36C25020B0016-013.pdf
PDF Posted
- Attached to
- Upgrade OIT HVAC 583-16-122 Federal contract opportunity
- Solicitation number
- 36C25020B0016
About this file
This pre-solicitation notice announces an upcoming solicitation for construction services. The Richard L. Roudebush VA Medical Center intends to solicit bids to install new Liebert units, in-rack cooling units, chilled water lines and insulation, drain lines, a new sump pump, and lay-in ceiling grid and tiles. Additional requirements include demolishing existing piping, hangers, equipment and ceiling; installing controls sensors integrating into the existing FX building management system; firestopping wall penetrations; and performing leak testing and commissioning. The contractor must provide phasing, lookahead scheduling, waste diversion reporting, and training. The work must be done according to the contract drawings and specifications. As a 100% SDVOSB set-aside, the estimated value is between $500,000 and $1,000,000. The solicitation will be issued on January 25, 2020 via https://uscontractorregistration.com.
36C25020B0016 583-16-122 C FBD Drawing Set_Part4.pdf
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25020B0016 A00010.pdf | ||
| 36C25020B0016 0008.docx | DOCX document | |
| 36C25020B0016 A00007.docx | DOCX document | |
| Drawings.pdf | ||
| Specs.pdf | ||
| 36C25020B0016 0006.docx | DOCX document | |
| 36C25020B0016-0005000.docx | DOCX document | |
| 36C25020B0016-0004000.docx | DOCX document | |
| 36C25020B0016-0003000.docx | DOCX document | |
| 36C25020B0016-0003001.pdf | ||
| 36C25020B0016-0002000.docx | DOCX document | |
| 36C25020B0016-0002001.docx | DOCX document | |
| 36C25020B0016-0001000.docx | DOCX document | |
| 36C25020B0016-007.pdf | ||
| 36C25020B0016-011.pdf | ||
| 36C25020B0016-010.pdf | ||
| 36C25020B0016-006.pdf | ||
| 36C25020B0016-008.pdf | ||
| 36C25020B0016-005.pdf | ||
| 36C25020B0016-002.docx | DOCX document | |
| 36C25020B0016-003.doc | DOC document | |
| 36C25020B0016-009.pdf | ||
| 36C25020B0016-004.docx | DOCX document | |
| 36C25020B0016-014.txt | TXT text file | |
| 36C25020B0016-012.pdf |
Show all 25
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2020 E. Washington Boulevard Suite 200 Fort Wayne, Indiana 46803
PH: 260.424.4830
www.viridian-design.netV IRIDIAN
ARCHITECTURAL DESIGN INC.
All concepts, ideas, design elements, plans, and details as shown on this document are the sole property of Viridian Architectural Design Inc. and shall not be used for any purpose without prior expressed written consent. The Contracting Officer Representative shall be permitted to retain copies for information and reference.
ROOFTOP UNITRTU-
DUCT WORK (UNLINED)
DUCT WORK (LINED)
VARIABLE AIR VOLUME TERMINAL BOX
DIFFUSER
DUCT COIL
FAN POWERED VAV BOX WITH REHEAT
EXHAUST OR RETURN GRILLE
RECTANGULAR DUCTXX"xXX"
ROUND DUCTX"Ø
DUAL DUCT TERMINAL BOX
SHUT-OFF TERMINAL BOX W/ REHEAT
SHUT-OFF TERMINAL BOX
FIRE DAMPER
TRANSFER AIR GRILLETG-
UNIT VENTILATOR
ABOVE FINISHED FLOOR
FLAT OVAL DUCT
UV-
VAV-
A.F.F.
XX"xXX"Ø
UNIT HEATERUH-
PRESSURE RELIEF VALVE
PRESSURE REGULATING VALVE
EXPANSION LOOP
TURBINE FLOWMETER
ORIFICE FLOWMETER
SUPPLY REGISTER
TERMINAL BOX
SUPPLY FANSF-
SR-
TB-
RELIEF VENTRV-
T
H
SECURITY THERMOSTAT
HUMIDISTAT
AV
MV
S SMOKE SENSOR
MANUAL AIR VENT
AUTOMATIC AIR VENT
HUMIDIFIERH-
ELECTRIC RADIATIONRAD-
RETURN AIR GRILLE
RETURN REGISTER
ROOF CAP
RELIEF FAN
RC-
RF-
RG-
RR-
T
T
S
P
P PRESSURE SENSOR
ELECTRONIC THERMOSTAT
PNUEMATIC THERMOSTAT
FLEXIBLE DUCT
BACKDRAFT DAMPER
HEAT EXCHANGER
LOUVER
PUMP
CONDITIONING UNIT
HX-
L-
P-
HEATING VENTILLATION AIRHVAC-
P
MANUAL AIR BALANCING DAMPER
MANUAL OPPOSED BLADE DAMPER
ACTUATOR
PRESSURE GAUGE
TIE-IN
INLINE PUMP EXHAUST GRILLEEG-
EXPANSION TANK
EXHAUST REGISTER
FINNED TUBE RADIATION
FIRE DAMPER
ER-
ET-
FD-
FTR-
PRESSURE & TEMPERATURE TEST PLUG
THERMOMETER
STRAINER
TEMPERATURE WELL
DUCT COILDC-
EXHAUST FANEF-
D-
CUH-
B- BOILER
DIFFUSER
CABINET UNIT HEATER
METER
PIPING RISE
PIPING DROP
THREADED HOSE CONNECTION W/ CAP
INLINE DROP
CHILLED WATER SUPPLY PIPING
CHILLED WATER RETURN PIPING
AS-
AHU-
AFMS-
AC-
CWR
AIR FLOW MEASURING STATION
AIR CONDITIONER
CONDENSER WATER RETURN
AIR HANDLING UNIT
AIR SEPARATOR
AUTOMATIC FLOW CONTROL VALVE
UNION
WITH P & T PORTS
BLIND FLANGE CONNECTION
WITH P & T PORTS
D
HWS
CHWS
HWR HOT WATER RETURN PIPING
HOT WATER SUPPLY PIPING
CONDENSATE DRAIN
CWS CONDENSER WATER SUPPLY
CHWR
PNEUMATIC 3-WAY VALVE
PNEUMATIC 2-WAY VALVE
ELECTRONIC 3-WAY VALVE
ELECTRONIC 2-WAY VALVE
CHECK VALVE
GLOBE VALVE
STEAMS
COND STEAM CONDENSATE
BALL VALVE
BUTTERFLY VALVE
MECHANICAL SYMBOL SCHEDULE
DUCT WORK (DOUBLE WALL/PERFORATED INNER)
NEW MECHANICAL EQUIPMENT
NEW MECHANICAL DUCTWORK
EXISTING MECHANICAL EQUIPMENT AND
DUCTWORK TO REMAIN
M
M
SMOKE/FIRE DAMPER
FD
SFD
LRP- LINEAR RADIANT PANEL
SFD- SMOKE/FIRE DAMPER
O.A.C. OPENING ABOVE CEILING
ST
T
HEAT PUMPHP-
MAU- MAKE UP AIR UNIT
GATE VALVE
FLANGE CONNECTION
PIPING SLEEVE
FLOW SWITCHF
SPHERICAL RUBBER VIBRATION ISOLATOR
PIPING INCREASER
T STEAM TRAP
FLOW METER WITH WELL
MANUAL FLOW CONTROL VALVE
PLUMBING SYMBOL SCHEDULE
AW
AW
SAN
SAN
ST
ST
G
RAW
HOT WATER
COLD WATER
VENT
GAS
BELOW GRADE ACID WASTE
ABOVE GROUND ACID WASTE
HOT WATER RECIRC
DOMESTIC WATER (RAW)
STORM DRAIN BELOW FLOOR
STORM DRAIN ABOVE FLOOR
SANITARY DRAIN BELOW FLOOR
SANITARY DRAIN ABOVE FLOORBALL VALVE
BUTTERFLY VALVE
PRESSURE REDUCING STATION
GATE VALVE
GLOBE VALVE
TEMPERATURE MIXING VALVE
GAS COCK
GAS TURRET
COMPRESSED AIR TURRET
CHECK VALVE
IN LINE PUMP
STRAINER
AUTOMATIC FLOW VALVE
UNION
ACTUATOR
METER
PIPING DROP
INLINE PIPING DROP
PIPING RISE
PIPE CAP
PIPE BREAK
WALL CLEANOUT/ END FERRULE CLEANOUT
TIE-IN
THERMOMETER
WATER HAMMER ARRESTOR TAG
(SHOCK ABSORBER)
SHOCK ABSORBER
CLEAN OUT
FLOOR DRAIN
FLOOR SINK
ROOF DRAIN
VENT THROUGH ROOF
WALL HYDRANT/ HOSE BIBB
SHOWER HEAD
REDUCED PRESSURE PRINCIPLE
BACKFLOW PREVENTER
X
M
M
CLEANOUT
DRINKING FOUNTAIN
EMERGENCY DRENCH SHOWER
EMERGENCY EYE WASH
EXPANSION TANK
ELECTRIC WATER COOLER
ELECTRIC WATER HEATER
HOSE BIBB
LAVATORY
MOP BASIN
ROOF DRAIN
REDUCED PRESSURE PRINCIPLE
BACKFLOW PREVENTER
SINK
SHOWER
SUMP PUMP
TRENCH DRAIN
TEMPERATURE MIXING VALVE
URINAL
VENT THROUGH ROOF
WALL BOX
WATER CLOSET
WALL HYDRANT
YARD HYDRANT
SUFFIX INDICATES HANDICAP
ACCESSIBLE
ABOVE FINISHED FLOOR
FLOOR DRAIN
GARBAGE DISPOSER
GAS WATER HEATER
CO-
DF-
EDS-
EEW-
ET-
EWC-
EWH-
FD-
GD-
GWH-
HB-
L-
MB-
RD-
RPBP-
S-
SH-
SP-
TD-
TMV-
U-
VTR-
WB-
WC-
WH-
YH-
"H"
A.F.F.
