RFI 01 - Building 6 - Answers (001).pdf

PDF 80 KB Posted

Attached to
AMENDMENT 02 - Z1DA--Correct OIT Deficiencies 610A4-16-101 SB Federal contract opportunity
Solicitation number
36C25020B0037
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10

About this file

This document includes a request for information (RFI) response related to solicitation number 36C25020B0037 for correct information technology deficiencies at the Northern IN VA Healthcare System. The RFI response clarifies that building #6 is not included in the scope of work. It provides that the expected award date will be as soon as all required documents are received from the apparent awardee. For planning purposes, specification section 01 33 23 outlines that the review period for resubmittals is 15 working days, while the review period for requests for information is 10 working days. The related federal contract opportunity seeks a contractor to provide all tools, equipment, parts, materials, labor and supervision necessary to complete correct information technology deficiencies projects 610A4-16-101 at the specified location. The solicitation is issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10.

View the file

Other files for this federal contract opportunity

Other files attached to AMENDMENT 02 - Z1DA--Correct OIT Deficiencies 610A4-16-101 SB, newest first.
File Type Posted
RFI 02 - Answers.pdf PDF
36C25020B0037 0002.pdf PDF
Specifications Revised.pdf PDF
RFI Answer.pdf PDF
36C25020B0037 0001.pdf PDF
Sheets 41 to 60 from 610A4-16-101_Combined_Final-3.pdf PDF
Sheets 1 to 20 from 610A4-16-101_Combined_Final.pdf PDF
Sheets 21 to 40 from 610A4-16-101_Combined_Final-2.pdf PDF
Sheets 61 to 87 from 610A4-16-101_Combined_Final-4.pdf PDF
Drawings 7 of 11.pdf PDF
Drawings 1 of 11.pdf PDF
Drawings 6 of 11.pdf PDF
36C25020B0037_final.pdf PDF
Drawings 10 of 11.pdf PDF
Drawings 11 of 11.pdf PDF
Drawings 3 of 11.pdf PDF
Drawings 2 of 11.pdf PDF
Drawings 4 of 11.pdf PDF
Drawings 8 of 11.pdf PDF
Specifications.pdf PDF
Drawings 9 of 11.pdf PDF
RFI Form.doc DOC document
Wage Determination IN20200002 04032020.pdf PDF
Drawings 5 of 11.pdf PDF
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION (RFI)

PROJECT NUMBER: 610A4-16-101 Please ensure that before submitting questions or requests for clarification that you thoroughly read the solicitation, specifications, drawings and other pertinent documents.

When submitting questions on this project the Government requires contractors to specifically identify the specification and/or solicitation section(s) or drawing number(s) in reference to the question or request for clarification submitted. No question or request for clarification will be answered by the Government unless the above requirements are met. Failure to comply may prevent the Government from responding in a timely manner.

PROJECT TITLE: Correct OIT Deficiencies

PROJECT LOCATION:

Northern IN VA Healthcare System 2121 Lake Avenue Fort Wayne, IN 466805

TO:

Nathan Heikkinen, Contract Specialist Department of Veterans Affairs Network 10 Contracting Office 8888 Keystone Crossing, Suite 1100 Indianapolis, IN 46240 Nathan.heikkinen@va.gov

RFI NO.:01 DATE:7/14/2020

SPEC/DWG. REFERENCE(s):

REPLY NEEDED BY:

INFORMATION NEEDED:

1. During the Bid Walk on 07/09/2020, it was mentioned that Building #6 would not be in the Contract. However, in the Solicitation it is mentioned. Can you confirm if we shall bid any work to Build #6?

2. For planning and scheduling purposes, can you provide the expected date of award?

3. The specs do not specifically say the number of calendars days for RFI responses and submittal review and approval. This information in necessary for an accurate CPM schedule. Please advise.

REPLY:

1. During the walk-through we toured Building # 6, OIT Closet 107. It was the small IT Closet on the first floor.

The contractor is mistaken, the building referenced during the walk-through was Building #7 which is not in the plans or specifications.

2. Expected award date: As soon as practicable, considering potential awardee supplies all required documents.

3. (see attached) Specification 01 33 23 – 9 and 10, page 39 and 40, 1.10 VA REVIEW OF SUBMITTALS AND

RFIS, Paragraph’s:

C. Period of review for each resubmittal is the same as for initial submittal.

D. VA review period is 15 working days for submittals.

E. VA review period is 10 working days for RFIs.

REPLY FROM: Russell Becker COR

DATE: 15JUL2020

ATTACHMENTS: Specification 01 33 23 – 9 and10

COPY TO: Contracting