This amendment modifies a solicitation for a construction project to replace dry pipe sprinklers at a Veterans Affairs facility. It incorporates additional clauses, removes one clause, and provides responses to offeror questions to clarify contract specifications and drawings. The project involves mechanical work in areas depicted on drawings and installing new ductwork to match existing after fire protection work. The amendment specifies that the schedule of costs must show itemized costs by work activity and event for each building, and identifies percentages paid for adjusting and testing various systems after installation. It also notifies offerors where to find an attachment listing attendees of a pre-proposal site visit.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--Replace Dry Pipe Sprinklers 515-23-204, newest first.
File Type Posted
S06 515-23-204 Site Visit Attendance Log.pdf PDF
36C25023B0060 0002.docx DOCX document
36C25023B0060 0001.docx DOCX document
S02 Contractor EMR Certification Form - 515-23-204.docx DOCX document
S03 Wage Determination MI20230079 04.14.2023 -Calhoun - 515-23-204.pdf PDF
S02 Drawings 515-23-204.pdf PDF
36C25023B0060_1.docx DOCX document
S02 RFI Form - 515-23-204.doc DOC document
S02 Specifications 515-23-204.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7.

ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF

PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE

OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERE

D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED

STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF

CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF

SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 515-23-3-155-0050 515-23-204 36250 Department of Veterans Affairs Network Contracting Office (NCO) 10 5500 Armstrong Rd., bldg. 9 Rm. 105 Battle Creek MI 48105 Y Same as Block 6

To all Offerors/Bidders

36C25023B0060 06-30-2023

X X X

The purpose of Amendment #0003 is to:

1. Add the referenced FAR and VAAR Clauses.

2. Removes a referenced VAAR Clause

3. Provide responses to the Request for Information (RFI).

See Continuation Pages for details.

Scott D. Brennan Contract Specialist

SF 30 CONTINUATION PAGE 36C25023B0060 AMENDMENT 0003

1. VAAR Clause 852.232-70 is hereby incorporated into this solicitation and any resultant contract. VAAR Clause 852.232-71 is hereby removed from this solicitation.

852.232-70 Payments Under Fixed-Price Construction Contracts (Without NAS-CPM).

As prescribed in 832.111-70, insert the following clause in contracts that do not contain a section entitled “Network Analysis System-Critical Path Method (NAS-CPM):”

PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS-CPM) (NOV 2018)

The clause FAR 52.232-5, Payments Under Fixed-Price Construction Contracts, is implemented as follows:

(a) Retainage:

(1) The Contracting Officer may retain funds—

(i) Where performance under the contract has been determined to be deficient or the Contractor has performed in an unsatisfactory manner in the past; or

(ii) As the contract nears completion, to ensure that deficiencies will be corrected and that completion is timely.

(2) Examples of deficient performance justifying a retention of funds include, but are not restricted to, the following—

(i) Unsatisfactory progress as determined by the Contracting Officer;

(ii) Failure to meet schedule in Schedule of Work Progress;

(iii) Failure to present submittals in a timely manner; or

(iv) Failure to comply in good faith with approved subcontracting plans, certifications, or contract requirements.

(3) Any level of retention shall not exceed 10 percent either where there is determined to be unsatisfactory performance, or when the retainage is to ensure satisfactory completion. Retained amounts shall be paid promptly upon completion of all contract requirements, but nothing contained in this paragraph (a)(3) shall be construed as limiting the Contracting Officer’s right to withhold funds under other provisions of the contract or in accordance with the general law and regulations regarding the administration of Government contracts.

(b) The Contractor shall submit a schedule of cost to the Contracting Officer for approval within 30 calendar days after date of receipt of notice to proceed. Such schedule will be signed and submitted in triplicate. The approved cost schedule will be one of the bases for determining progress payments to the Contractor for work completed. This schedule shall show cost by the work activity/event for each building or unit of the contract, as instructed by the resident engineer.

(1) The work activities/events shall be subdivided into as many sub-activities/events as are necessary to cover all component parts of the contract work.

(2) Costs as shown on this schedule must be true costs and the resident engineer may require the Contractor to submit the original estimate sheets or other information to substantiate the detailed makeup of the schedule.