T
PRESSURE REDUCING VALVE
MANUAL FLOW CONTROL VALVE
COLD WATERCW-
HUB DRAINHD-
ACCU- AIR COOLED CONDENSING UNIT
TERMINAL UNITTU-
S T TEMPERATURE SENSOR
F FLOOD SENSOR
CWD CITY WATER DRAIN
Point Description Air Conditioning Units (AC-1 through 6) Space Served
INPUT/OUTPUT SUMMARY TABLE
HARDWARE
OUTPUT (O)
DGTL
C on tr ol
R el ay S ol en oi d
ANALOG
Pn eu m at ic T ra ns du ce r El ec tr ic al
T ra ns du ce r
-2 m a or
-1
V
D C
INPUT (T, D, V, C)
DIGITAL
Pr es su re
S w itc h Fl ow S w itc h C on ta ct C lo su re A ux ili ar y C on ta ct
KW
M et er C on ta ct
ANALOG
Te m pe ra tu re
R el at iv e
H um id ity
S et
P oi nt A dj us tm en t Ps ig
Ps ia
Ps id
IN
H
O
Fl ow
El ec tr ic al C ur re nt F lo w
Po si tio n
Tr en di ng
ALARMS
DGTL
Eq ui pm en t S ta tu s
M ai nt en an ce
ANALOG
H ig h Li m it Lo w L im it
(T em pe ra tu re
R un
T im e
SOFTWARE
EMCS FUNCTIONS
S ch ed ul ed O n/ O ff O pt im um S ta rt
/S to p D em an d Li m iti ng
To ta liz at io n
D ay
/N ig ht S et ba ck Ec on om iz er
V en til at io n/
R ec irc ul at io n D ire ct
D gt al T em pe ra tu re C on tr ol En th al py G lo ba
l) H ea tin g or C oo lin g R es et B oi le r
O pt im iz at io n
O .A
R es et C hi lle r O pt im iz at io n
C hi lle d
W at er R es et
V A V C on tr ol V ar ia bl e S pe ed P um pi ng Ic e S to ra ge
C on tr ol
Le ad
/L ag
C on tr ol
Li gh tin g
C on tr ol
C ol or G ra ph ic s
It em
Liquid Sensors
SEQUENCE OF OPERATIONS FOR HVAC CONTROLS
1. ALARMS
A. Coordinate with the owner to identify alarms as "general" or " critical". General alarms will only be displayed at the computer graphics. Critical alarms will be displayed in the computer graphics program and dialed-out, emailed, or text messaged to pre-programmed telephone numbers and email address via the internet.
2. MONITORING SEQUENCES
A. Monitor space temperature of C-B022 and C-B027 and generate an alarm message at the computer graphics if space temperature falls below 50 deg F or rises above 76 deg F during occupied mode. Generate a critical alarm if space temperature falls below 40 deg F or rises above 80 deg F during occupied or unoccupied mode.
B. Connect to air conditioning equipment interface to read all available points.
Coordinate with the VA to determine which points should be displayed graphically on the building automation system. Air conditioning equipment factory controls are to provide the sequence of operation to maintain space temperature and humidity set points. Monitor air conditioning equipment capacity and generate an alarm message if an air conditioner reaches 80% of its maximum capacity for at lease 15 minutes (adjustable).
C. Monitor liquid sensors in floor space and send an alarm if liquid is detected.
D. Connect to Starline Modbus to read all available points. Coordinate with the VA to determine which points should be displayed graphically on the building automation system.
E. Monitor status of city water changeover valves. Valves are not to be adjustable from the BMS. Valves are to be controlled by switches in the space. The switches can allow either AC-3, AC-4, AC-5, and AC-6, or a combination of AC-2 and two in-row units (AC-3, AC-4, AC-5, or AC-6) to operate on city water but not all units can operate on city water at the same time. AC-1 may be operated on city water at any time independent of the other units. Include all wiring and switches as part of the controls contractor's work.
3. SINGLE DUCT SHUT OFF VAV TERINAL UNIT WITH HOT WATER REHEAT
A. Modulate open primary air valve with a rise in space temperature. With a fall in space temperature, modulate primary air valve towards the minimum setting.
With a continued fall in space temperature below the heating set point, modulate open the hot water coil control valve, when valve is 100% open, modulate air valve increasing air flow to maintain space heating set point. If hot water is not available, close primary air valve 100% with a fall in space temperature below heating set point.
4. SINGLE DUCT SHUT OFF VAV TERMINAL UNIT WITHOUT REHEAT
A. Occupied Mode: Modulate open primary air valve with a rise in space temperature. With a fall in space temperature, modulate primary air valve towards the minimum setting.
5. PUMP CONTROL SEQUENCE
A. P-1 & 1-A (Chilled Water Loop): Variable speed lead/Lag back-up operation. Lead pump is to run continuously. Modulate lead pump with a 4-20mA output to variable speed drive to maintain a differential pressure (adjustable) across the supply and return mains at the location shown. With a failure of the lead pump to establish flow within 15 seconds after a call to operate, start the lag pump and generate an alarm message reading "PRIMARY CHILLED WATER LEAD PUMP FAILURE" to be automatically displayed in computer graphics and dial out, text messaged, and email to pre-programmed addresses and/or numbers. Alternate lead and lag pumps every seven days.
B. P-2 & 2-A (Chilled Water Secondary Loop): Variable speed lead/Lag back-up operation. Lead pump is to run continuously. Modulate lead pump with a 4-20mA output to variable speed drive to maintain a differential pressure (adjustable) across the supply and return mains at the location shown. With a failure of the lead pump to establish flow within 15 seconds after a call to operate, start the lag pump and generate an alarm message reading "SECONDARY CHILLED WATER LEAD PUMP FAILURE" to be automatically displayed in computer graphics and dial out, text messaged, and email to pre-programmed addresses and/or numbers.
Alternate lead and lag pumps every seven days.
6. CITY WATER MANUAL CHANGEOVER SEQUENCE
A. A switch located in the IT space will allow the VA to manually switch to city water by opening automatic city water valves and closing chilled water valves. Each unit will have its own changeover switch. The BMS will only monitor the status of the valves and limit the maximum number of units that can operate on city water
Pumps P-1 & 1-A P-2 & 2-A
Chilled Water Primary Loop
CHWS
CHWR
Secondary Loop Supply Return
Shutoff VAV TU-6-22 Primary Air Space Served
Primary Air HW Coil Valve Discharge Air
Shutoff VAV TU-6-21
Space Served
Starline Modbus
A COMPRESSED AIR
City Water Changeover Valves simultaneously.
2020 E. Washington Boulevard Suite 200 Fort Wayne, Indiana 46803
PH: 260.424.4830
www.viridian-design.netV IRIDIAN
ARCHITECTURAL DESIGN INC.
All concepts, ideas, design elements, plans, and details as shown on this document are the sole property of Viridian Architectural Design Inc. and shall not be used for any purpose without prior expressed written consent. The Contracting Officer Representative shall be permitted to retain copies for information and reference.
DIFFUSER - SEE PLANS FOR
TYPES AND SIZES.
SUPPORT FROM CEILING
GRIDWORK OR BUILDING
STRUCTURE.
MANUAL BALANCE DAMPER LEAVE HANDLE
CLEAR FOR BALANCING, EXTEND BLADE
SHAFT TO PREVENT EXTERNAL INSULATION
DAMAGE FROM HANDLE
SEE PLANS FOR
DUCT SIZES
FLEXIBLE DUCT. KEEP DUCT
AS SHORT AS POSSIBLE.
