This solicitation is for triannual electrical testing services at the Battle Creek VA Medical Center. The solicitation is a 100% verified service-disabled veteran-owned small business set-aside issued by the Department of Veterans Affairs Network Contracting Office 10. Quotes are due by June 27, 2022. The contractor will perform maintenance, inspection, testing and calibration of the electrical power distribution system in accordance with the statement of work. Services include cleaning, testing and calibration of switchgear, transformers, generators, transfer switches and other electrical components. The contractor must have five years of relevant experience and qualified electrician staff. The period of performance is from the award date through January 18, 2023. Pricing is on a firm-fixed-price basis for all work required.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment D.3 Eaton Study.pdf | ||
| Attachment D.2 SOW Appendices A-K.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25022Q0675
PAGE 1 OF
1. REQUISITION NO.
2. CONTRACT NO.
3. AWARD/EFFECTIVE DATE
4. ORDER NO.
5. SOLICITATION NUMBER
6. SOLICITATION ISSUE DATE
a. NAME
b. TELEPHONE NO. (No Collect Calls)
8. OFFER DUE DATE/LOCAL
TIME
9. ISSUED BY
CODE
10. THIS ACQUISITION IS
UNRESTRICTED OR
SET ASIDE:
% FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
8(A)
NAICS:
SIZE STANDARD:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
RFQ
IFB
RFP
15. DELIVER TO
CODE
16. ADMINISTERED BY
CODE
17a. CONTRACTOR/OFFEROR
CODE
FACILITY CODE
18a. PAYMENT WILL BE MADE BY
CODE
TELEPHONE NO.
UEI:
EFT:
PHONE:
FAX:
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED
SEE ADDENDUM
19.
20.
21.
22.
23.
24.
ITEM NO.
SCHEDULE OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only) 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________
29. AWARD OF CONTRACT: REF. ___________________________________ OFFER
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
DATED ________________________________. YOUR OFFER ON SOLICITATION
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) 30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
(REV. NOV 2021)
PREVIOUS EDITION IS NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.212
7. FOR SOLICITATION
INFORMATION CALL:
STANDARD FORM 1449
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
515-22-3-390-0715 36C25022Q0675 06-17-2022 Jeffrey Martin 317-988-1510 06-27-2022 14:00
EDT
Department of Veterans Affairs Network Contracting Office 10 8888 Keystone Crossing Suite 1100 Indianapolis IN 46240 X X 238210 $16.5 Million N/A X Battle Creek VA Medical Center (BCVAMC) 5500 Armstrong Rd Battle Creek MI 49037 Department of Veterans Affairs Network Contracting Office 10 8888 Keystone Crossing Suite 1100 Indianapolis IN 46240
See website at:
https://www.fsc.va.gov/einvoice.asp for instructions & for invoicing website at:
https://www.tungsten-network.com/ customer-campaigns/veteransaffairs See CONTINUATION Page The Battle Creek VA Medical Center requires maintenance, inspection, testing, and calibration of the Electrical Power Distribution System. The contractor shall provide all labor, materials, and supervision to provide maintenance, inspection, testing and calibration of the Electrical Power Distribution System in accordance with the statement of work.
Quoters that do not submit all required information may not be considered for award. Quoters are encouraged to submit a quote in accordance with the Instructions to Quoters included in Section E of this solicitation.
This is a 100% VIP verified SDVOSB set-aside.
This procurement is being procured under FAR Part 12 and 13 as a firm fixed price contract.