(3) The sums of the sub-activities/events, as applied to each work activity/event, shall equal the total cost of such work activity/event. The total cost of all work activities/events shall equal the contract price.

(4) Insurance and similar items shall be prorated and included in the cost of each branch of the work.

(5) The cost schedule shall include separate cost information for the systems listed in the table in this paragraph (b)(5). The percentages listed below are proportions of the cost listed in the Contractor’s cost schedule and identify, for payment purposes, the value of the work to adjust, correct and test systems after the material has been installed. Payment of the listed percentages will be made only after the Contractor has demonstrated that each of the systems is substantially complete and operates as required by the contract.

VALUE OF ADJUSTING, CORRECTING, AND TESTING SYSTEM

System
Percent
Pneumatic tube system
10
Incinerators (medical waste and trash)
5
Sewage treatment plant equipment
5
Water treatment plant equipment
5
Washers (dish, cage, glass, etc.)
5
Sterilizing equipment
5
Water distilling equipment
5
Prefab temperature rooms (cold, constant temperature)
5
Entire air-conditioning system (Specified under 600 Sections)
5
Entire boiler plant system (Specified under 700 Sections)
5
General supply conveyors
10
Food service conveyors
10
Pneumatic soiled linen and trash system
10
Elevators and dumbwaiters
10
Materials transport system
10
Engine-generator system
5
Primary switchgear
5
Secondary switchgear
5
Fire alarm system
5
Nurse call system
5
Intercom system
5
Radio system
5
TV (entertainment) system
5

(c) In addition to this cost schedule, the Contractor shall submit such unit costs as may be specifically requested. The unit costs shall be those used by the Contractor in preparing its bid and will not be binding as pertaining to any contract changes.

(d) The Contracting Officer will consider for monthly progress payments material and/or equipment procured by the Contractor and stored on the construction site, as space is available, or at a local approved location off the site, under such terms and conditions as the Contracting Officer approves, including but not limited to the following—

(1) The materials or equipment are in accordance with the contract requirements and/or approved samples and shop drawings;

(2) The materials and/or equipment are approved by the resident engineer;

(3) The materials and/or equipment are stored separately and are readily available for inspection and inventory by the resident engineer;

(4) The materials and/or equipment are protected against weather, theft and other hazards and are not subjected to deterioration; and

(5) The Contractor obtains the concurrence of its surety for off-site storage.

(e) The Government reserves the right to withhold payment until samples, shop drawings, engineer’s certificates, additional bonds, payrolls, weekly statements of compliance, proof of title, nondiscrimination compliance reports, or any other requirements of this contract, have been submitted to the satisfaction of the Contracting Officer.

(f) The Contracting Officer will notify the Contractor in writing within 10 calendar-days of exercising retainage against any payment in accordance with FAR clause 52.232-5(e). The notice shall disclose the amount of the retainage in value and percent retained from the payment, and provide explanation for the retainage (End of clause)

2. In accordance with FAR 52.213-4, FAR clause 52.204-27, Prohibition on a ByteDance covered Application, is hereby incorporated by reference into this solicitation and any resultant contract.

3. The following answers to requests for information questions are hereby provided to clarify, update, revise, or correct contract specifications and/or drawings.

QUESTIONS AND ANSWERS

1. RFI #1 Question: Please confirm that Division 23 only applies to the mechanical rooms as depicted on page 11 of the drawings?

Answer: The note which reads “Remove duct and associated duct insulation in this area as necessary to complete fire protection work indicated. Install new duct and duct insulation to match existing after completion of fire protection work. Re-use existing duct supports. Refer to Division 23 specifications. Coordinate shutdown of associated HVAC system with VA COR.” Does only apply to HVAC equipment in the areas shown on the associated sheets.

2. RFI #2 Question: Will the contractor be allowed to submit a schedule of values to delineate phases of the project, for applicable bonding and invoicing?

Answer: See VAAR Clause 852.232-70 PaymentsUnder Fixed-Price Construction Contracts (Not Including NAS-CPM) paragraph b. regarding the content of the schedule of costs

3. RFI #3 Question: Please provide a copy of the site visit attendee list?

Answer: Attendee List is attached to the Amendment

A.1 List of Attachments See attached document: S06 515-23-204 Site Visit Attendance Log.

Page 1 of Page 1 of

Page 1 of Page 1 of