MAX. LENGTH 6 FT. MAY BE
LOCATED IN VERTICAL DROP
TO DIFFUSER
RIGID METAL ELBOW USE
FOR CHANGES IN
DIRECTION
NTS
TYPICAL CEILING DIFFUSER INSTALLATION DETAIL
S T
P
CHWS
CHWR
55°-65°F
70°-80°F
A
T
SB
FROM PUMPED LOOP
2"
2-POSITION ELECTRIC SOLENOID VALVE
UNION
FROM CITY WATER SUPPLY
ROUTE TO STORM DRAIN
SHUT-OFF VALVE
3-WAY VALVE
REFRIGERANT HOT GAS
REFRIGERANT LIQUID
IN ROW AC UNIT
CONNECTION POINT FOR CHWR PIPING.
CONNECTION POINT FOR CITY WATER DRAIN PIPING.
CONNECTION POINT FOR CHWS PIPING.
CONNECTION POINT FOR CITY WATER SUPPLY PIPING.
IN ROW AIR CONDITIONING UNIT, ALL COMPONENTS INSIDE DASHED LINE ARE
PROVIDED BY THE MANUFACTURER. CONNECTION POINTS FOR CHILLED WATER
SUPPLY AND RETURN AND CITY WATER SUPPLY AND DRAIN ARE INDICATED.
PRESSURE AND TEMPERATURE TRANSDUCER SHALL BE CONNECTED TO THE
AC UNIT PROGRAMABLE CONTROLLER TO OPEN AND CLOSE THE SOLENOID
VALVES NUMBERED 1 THROUGH 4 .
A
B
NTS
IN ROW AC UNIT SCHEMATIC PIPING DETAIL
WATER COOLED BRAZED PLATE CONDENSER
8"
8"
3"
3"
CHWS
CHWR
16" CHWS16" CHWR
CHWS
CHWR
T S
T S
P S
P S
S
T 80 GPM 3"
3"
3"
CHWS
CHWR
3"
2-1/2"
P-2 P-2A
3" CHWS TO AC-4, AC-5, AND AC-6
2" CHWS TO AC-3
2" CHWR FROM AC-3
CHWR
CHWS
T S
P-1A
P-1
2-1/2" CHWR FROM AC-1
2-1/2" CHWS TO AC-1
2-1/2" CHWR FROM AC-2
2-1/2" CHWS TO AC-2
3"
2-1/2"
NTS
COMPUTER ROOM AIR CONDITIONER CHILLED WATER SCHEMATIC
REFRIGERANT HOT GAS
REFRIGERANT LIQUID
CHWR
CHWR
CHWR
CHWS
CHWS
CHWR
CHWS 45°-55°F
CHWR 55°-65°F
THERMISTOR
3-WAY VALVE
COOLED
WATER
CONDENSER
WATER
CHILLED
COIL
REFRIGERANT HOT GAS
REFRIGERANT LIQUID
COOLED
WATER
CONDENSER
NTS
DOWN FLOW AC UNIT SCHEMATIC PIPING DETAIL
DIFFERENTIAL
PRESSURE
SENSOR
DIGITAL
THERMOMETER
2"
1-1/2"
2"
AUTOMATIC FLOW CONTROL VALVE
2-1/2"
T S
TEMPERATURE SENSOR
CONNECTION POINT FOR CHWR PIPING.
CONNECTION POINT FOR CHWS PIPING.
CONNECTION POINT FOR CITY WATER SUPPLY.
CONNECTION POINT FOR CITY WATER DRAIN.
DOWN FLOW AIR CONDITIONING UNIT, ALL
COMPONENTS INSIDE DASHED LINE ARE
PROVIDED BY THE MANUFACTURER.
CONNECTION POINTS FOR CHILLED WATER
SUPPLY AND RETURN AND CITY WATER SUPPLY
AND DRAIN ARE INDICATED.
1 4
CHWR
CHWS
CHWS
CHWR
NEENAH R-4380 GRATING
SURE SEAL TRAP SEALER
DEEP SEAL TRAP
HD-1, 4" WASTE
6" MIN. ABOVE SURE
SEAL TRAP SEALER
FLOOR
NTS
PIPE HANGERS - PROVIDE DOUBLE DEFLECTION
NEOPRENE (TYPE HN) FOR FIRST TWO ON EACH
SIDE OF PUMP (SEE NOTE NO. 1)
PRESSURE GAGE
1/2" [15mm]
STRAINERFLEXIBLE CONNECTION
BALL OR
BUTTERFLY TYP.
NOTES:
1. SUPPORT PUMP FROM PIPING ONLY. DO NOT SUPPORT PUMP FROM MOTOR.
IN-LINE PUMPS - CONNECTIONS
BALANCING DEVICE
NTS
HUB DRAIN DETAIL
NOTES:
NOTES:
T
T
T
T
FLEXIBLE HOSE TO
ALLOW MOVEMENT
OF UNIT
FLEXIBLE HOSE TO
ALLOW MOVEMENT
OF UNIT
B
3" CHWR FROM AC-4, AC-5, AND AC-6
A
SS
P
SS
P
DIFFERENTIAL PRESSURE SENSOR
2-HOUR FIRE STOPPING SYSTEM
AT ALL FLOOR PENETRATIONS
SS
T
T
STRAINER
TO STORM DRAIN
FROM CITY WATER SUPPLY
STRAINER
A
TO EXISTING AIR CONDITIONER IN UPS C-B017
3/4"
AIR CONDITIONING UNIT SCHEDULE
TAG
AC-1
AC-2
AC-3
AC-4
AC-5
AC-6
REMARKS:
1. PROVIDE WITH INTEGRAL INFRARED HUMIDIFIER AND ELECTRIC REHEAT.
2. PROVIDE WITH DIGITAL COMPRESSOR FULLY MODULATING BETWEEN 100% AND 20% CAPACITY, VARIABLE SPEED FAN, AND 12" FLOOR STAND.
3. PROVIDE WITH BACNET INTERFACE TO ALLOW THE BUILDING AUTOMATION SYSTEM TO MONITOR AND DISPLAY UNIT STATUS AND ALARMS.
4. DOWN FLOW UNITS ARE TO BE PROVIDED DISASSEMBLED INTO MODULES AND REASSEMBLED IN FINAL INSTALLATION LOCATION.
5. PROVIDE WITH INTEGRAL CANISTER HUMIDIFIER AND ELECTRIC REHEAT.
6. PROVIDE AND INSTALL WITH THREE RACK MOUNTED SENSORS AT LOCATION TO BE DETERMINED IN THE FIELD.
7. PROVIDE AND INSTALL WITH SUPPLY AND RETURN AIR TEMPERATURE SENSORS AND A HUMIDITY SENSOR.
8. PROVIDE AND INSTALL WITH SUPPLY AIR TEMPERATURE SENSOR ON 15 FOOT CABLE. INSTALL SENSOR UNDER THE FLOOR IN FRONT OF THE UNIT AS FAR FROM THE UNIT AS POSSIBLE. MAINTAIN A DISCHARGE AIR TEMPERATURE OF 62 DEGREES (ADJUSTABLE).
9. PROVIDE WITH VNSA NETWORK SWITCH TO NETWORK UNITS.
CONFIGURATION
DOWN FLOW
DOWN FLOW
IN-ROW
IN-ROW
IN-ROW
IN-ROW
AIR FLOW (CFM)
SUPPLY
RETURN
OA
ESP
0.2 0.2
BLOWER SECTION
QUANTITY
FAN TYPE
EC PLUG
EC PLUG
EC PLUG
EC PLUG
EC PLUG
EC PLUG
ELECT
208/3 208/3 208/3 208/3 208/3 208/3
COOLING (CHILLED WATER)
TON (NOMINAL)
20.0 20.0
MBH (TOT)
MBH (SEN)
EA DB/WB
75/61 75/61
LA DB/WB
57.4/53.9 57.4/53.9
EWT
LWT
GPM
ROWS
FPI
WPD (FT H2O)
COOLING (DX)
TON (NOMINAL)
20.0 20.0 10.0 10.0 10.0 10.0
MBH (TOT)
MBH (SEN)
EA DB/WB
75/61 75/61 80/59 80/59 80/59 80/59
LA DB/WB
54.6/51.5 54.6/51.5 50.1/46.0 50.1/46.0 50.1/46.0 50.1/46.0
EWT
LWT
GPM
ROWS
FPI
WPD (FT H2O)
COOLING (CITY WATER BACK-UP)
MBH (TOT)
MBH (SEN)
EWT
LWT
GPM
WPD (FT H2O)
FILTER MEDIA
DEPTH
4" 4" 4" 4" 4" 4"
RATING
MERV 8
MERV 8
MERV 8
MERV 8
MERV 8
MERV 8
REMARKS
1, 3, 4, 7, 8, 9 1, 3, 4, 7, 8, 9 2, 3, 5, 6, 7, 9 2, 3, 5, 6, 7, 9 2, 3, 5, 6, 7, 9 2, 3, 5, 6, 7, 9
DIFFUSER SCHEDULE
TAG
D-1 D-2 D-3
RG-1
RG-2
EG-1
TA-1
REMARKS:
1. PROVIDE ALL NECESSARY TRIM AND BORDERS FOR INSTALLATION INTO CEILING TYPES AND WALLS. REFER
TO ARCHITECTURAL DRAWINGS FOR ROOM FINISHES.