See CONTINUATION Page 515-3620162-390-854100-3223 0100555X9 X X X Sally L. Leitch Contracting Officer Table of Contents
| SECTION A | 1 |
| A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES | 1 |
| SECTION B - CONTINUATION OF SF 1449 BLOCKS | 3 |
| B.1 CONTRACT ADMINISTRATION DATA | 3 |
| B.2 ELECTRONIC INVOICE SUBMISSION AND INVOICING | 5 |
| B.3 CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM (CPARS) | 6 |
| B.4 PRICE/COST SCHEDULE | 7 |
| B.5 STATEMENT OF WORK | 8 |
| SECTION C - CONTRACT CLAUSES | 14 |
| C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021) | 14 |
| C.2 52.219-14 LIMITATIONS ON SUBCONTRACTING (SEP 2021) | 20 |
| C.3 SUPPLEMENTAL INSURANCE REQUIREMENTS | 21 |
| C.4 VAAR 852.212-70 PROVISIONS AND CLAUSES APPLICABLE TO VA ACQUISITION OF COMMERCIAL ITEMS (APR 2020) | 22 |
| C.5 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018) | 24 |
| C.6 VAAR 852.219-77 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (SEP 2021) (DEVIATION) | 25 |
| C.7 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) | 27 |
| C.8 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 27 |
| C.9 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (MAY 2022) | 27 |
| SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS | 36 |
| D.1 WAGE DETERMINATION INFORMATION | 36 |
| SECTION E - SOLICITATION PROVISIONS | 37 |
| E.1 52.212-1 INSTRUCTIONS TO QUOTERS—COMMERCIAL PROCUCTS AND COMMERCIAL SERVICES (Nov 2021) | 37 |
| E.1 INSTRUCTIONS TO QUOTERS – EVALUATION OF QUOTES | 40 |
| E.2 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 43 |
| E.3 52.233-2 SERVICE OF PROTEST (SEP 2006) | 45 |
| E.4 VAAR 852.215-72 NOTICE OF INTENT TO RE-SOLICIT (OCT 2019) | 45 |
| E.5 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 45 |
| E.6 52.212-2 EVALUATION—SIMPLIFIED ACQUISITION PROCEDURES | 46 |
| E.7 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021) | 46 |
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA
1. Contract Administration: All contract administration will be handled by the following individuals:
a. CONTRACTOR:
Prime
Address:
SAM UEI:
Point of Contact for Contract:
Alternate Point of contact:
Title:
Phone:
Email:
Subcontractor
Address:
SAM UEI:
Point of Contact for Contract:
Alternate Point of contact:
Title:
Phone:
Email:
b. GOVERNMENT:
| Contracting Officer 00250 |
| Contract Specialist 00250 |
| Sally L Leitch, 317-988-1538 |
| Jeffrey Martin, 317-988-1510 |
| Sally.Leitch@va.gov |
| Jeffrey.Martin8@va.gov |
| Department of Veterans Affairs |
| Department of Veterans Affairs |
| Network Contracting Office (NCO 10) |
| Network Contracting Office (NCO 10) |
| 8888 Keystone Crossing |
| 8888 Keystone Crossing |
| Suite 1100 |
| Suite 1100 |
| Indianapolis, IN 46240 |
| Indianapolis, IN 46240 |
2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:
| [X] |
| 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or |
3. INVOICES: Invoices shall be submitted in arrears:
c. Other [x] Monthly to: https://www.tungsten-network.com/customer-campaigns/veteransaffairs
4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests. Tungsten Network: https://www.tungsten-network.com/customer-campaigns/veteransaffairs
5. SECURE FAX: All faxes regarding this contract shall contain the following on the coversheet:
This fax is intended only for the use of the person or office to which it is addressed and may contain information that is privileged, confidential, or protected by law. All others are hereby notified that the receipt of this fax does not waive any applicable privilege or exemption for disclosure and that any dissemination, distribution, or copying of this communication is prohibited. If you have received this fax in error, please notify this office immediately at the telephone number listed above.
6. QUOTE SUBMISSION: Follow the submission instructions provided in the Instructions to Quoters.
7. LATE QUOTE SUBMISSION: Late submissions may not be considered.
8. QUESTIONS: All questions shall be submitted no later than the 5th calendar day at Noon, Eastern Time, after the issuance of the solicitation to Jeffrey.Martin8@va.gov. Phone calls shall not be accepted.
9. ACKNOWLEDGEMENT OF AMENDMENTS: Contractor shall acknowledge any and all amendments and include a signed copy with their quote submission. List of Amendments are listed below.
| AMENDMENT NUMBER |
| AMENDMENT NUMBER |
B.2 ELECTRONIC INVOICE SUBMISSION AND INVOICING
VENDOR ELECTRONIC INVOICE SUBMISSION REQUIREMENTS AND METHODS
Facsimile, e-mail, and scanned documents are not acceptable forms of submission for payment requests. Electronic form means an automated system transmitting information electronically according to the accepted electronic data transmission methods below:
1. VA’s Electronic Invoice Presentment and Payment System – the FSC uses a third-party contractor, Tungsten Network (referred to OB10), to transition vendors from paper to electronic invoice submission. Please go to website: https://www.tungsten-network.com/customer-campaigns/veteransaffairs to enroll in the program and begin submitting the electronic invoices, free of charge.
