance and advice or generally monitor the work to be performed under this contract. Such designation will be in writing and will define the scope and limitation of the designee's authority. A copy of the designation shall be furnished to the contractor.

(End of Provision)

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (OCT 2018)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 238210.

(2) The small business size standard is $15 Million.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204–7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:

[ ] (i) Paragraph (d) applies.

[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(vi) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.

(vii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(viii) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.

(ix) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(x) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(xi) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(xii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.

(xiii) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.

(xiv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.

(xv) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.

(xvi) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

(xvii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.

(xviii) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.)

(xix) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.

(xx) 52.225-4, Buy American—Free Trade Agreements—Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225-3.

(A) If the acquisition value is less than $25,000, the basic provision applies.

(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.

(C) If the acquisition value is $50,000 or more but is less than $80,317, the provision with its Alternate II applies.

(D) If the acquisition value is $80,317 or more but is less than $100,000, the provision with its Alternate III applies.

(xxi) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.

(xxii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan—Certification. This provision applies to all solicitations.

(xxiii) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certifications. This provision applies to all solicitations.

(xxiv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.

(A) Solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions; and

(B) For DoD, NASA, and Coast Guard acquisitions, solicitations that contain the clause at 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns.

(2) The following representations or certifications are applicable as indicated by the Contracting Officer:

[X](i) 52.204-17, Ownership or Control of Offeror.

[X](ii) 52.204-20, Predecessor of Offeror.

[](iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.

[](iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment—Certification.

[](v) 52.222-52, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services—Certification.

[](vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA-Designated Products (Alternate I only).

[](vii) 52.227-6, Royalty Information.

[](A) Basic.

[](B) Alternate I.

[](viii) 52.227-15, Representation of…