2. PROVIDE AND INSTALL DUCT TRANSITION FITTINGS AS REQUIRED FOR CONNECTION TO DIFFUSERS AND GRILLES.
3. PROVIDE WITH INTEGRAL VOLUME DAMPER.
NECK
8"
10" 24" X 6"
6" X 6" 12" X 12"
6" X 6"
24" X 6"
FACE
12" x 12" 24" x 24" 26" X 8"
12" x 12" 24" x 24"
12" x 12"
26" X 8"
TYPE
PERFORATED
PERFORATED
LOUVERED
PERFORATED
PERFORATED
PERFORATED
LOUVERED
MAX CFM
MAX PD
(TOTAL)
0.05" 0.05" 0.03"
0.10" 0.10"
0.10"
0.03"
MAX NC
THROW
(FEET)
MATERIAL
STEEL
STEEL
STEEL
STEEL
STEEL
STEEL
STEEL
REMARKS
1, 2 1, 2 1, 3
1, 2 1, 2
1, 2
1, 3
S
R
P&T PORT
AUTOMATIC FLOW
CONTROL VALVE WITH P&T
PORTS
2-WAY CONTROL VALVE
LINE SIZE STRAINER WITH
THREADED HOSE
CONNECTION AND CAP
NTS
TERMINAL UNIT 2-WAY HEATING COILS
NTS
MAXIMUM CAPACITY SIGN DIAGRAM3
THE MAXIMUM CITY WATER
COOLING CAPACITY IS 40 TONS
PUMP SCHEDULE
TAG
P-1 P-1A P-2 P-2A
SP-1
SP-2
REMARKS:
1. PUMPS ARE TO BE LEAD/LAG OPERATION WITH 100% BACK-UP.
2. PUMPS ARE TO BE CONTROLLED WITH VARIABLE FREQUENCY DRIVE.
3. PUMPS ARE FLOAT CONTROLLED.
4. PROVIDE CORD LENGTH TO NEARBY RECEPTACLE. PROVIDE INLINE CHECK VALVE.
TYPE
INLINE
INLINE
INLINE
INLINE
SUMP
SUMP
FLOW
(GPM)
HEAD
(FT)
PUMP EFF
(+/- 5%)
RPM
HP
0.75 0.75
BHP
2.37 2.37 2.72 2.72
ELEC.
(V/PH)
208/3 208/3 208/3 208/3 115/1 115/1
SERVICE
PRIMARY LOOP (AC-1, 2 & AC-3, 4, 5, 6)
PRIMARY LOOP (AC-1, 2 & AC-3, 4, 5, 6)
AC-3, 4, 5, 6
AC-3, 4, 5, 6
SUMP PUMP
SUMP PUMP
REMARKS
1, 2 1, 2 1, 2 1, 2 3, 4 3, 4
VARIABLE AIR VOLUME TERMINAL SCHEDULE
TAG
TU-6-21
TU-6-22
TU-6-22A
REMARKS:
1. SHEETMETAL CONTRACTOR SHALL TRANSITION DUCT AS REQUIRED FOR INLET AND DISCHARGE CONNECTIONS.
2. UNIT SHALL BE DIRECT DIGITAL CONTROLLED AND PRESSURE INDEPENDENT.
3. UNIT SHALL BE PRESSURE INDEPENDENT/ CONSTANT VOLUME.
TYPE
SHUT OFF
SHUT OFF
SHUT OFF
MAX
AIR (CFM)
MINIMUM
AIR (CFM)
MAX
INLET
S.P.
1.5" 1.5" 1.5"
INLET
SIZE (IN)
MAX
NC
HEATING COIL
HEATING
AIR (CFM)
HEATING
MBH
3.5
GPM
0.5
EAT
LAT
EWT
LWT
AIR
P.D. (IN)
0.05 0.12 0.05
WATER
P.D. (IN)
0.75 0.75
AREA
SERVED
IMS C-B027A
IMS MECH C-B027
TELECOM C-B022
REMARKS
1, 2 1, 2 1, 3
NTS
DUPLEX SUMP PUMPS8
UNION
H R
FIR
E B A R R
IER
2HR FIRE BARRIER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
2HR FIRE BARRIER
H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R
2HR FIRE BARRIER
H R
FIR
E B A R R
IER
2HR FIRE BARRIER
2 5
2020 E. Washington Boulevard Suite 200 Fort Wayne, Indiana 46803
PH: 260.424.4830
www.viridian-design.netV IRIDIAN
ARCHITECTURAL DESIGN INC.
All concepts, ideas, design elements, plans, and details as shown on this document are the sole property of Viridian Architectural Design Inc. and shall not be used for any purpose without prior expressed written consent. The Contracting Officer Representative shall be permitted to retain copies for information and reference.
SCALE: 1/16" = 1'-0"
MECHANICAL - DEMOLITION PLAN - PARTIAL SUB BASEMENT/CRAWL SPACE OVERALL PLAN
MD100
REMOVE EXISTING CITY WATER PIPING BACK TO THIS LOCATION.
REMOVE EXISTING PIPING, FITTINGS, VALVES, STRAINERS, AND PNEUMATIC ACTUATED
VALVES. VALVES ARE TO BE SALVAGED AND TURNED OVER TO THE VA.
REMOVE EXISTING CHILLED WATER SUPPLY PIPING BACK TO THIS LOCATION.
REMOVE EXISTING CHILLED WATER RETURN PIPING BACK TO THIS LOCATION.
PATCH / REPAIR FLOOR TO MATCH EXISTING, ADJACENT FLOOR IN CONSTRUCTION.
REMOVE EXISTING HUB DRAIN AND SANITARY DRAIN PIPING. REPAIR ABANDONED
FLOOR OPENING TO MATCH EXISTING, ADJACENT FLOOR IN CONSTRUCTION.
EXISTING HUB DRAIN AND SANITARY DRAIN PIPING TO SANITARY BRANCH TO REMAIN.
PATCH / REPAIR WALL OPENINGS TO MATCH EXISTING, ADJACENT WALL IN
CONSTRUCTION AND FIRE RATING.
REMOVE EXISTING CLEANOUT AND PREPARE PIPE FOR NEW WORK.
REMOVE COMPRESSED AIR PIPING BACK TO COMPRESSOR.
REMOVE EXISTING SUMP PUMPS AND TURN OVER TO VA. REMOVE PUMP DISCHARGE
PIPING TO ABOVE WYE FITTING. TURN CHECK VALVES OVER TO VA & MAKE READY FOR
NEW WORK.
THESE NOTES APPLY TO ALL DEMOLITION DRAWINGS AND TO ALL CONTRACTORS AND /
OR SUBCONTRACTORS THAT WORK WITHIN THIS BUILDING.
1. ALL MATERIALS INDICATED AS DASHED ARE TO BE REMOVED. THIS INCLUDES ALL
FINISHES AND MATERIALS NOT SPECIFICALLY CALLED OUT BUT PERTAINING TO THE
INTENDED SCOPE.
2. CONTRACTORS SHALL BE RESPONSIBLE FOR VISITING THE SITE TO BECOME FAMILIAR
WITH THE EXISTING CONDITIONS. THESE DEMOLITION SHEETS SHALL SERVE TO AID THE
CONTRACTOR IN THE EVALUATION OF THE EXTENT OF DEMOLITION: BUT SHALL NOT BE
HELD TO BE ALL INCLUSIVE.
3. CONTRACTORS SHALL FIELD INSPECT ALL DEMOLITION WORK PRIOR TO REMOVAL, TO
ENSURE SUCH REMOVAL DOES NOT IMPAIR STRUCTURAL INTEGRITY OF THE EXISTING
SITE OR BUILDING. IF THE INSPECTION INDICATES THAT THE STRUCTURAL INTEGRITY
MAY BE COMPROMISED, NOTIFY THE CONTRACTING OFFICER REPRESENTATIVE (COR)
IMMEDIATELY.