1. A system that conforms to the X12 electronic data interchange (EDI) formats established by the Accredited Standards Center (ASC) chartered by the American National Standards Institute (ANSI). The X12 EDI website is: http://www.x12.org
1. Please contact Tungsten at the phone number or email address listed below to begin submitting your electronic invoices to the VA Financial Services Center for payment processing, free of charge. If you have questions about the e-invoicing program or Tungsten, please contact the FSC at the phone number or email address listed below:
2. Tungsten e-Invoice Setup Information: 1-877-489-6135
2. Tungsten e-Invoice email: VA.Registration@Tungsten-Network.com
2. FSC e-Invoice Contact Information: 1-877-353-9791
2. FSC e-Invoice email: vafsccshd@va.gov
BILLING AND INVOICING
1. In accordance with this contract, all services shall be billed once job is complete.
2. Contractor shall only bill for services rendered and for line items delivered.
3. A proper invoice that is submitted for payment, shall be accepted, and certified for payment if:
a. All services shall be billed once job is complete.
b. Invoice contains in addition to the information required for submission of a ‘proper’ invoice in accordance with FAR 52.212-4(g) the following information:
i. Name and Address of the Contractor
ii. Invoice Date and Invoice Number
iii. Contract Number
iv. Contract Order Number
v. Purchase Order Number
vi. Date Range of Services Provided
vii. Description of Services Provided
viii. Line/Sub-Line Item-number(s) of services provided
ix. Quantity of each Line/Sub-Line Item
x. Unit Rate for each Line/Sub-Line Item
xi. Total Cost for each Line/Sub-Line Item
xii. Total Invoice Cost
4. The Certifying Official will confirm the information in the submitted invoice to the contract and invoice to ensure it is correct and valid.
a. If the invoice submitted is not a proper invoice, the certifying official shall refuse the invoice with a detailed statement as to why the invoice was refused.
b. Contractor shall make corrections and resubmit using a separate invoice number, notating the invoice number it is replacing.
B.3 CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM (CPARS)
As prescribed in FAR Part 42.15, the Department of Veterans Affairs (VA) evaluates contractor past performance on all contracts and contracts that exceed $250,000.00 and shares those evaluations with other Federal Government contract specialists and procurement officials. The FAR requires that the contractor be provided an opportunity to comment on past performance evaluations prior to each report closing. To fulfill this requirement VA uses an online database, CPARS, which is maintained by the Naval Seal Logistics Center in Portsmouth, New Hampshire. CPARS has connectivity with the Past Performance Information Retrieval System (PPIRS) database, which is available to all federal agencies. PPIRS is the system used to collect and retrieve performance assessment reports used in source selection determinations and completed CPARS report cards transferred to PPIRS. CPARS also includes access to Federal Awardee Performance and Integrity Information System (FAPIIS). FAPIIS is a web-enabled application accessed via CPARS for contractor responsibility determination information.
Each contractor whose contract award is estimated to exceed $250,000.00 requires a CPARs evaluation. A government Focal Point will register your contract within 30 days after award and, at that time, you will receive and email message with a User ID (to be used when reviewing evaluations). Additional information regarding the evaluation process can be found at www.cpars.gov or if you have any questions you may contact the Customer Support Desk at DSN: 684-1690 or COMM: 207-438-1690.
For contracts with a period of one year or less, the contracting officer will perform a single evaluation when the contract is complete. For contracts exceeding one year, the contracting officer will evaluate the contractor’s performance annually. Interim reports will be filed each year until the last year of the contract, when the final report will be completed. The report shall be assigned in CPARS to the contractor’s designated representative for comment. The contractor representative will have 60 days to submit any comments and re-assign the report to the CO.
B.4 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1.00 |
| JB |
| _________ |
| ________________ |
Contractor shall perform maintenance, inspection, and testing of the Electrical Power Distribution System at the Battle Creek VA Medical Center in accordance with the statement of work.