4. GENERAL CONTRACTOR TO COORDINATE ALL ASSOCIATED WORK WITH ALL
SUB-CONTRACTORS.
5. ALL CONTRACTORS TO VERIFY STAGING AND STORAGE LOCATIONS OF ALL MATERIALS
AND EQUIPMENT WITH COR PRIOR TO BEGINNING OF CONSTRUCTION.
6. ALL CONSTRUCTION AREAS AND ASSOCIATED WORK AREAS SHALL BE KEPT CLEAN BY
THE CONTRACTOR - DAILY.
7. PROTECT ADJACENT SPACES AND EXISTING EQUIPMENT FROM DEMOLITION DEBRIS
AND DAMAGE DURING CONSTRUCTION.
8. CONTRACTOR TO ENSURE NO DEMOLITION DEBRIS IS LEFT ON SITE PRIOR TO
COMPLETING ALL DEMOLITION WORK.
9. ALL CONTRACTORS SHALL BE RESPONSIBLE FOR ANY DAMAGES CAUSED BY THEM
DURING THE CONSTRUCTION PROCESS. IN THE EVENT OF ANY DAMAGES CONTRACTOR
IS TO CONTACT THE COR IMMEDIATELY; PRIOR TO THE END OF THE DAY OF
CONSTRUCTION.
10. ALL CONTRACTORS TO COORDINATE RELOCATION AND STORAGE OF EXISTING AND
DEMOLISHED EQUIPMENT AND MATERIALS WITH THE COR PRIOR TO THE START OF
CONSTRUCTION.
11. REMOVAL OF EXISTING EQUIPMENT SHALL BE COMPLETED WHILE ADJACENT EQUIPMENT
IS IN OPERATION. SMOKE AND DUST CONTROL MEASURES SHALL BE IN PLACE PRIOR
TO REMOVAL OF HVAC EQUIPMENT, DUCTWORK, PIPING, AND SUPPLY/RETURN GRILLES.
NOT TO SCALE
SUBBASEMENT KEY PLAN
N
RICHARD L. ROUDEBUSH
VA MEDICAL CENTER
RENOVATION
AREA
NOTE:
PROVIDE FIRE STOPPING AT ALL NEW PENETRATIONS OF FLOOR. PATCH ALL
ABANDONED OPENINGS AND MAINTAIN FIRE RATING OF FLOOR.
NOTE:
CONTRACTOR IS TO PROTECT ALL ADJACENT SPACES, EQUIPMENT, AND FINISHES
DURING CORE DRILLING AND OTHER WORK. COORDINATE AND SCHEDULE ALL CORE
DRILLING AND SHUTDOWNS WITH COR.
RA
M
P
DO
W N
RAMP
DOWN
EXISTING
TELECOM
C-BO22EXISTING
LOBBY
EXISTING
ELEVATOR P1
EXISTING
ELEVATOR P2
EXISTING
ELEVATOR P3
EXISTING
ELEVATOR P4
EXISTING
SERVICE
ELEVATOR S6
EXISTING
SERVICE
ELEVATOR S5
EXISTING
CORRIDOR
CB-35EXISTING
PAPER
STORAGE
C-B177
EXISTING
TELECOM
C-B178
EXISTING
MECH
C-B021
EXISTING
CORRIDOR
CB-38
EXISTING
CLOSET
C-B018
EXISTING
SWITCH GEAR
C-B019
EXISTING
STAIR-1
UPDO
W
N
EXISTING
UPS
C-BO17
EXISTING
IMS ENTRY
EXISTING
IMS
C-B027A
EXISTING
IMS MECH
C-B027
EXISTING
REPAIR AND
DEVELOPMENT
C-B031
EXISTING
OI&T SYSTEMS
C-B026
EXISTING
OI&T SUPERVISOR
C-B028
ELEC
EL
EC
PANEL PANEL
2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER 1HR FIRE BARRIER 1HR FIRE BARRIER 1HR FIRE BARRIER 1HR FIRE BARRIER 1HR FIRE BARRIER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER1
7 8
2020 E. Washington Boulevard Suite 200 Fort Wayne, Indiana 46803
PH: 260.424.4830
www.viridian-design.netV IRIDIAN
ARCHITECTURAL DESIGN INC.
All concepts, ideas, design elements, plans, and details as shown on this document are the sole property of Viridian Architectural Design Inc. and shall not be used for any purpose without prior expressed written consent. The Contracting Officer Representative shall be permitted to retain copies for information and reference.
REMOVE CHILLED WATER SUPPLY AND RETURN PIPING THROUGH FLOOR TO
CRAWLSPACE. PATCH / REPAIR FLOOR TO MATCH EXISTING, ADJACENT FLOOR IN
CONSTRUCTION.
REMOVE CITY WATER THROUGH FLOOR TO SUB-BASEMENT. PATCH / REPAIR FLOOR
TO MATCH EXISTING, ADJACENT FLOOR IN CONSTRUCTION.
REMOVE CITY WATER PIPING THROUGH FLOOR TO CRAWLSPACE. PATCH / REPAIR
FLOOR TO MATCH EXISTING, ADJACENT FLOOR IN CONSTRUCTION.
REMOVE EXISTING CHILLED WATER SUPPLY AND RETURN PIPING TO THIS POINT.
PREPARE FOR NEW WORK.
REMOVE EXISTING HUB DRAIN THROUGH FLOOR. PATCH / REPAIR FLOOR TO MATCH
EXISTING, ADJACENT FLOOR IN CONSTRUCTION.
REMOVE CHILLED WATER SUPPLY AND RETURN PIPING THROUGH FLOOR TO
SUB-BASEMENT. PATCH / REPAIR FLOOR TO MATCH EXISTING, ADJACENT FLOOR IN
CONSTRUCTION.
REMOVE EXISTING LIQUID SENSOR. PREPARE WIRING FOR CONNECTION TO NEW
SENSOR.
REMOVE EXISTING LIQUID SENSOR.
PIPING TO EXISTING COOLING UNIT TO REMAIN.
TEMPERATURE CONTROL PANEL TO REMAIN ACTIVE.
EXISTING VALVES ARE TO BE SALVAGED AND TURNED OVER TO THE VA.
REMOVE PNEUMATIC ACTUATED VALVES. VALVES ARE TO BE SALVAGED AND TURNED
OVER TO THE VA.
REMOVE DRAIN PIPE TO POINT INDICATED AND PREPARE FOR RECONNECTION.
EXISTING HUB DRAIN TO REMAIN.
REMOVE EXISTING CHILLED WATER / CITY WATER CHANGEOVER SWITCH COMPLETE.
SCALE: 1/4" = 1'-0"
MECHANICAL - DEMOLITION PLAN - PARTIAL BASEMENT FLOOR - UNDER FLOOR PIPING 1
MD101A
THESE NOTES APPLY TO ALL DEMOLITION DRAWINGS AND TO ALL CONTRACTORS AND /
OR SUBCONTRACTORS THAT WORK WITHIN THIS BUILDING.
1. ALL MATERIALS INDICATED AS DASHED ARE TO BE REMOVED. THIS INCLUDES ALL
FINISHES AND MATERIALS NOT SPECIFICALLY CALLED OUT BUT PERTAINING TO THE
INTENDED SCOPE.
2. CONTRACTORS SHALL BE RESPONSIBLE FOR VISITING THE SITE TO BECOME FAMILIAR
WITH THE EXISTING CONDITIONS. THESE DEMOLITION SHEETS SHALL SERVE TO AID THE
CONTRACTOR IN THE EVALUATION OF THE EXTENT OF DEMOLITION: BUT SHALL NOT BE
HELD TO BE ALL INCLUSIVE.
3. CONTRACTORS SHALL FIELD INSPECT ALL DEMOLITION WORK PRIOR TO REMOVAL, TO
ENSURE SUCH REMOVAL DOES NOT IMPAIR STRUCTURAL INTEGRITY OF THE EXISTING
SITE OR BUILDING. IF THE INSPECTION INDICATES THAT THE STRUCTURAL INTEGRITY
MAY BE COMPROMISED, NOTIFY THE CONTRACTING OFFICER REPRESENTATIVE (COR)
IMMEDIATELY.
4. GENERAL CONTRACTOR TO COORDINATE ALL ASSOCIATED WORK WITH ALL
SUB-CONTRACTORS.
5. ALL CONTRACTORS TO VERIFY STAGING AND STORAGE LOCATIONS OF ALL MATERIALS
AND EQUIPMENT WITH COR PRIOR TO BEGINNING OF CONSTRUCTION.
6. ALL CONSTRUCTION AREAS AND ASSOCIATED WORK AREAS SHALL BE KEPT CLEAN BY
THE CONTRACTOR - DAILY.
7. PROTECT ADJACENT SPACES AND EXISTING EQUIPMENT FROM DEMOLITION DEBRIS
AND DAMAGE DURING CONSTRUCTION.
8. CONTRACTOR TO ENSURE NO DEMOLITION DEBRIS IS LEFT ON SITE PRIOR TO
COMPLETING ALL DEMOLITION WORK.
9. ALL CONTRACTORS SHALL BE RESPONSIBLE FOR ANY DAMAGES CAUSED BY THEM
DURING THE CONSTRUCTION PROCESS. IN THE EVENT OF ANY DAMAGES CONTRACTOR
IS TO CONTACT THE COR IMMEDIATELY; PRIOR TO THE END OF THE DAY OF
CONSTRUCTION.
10. ALL CONTRACTORS TO COORDINATE RELOCATION AND STORAGE OF EXISTING AND
DEMOLISHED EQUIPMENT AND MATERIALS WITH THE COR PRIOR TO THE START OF
CONSTRUCTION.
11. REMOVAL OF EXISTING EQUIPMENT SHALL BE COMPLETED WHILE ADJACENT EQUIPMENT
IS IN OPERATION. SMOKE AND DUST CONTROL MEASURES SHALL BE IN PLACE PRIOR
TO REMOVAL OF HVAC EQUIPMENT, DUCTWORK, PIPING, AND SUPPLY/RETURN GRILLES.
NOT TO SCALE
BASEMENT KEY PLAN
N
RICHARD L. ROUDEBUSH
VA MEDICAL CENTER
RENOVATION
AREA
NOTE:
PROVIDE FIRE STOPPING AT ALL NEW PENETRATIONS OF FLOOR. PATCH ALL
ABANDONED OPENINGS AND MAINTAIN FIRE RATING OF FLOOR.
NOTE:
CONTRACTOR IS TO PROTECT ALL ADJACENT SPACES, EQUIPMENT, AND FINISHES
DURING CORE DRILLING AND OTHER WORK. COORDINATE AND SCHEDULE ALL CORE
DRILLING AND SHUTDOWNS WITH COR.
P
DO
W N
RAMP
DOWN
EXISTING
TELECOM
C-BO22EXISTING
LOBBY
EXISTING
ELEVATOR P1
EXISTING
ELEVATOR P2
EXISTING
ELEVATOR P3
EXISTING
ELEVATOR P4
EXISTING
SERVICE
ELEVATOR S6
EXISTING
SERVICE
ELEVATOR S5
EXISTING
CORRIDOR
CB-35EXISTING
PAPER
STORAGE
C-B177
EXISTING
TELECOM
C-B178
EXISTING
MECH
C-B021
EXISTING
CORRIDOR
CB-36
EXISTING
CORRIDOR
CB-38
EXISTING
CLOSET
C-B018
EXISTING
SWITCH GEAR
C-B019
EXISTING
MECH
C-B020
EXISTING
STAIR-1
UPDO
W
N
EXISTING
UPS
C-BO17
EXISTING
IMS ENTRY
EXISTING
IMS
C-B027A
EXISTING
IMS MECH
C-B027
EXISTING
REPAIR AND
DEVELOPMENT
C-B031
EXISTING
OI&T SYSTEMS
C-B026
EXISTING
OI&T SUPERVISOR
C-B028
ELEC
EL
EC
PANEL PANEL
2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER 1HR FIRE BARRIER 1HR FIRE BARRIER 1HR FIRE BARRIER 1HR FIRE BARRIER 1HR FIRE BARRIER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
2020 E. Washington Boulevard Suite 200 Fort Wayne, Indiana 46803
PH: 260.424.4830
www.viridian-design.netV IRIDIAN
ARCHITECTURAL DESIGN INC.
All concepts, ideas, design elements, plans, and details as shown on this document are the sole property of Viridian Architectural Design Inc. and shall not be used for any purpose without prior expressed written consent. The Contracting Officer Representative shall be permitted to retain copies for information and reference.
SCALE: 1/4" = 1'-0"
MECHANICAL - DEMOLITION PLAN - PARTIAL BASEMENT FLOOR 1
MD101B
REMOVE EXISTING IT ROOM AIR CONDITIONER IN ITS ENTIRETY. PUMP DOWN ALL
REFRIGERANT AND PROPERLY DISPOSE OF REFRIGERANT AND REFRIGERANT OIL. UNITS
TO BE DISMANTLED AND REMOVED IN SECTIONS AS NEEDED TO FIT THROUGH
EXISTING OPENINGS.
REMOVE EXISTING EXHAUST GRILLE. PATCH AND SEAL OPENING TO MATCH EXISTING
DUCTWORK.
REMOVE EXISTING TRANSFER AIR GRILLES LOCATED NEAR CEILING ON BOTH SIDES OF
WALL. REMOVE EXISTING SUPPLY AIR DIFFUSERS LOCATED NEAR FLOOR ON BOTH
SIDES OF WALL. PREPARE OPENING IN WALL NEAR CEILING AND FLOOR FOR NEW
WORK.
REMOVE EXISTING DIFFUSERS, DUCTWORK, AND TERMINAL UNITS IN THEIR ENTIRETY.
REMOVE EXISTING SUPPLY AIR BACK TO THIS LOCATION. PREPARE DUCTWORK FOR
NEW WORK.
REMOVE EXISTING HEATING HOT WATER SUPPLY AND RETURN PIPING BACK TO THIS
LOCATION. PREPARE PIPING FOR NEW WORK.
REMOVE GRILLE AND RETURN DUCT BACK TO MAIN. CAP MAIN DUCT AT TAKEOFF.
PATCH WALL TO MAINTAIN FIRE RATING.
REMOVE EXHAUST GRILLES AND DUCT BACK TO MAIN.
THESE NOTES APPLY TO ALL DEMOLITION DRAWINGS AND TO ALL CONTRACTORS AND /
OR SUBCONTRACTORS THAT WORK WITHIN THIS BUILDING.
1. ALL MATERIALS INDICATED AS DASHED ARE TO BE REMOVED. THIS INCLUDES ALL
FINISHES AND MATERIALS NOT SPECIFICALLY CALLED OUT BUT PERTAINING TO THE
INTENDED SCOPE.
2. CONTRACTORS SHALL BE RESPONSIBLE FOR VISITING THE SITE TO BECOME FAMILIAR
WITH THE EXISTING CONDITIONS. THESE DEMOLITION SHEETS SHALL SERVE TO AID THE
CONTRACTOR IN THE EVALUATION OF THE EXTENT OF DEMOLITION: BUT SHALL NOT BE
HELD TO BE ALL INCLUSIVE.
3. CONTRACTORS SHALL FIELD INSPECT ALL DEMOLITION WORK PRIOR TO REMOVAL, TO
ENSURE SUCH REMOVAL DOES NOT IMPAIR STRUCTURAL INTEGRITY OF THE EXISTING
SITE OR BUILDING. IF THE INSPECTION INDICATES THAT THE STRUCTURAL INTEGRITY
MAY BE COMPROMISED, NOTIFY THE CONTRACTING OFFICER REPRESENTATIVE (COR)
IMMEDIATELY.
4. GENERAL CONTRACTOR TO COORDINATE ALL ASSOCIATED WORK WITH ALL
SUB-CONTRACTORS.
5. ALL CONTRACTORS TO VERIFY STAGING AND STORAGE LOCATIONS OF ALL MATERIALS
AND EQUIPMENT WITH COR PRIOR TO BEGINNING OF CONSTRUCTION.
6. ALL CONSTRUCTION AREAS AND ASSOCIATED WORK AREAS SHALL BE KEPT CLEAN BY
THE CONTRACTOR - DAILY.
7. PROTECT ADJACENT SPACES AND EXISTING EQUIPMENT FROM DEMOLITION DEBRIS
AND DAMAGE DURING CONSTRUCTION.
8. CONTRACTOR TO ENSURE NO DEMOLITION DEBRIS IS LEFT ON SITE PRIOR TO
COMPLETING ALL DEMOLITION WORK.
9. ALL CONTRACTORS SHALL BE RESPONSIBLE FOR ANY DAMAGES CAUSED BY THEM
DURING THE CONSTRUCTION PROCESS. IN THE EVENT OF ANY DAMAGES CONTRACTOR
IS TO CONTACT THE COR IMMEDIATELY; PRIOR TO THE END OF THE DAY OF
CONSTRUCTION.
10. ALL CONTRACTORS TO COORDINATE RELOCATION AND STORAGE OF EXISTING AND
DEMOLISHED EQUIPMENT AND MATERIALS WITH THE COR PRIOR TO THE START OF
CONSTRUCTION.