Contract Period: Base POP Begin: 07-18-2022 POP End: 01-18-2023
PRINCIPAL NAICS CODE: 238210 - Electrical Contractors and Other Wiring Installation Contractors PRODUCT/SERVICE CODE: J059 - Maintenance, Repair, and Rebuilding of Equipment - Electrical and Electronic Equipment Components
| GRAND TOTAL |
| __________________ |
Page 1 of Page 1 of
B.5 STATEMENT OF WORK
Maintenance, Inspection, and Testing of the Electrical Power Distribution System Department of Veterans Affairs Battle Creek VA Medical Center
PART I: General Information
1. Introduction:
A. This Statement of Work (SOW) describes the requirements for the maintenance, inspection, testing, and/or calibration of the Electrical Power Distribution System and all of its components at the Battle Creek VA Medical Center. These work items are referenced as “Maintenance and Testing” in this document, hereafter.
B. Additionally, the Qualified Electrical Contract Professionals – known as “Contractors” in this document, hereafter, shall refer to National Fire Protection Association (NFPA) 70B, Electrical Equipment Maintenance, Chapter 9, Section 9.6, Risk Assessment Studies and conduct a risk assessment for all facility electrical systems.
C. The risk assessment study results will be field marked by a label on the equipment in accordance with NFPA 70E, Article 130.5D.
D. This SOW describes the requirements for contractors who are contracted by VA Medical Center to perform maintenance and testing of the Electrical Power Distribution System, and all of its components. The contractor shall meet all requirements stated in paragraph 2, “Qualifications of Contractors” below.
E. This SOW describes the requirements to establish maintenance and testing reports.
2. Qualifications of Contractors:
A. Contractors shall be experienced Electrical Contractors, having properly trained and licensed permanent staff required to perform the proposed work. Electrical Contracting (i.e., the construction, repair, testing and maintenance of industrial and commercial electrical distribution systems) shall be the primary interest/specialty of the Contractor’s business.
B. Contractors shall be certified by the InterNational Electrical Testing Association (NETA) or equivalent certifying organization as Certified Technicians with each having completed the Occupational Safety & Health Administration (OSHA) approved 10-hour construction safety training. Certifications must be provided prior to work.
C. Contractors shall have technical training and demonstrable track records of working experience in maintenance, inspection, and testing of the Electrical Power Distribution Systems and related components in healthcare, industrial, educational, and commercial facilities for a minimum of five (5) continuous years. Electrical components on which the Contractors have experience shall include, switchboards & switchgear (low and medium voltage); low voltage controls; emergency and standby generators; automatic transfer switches, wiring, transformers, meters, and other electrical appurtenances. Provide a list of three (3) jobs that are similar is scope and cost.
D. Contractors shall have safety trainings – either on-the-job or class-room type - in electrical safety outlined in the OSHA Standard 29 Code of Federal Regulations (CFR) 1910 Subpart S – Electrical, and the NFPA 70E – Standard for Electrical Safety in the Workplace. Training certification shall be provided indicating each technician is a Qualified Person as defined by NFPA 70E. Training certifications shall be submitted to the VA Contracting Officer prior to work. If no training certifications are available, the contractor’ Employer shall certify that he/she has met this requirement in writing and submit it to the VA Contracting Officer prior to work.
E. Contractors shall have ready access to the latest versions of the following references:
1) NFPA 70, National Electrical Code. NFPA 70®: National Electrical Code®
2) NFPA 70B, Recommended Practice for Electrical Equipment Maintenance. NFPA 70B: Recommended Practice for Electrical Equipment Maintenance
3) NFPA 70E, Standard for Electrical Safety for the Workplace. NFPA 70E®: Standard for Electrical Safety in the Workplace®
4) NFPA 110, Standard for Emergency and Standby Power System. NFPA 110: Standard for Emergency and Standby Power Systems
5) OSHA Standard 29 CFR 1910, Subparts I & S. 1910 | Occupational Safety and Health Administration (osha.gov)
6) InterNational Electrical Testing Association, Inc. (NETA) – Maintenance and Testing Specifications. ANSI/NETA MTS - InterNational Electrical Testing Association (netaworld.org)
7) Operating/Maintenance manuals, and specifications of the electrical equipment to be maintained and tested. These documents may be obtained from the VHA Medical Center, or the equipment manufacturers.
8) VHA Directive 1028, Electrical Power Distribution System VHA Publications (va.gov)
F. Contractors shall have and provide all necessary tools, equipment, and Personal Protective Equipment (PPE) to perform the work safely, effectively, and timely. Tools, equipment, and PPE shall comply with the requirements of OSHA Standard 29 CFR 1910, Subpart I, and NFPA 70E. Prior to initiating work, Contractor shall provide documentation that all instruments, test equipment, tools and PPE have current calibration. Dated calibration labels shall be visible on all instruments, test equipment, tools and PPE as appropriate.