11. REMOVAL OF EXISTING EQUIPMENT SHALL BE COMPLETED WHILE ADJACENT EQUIPMENT
IS IN OPERATION. SMOKE AND DUST CONTROL MEASURES SHALL BE IN PLACE PRIOR
TO REMOVAL OF HVAC EQUIPMENT, DUCTWORK, PIPING, AND SUPPLY/RETURN GRILLES.
NOT TO SCALE
BASEMENT KEY PLAN
N
RICHARD L. ROUDEBUSH
VA MEDICAL CENTER
RENOVATION
AREA
NOTE:
PROVIDE FIRE STOPPING AT ALL NEW PENETRATIONS OF FLOOR. PATCH ALL
ABANDONED OPENINGS AND MAINTAIN FIRE RATING OF FLOOR.
NOTE:
CONTRACTOR IS TO PROTECT ALL ADJACENT SPACES, EQUIPMENT, AND FINISHES
DURING CORE DRILLING AND OTHER WORK. COORDINATE AND SCHEDULE ALL CORE
DRILLING AND SHUTDOWNS WITH COR.
R
FIR
E B A R R
IER
2HR FIRE BARRIER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
2HR FIRE BARRIER
H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R
2HR FIRE BARRIER
H R
FIR
E B A R R
IER
2HR FIRE BARRIER
2 3 4
MH100B
2020 E. Washington Boulevard Suite 200 Fort Wayne, Indiana 46803
PH: 260.424.4830
www.viridian-design.netV IRIDIAN
ARCHITECTURAL DESIGN INC.
All concepts, ideas, design elements, plans, and details as shown on this document are the sole property of Viridian Architectural Design Inc. and shall not be used for any purpose without prior expressed written consent. The Contracting Officer Representative shall be permitted to retain copies for information and reference.
SCALE: 1/16" = 1'-0"
MECHANICAL - PLAN - PARTIAL SUB BASEMENT/CRAWL SPACE OVERALL PLAN
MH100A
CONNECT CHWS AND CHWR TO EXISTING 8" CHWS AND CHWR AND EXTEND AS
INDICATED.
REFER TO PIPING SCHEMATIC AND SUB-BASEMENT FLOOR PLAN ON DRAWING
MH100B.
REFER TO ENLARGED PLAN ON DRAWING MH100B.
PROVIDE THROUGH PENETRATION FIRE STOPPING AT ALL OPENINGS CREATED BY
WORK OF THIS PROJECT IN RATED FLOORS AND WALLS.
CORE DRILL THROUGH WALLS FOR ROUTING OF NEW PIPING.
CONNECT (2) NEW 2"CW TO (2) EXISTING 2"CW TAPS. COMBINE INTO A SINGLE 3"CW
PIPE WITH A REDUCED PRESSURE BACKFLOW PREVENTER MOUNTED BETWEEN 12"
AND 60" A.F.F. PROVIDE AND INSTALL FUNNEL DRAIN ASSEMBLY PIPED TO NEAREST
FLOOR DRAIN.
CONNECT NEW 3" CITY WATER DRAIN INTO TAP OFF TOP OF EXISTING 8" STORM PIPE.
COORDINATE PIPE ROUTING TO NOT BE ABOVE EXISTING ELECTRICAL PANELS.
INSTALL CHECK VALVE IN CITY WATER DRAIN NEAR THE CONNECTION TO THE STORM
SEWER.
1. ALL CONTRACTORS SHALL CLEAN SITE THOROUGHLY AT THE END OF EACH WORK DAY.
2. ALL CONTRACTORS TO VERIFY STAGING AND STORAGE LOCATIONS OF ALL MATERIALS
AND EQUIPMENT WITH CONTRACTING OFFICER REPRESENTATIVE (COR) PRIOR TO
BEGINNING OF CONSTRUCTION.
3. ALL CONTRACTORS ARE RESPONSIBLE FOR ANY DAMAGES CAUSED BY THEM DURING
THE CONSTRUCTION PROCESS. IN THE EVENT OF ANY DAMAGES, CONTRACTOR IS TO
CONTACT THE COR IMMEDIATELY.
NOT TO SCALE
SUBBASEMENT KEY PLAN
N
RICHARD L. ROUDEBUSH
VA MEDICAL CENTER
RENOVATION
AREA
NOTE:
PROVIDE FIRE STOPPING AT ALL NEW PENETRATIONS OF FLOOR. PATCH ALL
ABANDONED OPENINGS AND MAINTAIN FIRE RATING OF FLOOR. FLOOR FIRE RATING IS
2 HOURS. REFER TO ARCHITECTURAL DRAWINGS FOR ADDITIONAL INFORMATION.
NOTE:
CONTRACTOR IS TO PROTECT ALL ADJACENT SPACES, EQUIPMENT, AND FINISHES
DURING CORE DRILLING AND OTHER WORK. COORDINATE AND SCHEDULE ALL CORE
DRILLING AND SHUTDOWNS WITH COR.
NOTE:
PROVIDE VALVE TAGS ON ALL VALVES INDICATING THE SERVICE AND A NUMBER.
PROVIDE A CORRESPONDING VALVE TAG CHART MOUNTED ON THE WALL AT A
LOCATION TO BE DETERMINED BY THE VA.
R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
2HR FIRE BARRIER2HR FIRE BARRIER2HR FIRE BARRIER2HR FIRE BARRIER2HR FIRE BARRIER2HR FIRE BARRIER
H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R H R F
IR
E
B A R R
IE
R
2HR FIRE BARRIER2HR FIRE BARRIER2HR FIRE BARRIER2HR FIRE BARRIER2HR FIRE BARRIER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
H R
FIR
E B A R R
IER
2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER
2020 E. Washington Boulevard Suite 200 Fort Wayne, Indiana 46803
PH: 260.424.4830
www.viridian-design.netV IRIDIAN
ARCHITECTURAL DESIGN INC.
All concepts, ideas, design elements, plans, and details as shown on this document are the sole property of Viridian Architectural Design Inc. and shall not be used for any purpose without prior expressed written consent. The Contracting Officer Representative shall be permitted to retain copies for information and reference.
SCALE: 1/4" = 1'-0"
MECHANICAL - PLAN - PARTIAL SUB BASEMENT/CRAWL SPACE
MH100B
3" CONDENSATE DRAIN DOWN TO EXISTING SUMP PUMP.
REFER TO AIR CONDITIONING PIPING SCHEMATIC AND DETAILS FOR ADDITIONAL
INFORMATION AND WORK OF THIS PROJECT. REFER TO DRAWING MG002.
CORE DRILL BASEMENT FLOOR NEAR TO AC UNIT. ROUTE CHW PIPING UP THROUGH
FLOOR AND CONNECT TO AC UNIT.
PROVIDE THROUGH PENETRATION FIRE STOPPING AT ALL OPENINGS CREATED BY
WORK OF THIS PROJECT IN RATED FLOORS AND WALLS.
CORE DRILL BASEMENT FLOOR NEAR TO AC UNIT. ROUTE CITY WATER UP THROUGH
FLOOR.
3/4" CW UP TO HUMIDIFIER CONNECTION WITHIN AC UNIT.
CORE DRILL BASEMENT FLOOR AND ROUTE 3" SAN DRAIN UP TO 4" HUB DRAIN.
PROVIDE DEEP SEAL TRAP. FIRESTOP TO MAINTAIN FIRE RATING INDICATED.
CONNECT 2" CW TO THE EXISTING 2" CW PIPING AS INDICATED AND EXTEND.
CONNECT NEW 3" CITY WATER DRAIN TO EXISTING STORM PIPING.
REFER TO DRAWING MH100A FOR CONTINUATION.
CORE DRILL SUB-BASEMENT/CRAWL SPACE WALL. TYPICAL OF ALL NEW PIPING
PENETRATING WALL. FIRESTOP TO MAINTAIN FIRE RATING INDICATED.
COORDINATE PIPE ROUTING TO NOT BE ABOVE EXISTING ELECTRICAL PANELS.
PROVIDE AND INSTALL DIFFERENTIAL PRESSURE SENSOR TO CONTROL VFD-P-1 AND
VFD-P-1A.
PROVIDE AND INSTALL DIFFERENTIAL PRESSURE SENSOR TO CONTROL VFD-P-2 AND
VFD-P-2A.
PROVIDE AND INSTALL VARIABLE FREQUENCY DRIVES ON EXISTING WALL.
3/4" CITY WATER UP TO FLOOR CAVITY FOR FUTURE CONNECTION TO PORTABLE
COOLER.
PROVIDE INLINE WATER FILTER RATED AT 0.5 GPM, 500 GALLONS, WITH QUICK
DISCONNECT FITTINGS. INSTALL THE FILTER IN AN ACCESSIBLE LOCATION ON THE
INLET TO THE HUMIDIFIER.