PART II: Work Requirements
1. Summary of Work:
****Note: Contractor shall refer to VHA Directive 1028 part 12 a–c & part 13 a-h; government furnished one-line diagrams; and attached Inventory of Items tested, to determine a complete list of every component that requires testing.
A. The Contractor shall provide a proposed schedule within 14 days of award date. The schedule shall be in the form of a progress chart of suitable scale to indicate the work scheduled for completion by any given date during the work period. The proposed schedule shall be reviewed by the VAMC Facilities Management; any requirements for adjusting the schedule (e.g. to minimize disruption to the VAMC) shall be incorporated by the Contractor.
B. Contractors shall report deficiencies that are deemed critical or catastrophic immediately to the Contracting Officer and the COR for immediate actions.
C. Work items, definitions, and references shall comply with the latest edition of the NETA – Maintenance Testing Specifications (MTS) and with the VHA Directive, Electrical Power Distribution System. Below is a list of the most common electrical equipment applications present at Battle Creek VA that shall be cleaned and tested:
1) Switchgear and Switchboard Assemblies, Medium and Low Voltage.
2) Transformers, Dry Type and Liquid-Filled, Medium Voltage (Note: some Medium Voltage Transformers may have internal switching that requires additional testing).
3) Transformers, Dry Type and Liquid-Filled, Non-Medium Voltage.
4) Switches, Medium-Voltage, All Types.
5) Medium Voltage Cabling (Note: Testing to be accomplished using the frequency method as opposed to high pot method in order to reduce degradation of cabling)
6) Circuit Breakers, Low-Voltage Power, All Types 100 amp or greater.
7) Circuit Breakers, Medium-Voltage, All Types.
8) Grounding Systems (Each Building).
9) Motor Control Center (MCC), Low-Voltage.
10) Conduct a risk assessment for all facility electrical systems to determine the following for each piece of electrical equipment:
a. Incident energy exposure at working distance
b. Arc flash boundary
c. Appropriate arc-flash personal protective equipment required within arc flash boundary
11) Replace any existing arc-flash labels and/or install any new labels required to bring station into compliance
D. Attachments, Government Furnished:
1) One-line and other informational drawings of the Electrical Power Distribution System. These drawings are not certified as-built drawings (Appendix A and B).
2) Inventory of Electrical Power Distribution System equipment to be maintained, inspected, and tested under this Scope of Work (Appendix C through K).
3) Electrical Power System study information relevant to the scope of this effort, such as coordination study data, short-circuit analysis, arc-flash hazard analysis and available protective device setting information:
a. Eaton Study (Provided under separate cover) – Contractor shall field verify all information provided under the study and provide the COR with a report of any discrepancies.
E. Infra-Red Scanning/Thermographic Survey shall be performed on electrical equipment as part of the cleaning and testing process.
1) Use an infra-red scanning camera to detect hot spots in the Electrical Power Distribution System. Objective of this work is to detect any loose, broken, or corroded connections in the system. Problem connections shall be identified in the list of deficiencies.
2) Note that since this work item must be done while the Electrical Power Distribution System is energized, appropriate safety precautions must be taken before, during and after scanning the system.
3) Infrared testing is to be completed in advance of the remainder of the work to allow the VA the opportunity to make repairs on items found during this testing while equipment is de-energized for other testing.
F. System Function Tests. Provide function test for all equipment listed in this Scope of Work.
2. Deliverables:
A. A complete written report of the work performed shall be provided to the VA within 7 days of completion. Information shown in the report shall be as following:
1) Company’s name, addresses, telephone, & FAX numbers.
2) Name and signature of contractors who perform the maintenance and testing.
3) VA Work Contract Number, name and number of VA Contracting Officer.
4) Date and Time of work.
5) Copies of contractors’ valid licenses, professional and training certificates.
6) Descriptions and model number of specialized tools and equipment used, such as torque wrench or infra-red scanning camera.
7) Location, Type, Name, and nameplate information of electrical equipment to be maintained and tested.
8) Descriptions of work items.
9) Test data.
10) Reference materials such as equipment manufacturer’s specifications, coordination study, etc.
11) Remarks on conditions of electrical equipment. List all deficiencies, if any.
12) Recommended corrective actions, if any.
B. Submit two (2) hard copies of the complete written report to VA Contracting Officer Representative (COR) within seven (7) calendar days of visit.
C. Submit two (2) hard copies of the complete written report, and one (1) copy in electronic format in Microsoft Word to the COR within seven (7) calendar days of visit. All reference materials shall be included in the electronic version of the report, either through scanning or other means.
PART III: Work Requirements
1. Security: The C&A requirements do not apply, and a Security Accreditation Package is not required. On Site personnel are required to complete the VA Privacy Training for Personnel without Access to VA Computer Systems or Direct Access or Use to VA Sensitive Information (course number VA20939). A copy of the signed training must be submitted to the COR and uploaded into VA Talent Management System (TMS.) The training accessed by going to VA TMS Self Enrollment Training (ns2cloud.com) and following the step-by-step procedures.
2. Place of Performance: Battle Creek VA Medical Center (BCVAMC), 5500 Armstrong Rd, Battle Creek, MI 49037
3. Qualifications of Key Personnel: See Part I, paragraph 2 above.
4. Hours of Work: Hours of work are 8:00 a.m. to 4:30 p.m. Monday through Friday, excluding federal holidays. Federal holidays can be found at the website here Federal Holidays (opm.gov).
5. Period of Performance: Period of performance will be from the date of contract award until 1/18/2022.
PART IV: VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors
1. Contractor employees who work in or travel to VHA locations must comply with the following:
A. Documentation requirements:
1) If fully vaccinated, shall show proof of vaccination NOTE: Acceptable proof of vaccination includes a signed record of immunization from a health care provider or pharmacy, a copy of the COVID-19 Vaccination Record Card (CDC Form MLS-319813_r, published on September 3, 2020), or a copy of medical records documenting the vaccination
2) If unvaccinated and granted a medical or religious exception, shall show negative COVID-19 test results dated within three calendar days prior to desired entry date. Test must be approved by the Food and Drug Administration (FDA) for emergency use or full approval. This includes tests available by a doctor’s order or an FDA approved over-the-counter test.
3) Documentation cited in this section shall be digitally or physically maintained on each contractor employee while in a VA facility and is subject to inspection prior to entry to VA facilities and after entry for spot inspections by Contracting Officer Representatives (CORs) or other hospital personnel.
4) Documentation will not be collected by the VA; contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.
B. Contractor employees are subject to daily screening for COVID-19 and may be denied entry to VA facilities if they fail to pass screening protocols. As part of the screening process contractors may be asked screening questions found on the following website: COVID-19 Screening Tool. Regularly check the website for updates.
1) Contractor employees who work away from VA locations, but who will have direct patient contact with VA patients shall self-screen utilizing the COVID-19 Screening Tool, in advance each day that they will have direct patient contact and in accordance with their person or persons who coordinate COVID-19 workplace safety efforts at covered contractor workplaces. Contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.
C. Contractor must immediately notify their COR or Contracting Officer if contract performance is jeopardized due to contractor employees being denied entry into VA Facilities.
SECTION C - CONTRACT CLAUSES
C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights—
(1) Within a reasonable time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at Federal Acquisition Regulation (FAR) 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(g) Invoice.
(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include—
(i) Name and address of the Contractor.
(ii) Invoice date and number.
(iii) Contract number, line-item number and, if applicable, the order number.
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered.
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading.
(vi) Terms of any discount for prompt payment offered.
(vii) Name and address of official to whom payment is to be sent.
(viii) Name, title, and phone number of person to notify in event of defective invoice; and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer—Other Than System for Award Management), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payment.—
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.
(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.
(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable.
(C) Affected line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(6) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if—
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days.
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—
(A) The date on which the designated office receives payment from the Contractor.
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in FAR 32.608-2 in effect on the date of this contract.
(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.
(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.
(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.
(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.
(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.
(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 41 U.S.C. 4712 and 10 U.S.C. 2409 relating to whistleblower protections; 49 U.S.C. 40118, Fly American; and 41 U.S.C. chapter 21 relating to procurement integrity.
(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:
(1) The schedule of supplies/services.
(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;
(3) The clause at 52.212-5.
(4) Addenda to this solicitation or contract, including any license agreements for computer software.
(5) Solicitation provisions if this is a solicitation.
(6) Other paragraphs of this clause.
(7) The Standard Form 1449.
(8) Other documents, exhibits, and attachments
(9) The specification.
(t) [Reserved]
(u) Unauthorized Obligations.
(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:
(i) Any such clause is unenforceable against the Government.
(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an “I agree” click box or other comparable mechanism (e.g., “click-wrap” or “browse-wrap” agreements), execution does not bind the Government or any Government authorized end user to such clause.
(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.
(2) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.
(v) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
(End of Clause) ADDENDUM to FAR 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES Clauses that are incorporated by reference (by Citation Number, Title, and Date), have the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available.
The following clauses are incorporated into 52.212-4 as an addendum to this contract:
C.2 52.219-14 LIMITATIONS ON SUBCONTRACTING (SEP 2021)
(a) This clause does not apply to the unrestricted portion of a partial set-aside.
(b) Definition. Similarly situated entity, as used in this clause, means a first-tier subcontractor, including an independent contractor, that—
(1) Has the same small business program status as that which qualified the prime contractor for the award (e.g., for a small business set-aside contract, any small business concern, without regard to its socioeconomic status); and
(2) Is considered small for the size standard under the North American Industry Classification System (NAICS) code the prime contractor assigned to the subcontract.
(c) Applicability. This clause applies only to—
(1) Contracts that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(2) Part or parts of a multiple-award contract that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(3) Contracts that have been awarded on a sole-source basis in accordance with subparts 19.8, 19.13, 19.14, and 19.15;
(4) Orders expected to exceed the simplified acquisition threshold and that are—
(i) Set aside for small business concerns under multiple-award contracts, as described in 8.405–5 and 16.505(b)(2)(i)(F); or
(ii) Issued directly to small business concerns under multiple-award contracts as described in 19.504(c)(1)(ii);
(5) Orders, regardless of dollar value, that are—
(i) Set aside in accordance with subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 8.405–5 and 16.505(b)(2)(i)(F); or
(ii) Issued directly to concerns that qualify for the programs described in subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 19.504(c)(1)(ii); and
(6) Contracts using the HUBZone price evaluation preference to award to a HUBZone small business concern unless the concern waived the evaluation preference.
(d) Independent contractors. An independent contractor shall be considered a subcontractor.
(e) Limitations on subcontracting. By submission of an offer and execution of a contract, the Contractor agrees that in performance of a contract assigned a North American Industry Classification System (NAICS) code for—
(1) Services (except construction), it will not pay more than 50 percent of the amount paid by the Government for contract performance to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract;
(2) Supplies (other than procurement from a nonmanufacturer of such supplies), it will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 50 percent subcontract amount that cannot be exceeded. When a contract includes both supplies and services, the 50 percent limitation shall apply only to the supply portion of the contract;
(3) General construction, it will not pay more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 85 percent subcontract amount that cannot be exceeded; or
(4) Construction by special trade contractors, it will not pay more than 75 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 75 percent subcontract amount that cannot be exceeded.
(f) The Contractor shall comply with the limitations on subcontracting as follows:
(1) For contracts, in accordance with paragraphs (c)(1), (2), (3) and (6) of this clause— [N/A] By the end of the base term of the contract and then by the end of each subsequent option period; or [X] By the end of the performance period for each order issued under the contract.
(2) For orders, in accordance with paragraphs (c)(4) and (5) of this clause, by the end of the performance period for the order.
(g) A joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph (e) of this clause will be performed by the aggregate of the joint venture participants.
(End of Clause)
C.3 SUPPLEMENTAL INSURANCE REQUIREMENTS
In accordance with FAR 28.307-2 and FAR 52.228-5, the following minimum coverage shall apply to this contract:
(a) Workers' compensation and employers liability: Contractors are required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 is required, except in States with exclusive or monopolistic funds that do not permit workers' compensation to be written by private carriers.
(b) General Liability: $500,000.00 per occurrences.
(c) Automobile liability: $200,000.00 per person; $500,000.00 per occurrence and $20,000.00 property damage.
(d) The successful bidder must present to the Contracting Officer, prior to award, evidence of general liability insurance without any exclusionary clauses for asbestos that would void the general liability coverage.
(End of Clause) C.4 VAAR 852.212-70 PROVISIONS AND CLAUSES APPLICABLE TO VA ACQUISITION OF COMMERCIAL ITEMS (APR 2020)
(a) The Contractor agrees to comply with any provision or clause that is incorporated herein by reference to implement agency policy applicable to acquisition of commercial items or components.