EXISTING OPEN HUB DRAIN TO REMAIN. DRAIN IS CONNECTED TO EXISTING SANITARY.
INSTALL AUTOMATIC CHANGEOVER VALVE IN EXISTING PIPING.
INSTALL AUTOMATIC FLOW CONTROL VALVE IN CITY WATER LINE TO LIMIT THE
MAXIMUM FLOW TO 81 GPM.
REFER TO SHEET MG002, DETAIL #1 FOR CHILLED WATER PIPE CONNECTIONS IN THIS
AREA.
CONNECT NEW 2" PVC TO EXISTING AND EXTEND DOWN TO NEW SUMP PUMPS. REFER
TO DETAIL #8 ON SHEET MG002.
1. ALL CONTRACTORS SHALL CLEAN SITE THOROUGHLY AT THE END OF EACH WORK DAY.
2. ALL CONTRACTORS TO VERIFY STAGING AND STORAGE LOCATIONS OF ALL MATERIALS
AND EQUIPMENT WITH CONTRACTING OFFICER REPRESENTATIVE (COR) PRIOR TO
BEGINNING OF CONSTRUCTION.
3. ALL CONTRACTORS ARE RESPONSIBLE FOR ANY DAMAGES CAUSED BY THEM DURING
THE CONSTRUCTION PROCESS. IN THE EVENT OF ANY DAMAGES, CONTRACTOR IS TO
CONTACT THE COR IMMEDIATELY.
NOT TO SCALE
SUBBASEMENT KEY PLAN
N
RICHARD L. ROUDEBUSH
VA MEDICAL CENTER
RENOVATION
AREA
NOTE:
PROVIDE FIRE STOPPING AT ALL NEW PENETRATIONS OF FLOOR. PATCH ALL
ABANDONED OPENINGS AND MAINTAIN FIRE RATING OF FLOOR. FLOOR FIRE RATING IS
2 HOURS. REFER TO ARCHITECTURAL DRAWINGS FOR ADDITIONAL INFORMATION.
NOTE:
CONTRACTOR IS TO PROTECT ALL ADJACENT SPACES, EQUIPMENT, AND FINISHES
DURING CORE DRILLING AND OTHER WORK. COORDINATE AND SCHEDULE ALL CORE
DRILLING AND SHUTDOWNS WITH COR.
SCALE: 1/16" = 1'-0"
TEMPORARY PIPING PRIOR TO PHASE 1
MH100B
TEMPORARY PIPING NOTES
PROVIDE TEMPORARY TIE-INS TO EXISTING CHILLED WATER MAINS
ROUTE 2" CHILLED WATER SUPPLY AND RETURN TO AC-5 AND AC-6 INSTALLED IN A
TEMPORARY LOCATION TO BE DETERMINED BY THE VA. PROVIDE AND INSTALL
FLEXIBLE HOSE CONNECTIONS TO ALLOW UNITS TO BE MOVED. ROUTE TEMORARY
CONDENSATE DRAIN PIPING TO SUMP PUMP.
NOTE:
PROVIDE VALVE TAGS ON ALL VALVES INDICATING THE SERVICE AND A NUMBER.
PROVIDE A CORRESPONDING VALVE TAG CHART MOUNTED ON THE WALL AT A
LOCATION TO BE DETERMINED BY THE VA.
P
DO
W N
RAMP
DOWN
UPDO
W
N
ELEC
EL
EC
PANEL PANEL
2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER 1HR FIRE BARRIER 1HR FIRE BARRIER 1HR FIRE BARRIER 1HR FIRE BARRIER 1HR FIRE BARRIER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1 2
1 2 3
5 6
1 2
65 7
1 2
65 7
1 2
65 7
1 2
65 7
TELECOM
C-B022
UPS
C-B017
EXISTING
IMS ENTRY
EXISTING
IMS
C-B027A
EXISTING
IMS MECH
C-B027
15 13
2020 E. Washington Boulevard Suite 200 Fort Wayne, Indiana 46803
PH: 260.424.4830
www.viridian-design.netV IRIDIAN
ARCHITECTURAL DESIGN INC.
All concepts, ideas, design elements, plans, and details as shown on this document are the sole property of Viridian Architectural Design Inc. and shall not be used for any purpose without prior expressed written consent. The Contracting Officer Representative shall be permitted to retain copies for information and reference.
SCALE: 1/4" = 1'-0"
MECHANICAL - PLAN - PARTIAL BASEMENT FLOOR - UNDER FLOOR PIPING 1
MH101A
ROUTE CHWS AND CHWR PIPING UP THROUGH FLOOR AND CONNECT TO AC UNIT.
MAKE FINAL CONNECTION USING STAINLESS STEEL FLEXIBLE HOSE CONNECTOR.
ROUTE CONDENSATE DRAIN TO NEAREST TRAPPED HUB DRAIN.
CONNECT NEW 3/4" CHWS AND 3/4" CHWR TO EXISTING AND ROUTE TO NEW 2-1/2"
CHWS AND 2-1/2" CHWR NEAR AC-2. CONNECT NEW 3/4" CONDENSATE DRAIN TO
EXISTING AND ROUTE TO HD-1. REFER TO DETAIL 1 ON DRAWING MG002. VALVES
ARE TO BE IN AN ACCESSIBLE LOCATION BELOW THE AISLE. LABEL FLOOR TILE TO
INDICATE VALVES BELOW.
REFER TO DRAWING MG002 PIPING SCHEMATICS AND DETAILS FOR ADDITIONAL
INFORMATION.
ROUTE CITY DOMESTIC COLD WATER PIPING UP THROUGH FLOOR AND CONNECT TO
AC UNIT AND HUMIDIFIER.
ROUTE CITY WATER DISCHARGE THROUGH FLOOR TO STORM DRAIN. REFER TO
DRAWING MH100B FOR CONTINUATION. CITY WATER DISCHARGE IS TO BE A HARD
PIPE CONNECTION THROUGH THE FLOOR.
INSTALL NEW LIQUID DETECTOR.
PIPING PENETRATIONS FROM BELOW. REFER TO DRAWING MH100B.
PROVIDE AND INSTALL NEW TEMPERATURE CONTROL PANEL TO PICK UP ADDITIONAL
CONTROL POINTS FOR NEW EQUIPMENT. CONNECT TO EXISTING PANEL FOR POWER
AND CONTROL WIRING.
PROVIDE AND INSTALL NEW ELECTRONIC CHANGEOVER VALVE FOR EXISTING AC UNIT
IN UPS C-B017. LABEL FLOOR TILE TO INDICATE VALVE BELOW.
ROUTE EXISTING DRAIN TO NEW HUB DRAIN.
MAINTAIN OPERATION OF EXISTING CITY WATER CHANGEOVER DRAIN VALVE. LABEL
FLOOR TILE TO INDICATE VALVE BELOW. DRAIN IS TO TERMINATE IN THE HUB DRAIN.
PROVIDE AND INSTALL 3/4" CAPPED AND VALVED CITY WATER CONNECTION FOR
FUTURE CONNECTION TO TEMPORARY COOLER. PROVIDE WITH HOSE THREAD
CONNECTION. LABEL FLOOR TILE TO INDICATE LOCATION OF TEMPORARY
CONNECTION.
INSTALL SUPPLY AIR TEMPERATURE SENSOR AND CABLE UNDER THE FLOOR AS FAR
AS POSSIBLE FROM THE UNIT AND UNDER THE COLD AISLE CONTAINMENT.
ROUTE CITY WATER BACKUP DRAIN TO EXISTING OPEN HUB DRAIN.
PROVIDE AND INSTALL NETWORK SWITCHES AND ALL INTERCONNECTING ETHERNET
WIRING TO CONNECT ALL AC UNITS TO NEW SWITCHES.
REFER TO SHEET MG002, DETAIL #1 FOR CHILLED WATER PIPE CONNECTIONS IN THIS
AREA.
1. ALL CONTRACTORS SHALL CLEAN SITE THOROUGHLY AT THE END OF EACH WORK DAY.
2. ALL CONTRACTORS TO VERIFY STAGING AND STORAGE LOCATIONS OF ALL MATERIALS
AND EQUIPMENT WITH CONTRACTING OFFICER REPRESENTATIVE (COR) PRIOR TO
BEGINNING OF CONSTRUCTION.
3. ALL CONTRACTORS ARE RESPONSIBLE FOR ANY DAMAGES CAUSED BY THEM DURING
THE CONSTRUCTION PROCESS. IN THE EVENT OF ANY DAMAGES, CONTRACTOR IS TO
CONTACT THE COR IMMEDIATELY.
NOT TO SCALE
BASEMENT KEY PLAN
N
RICHARD L. ROUDEBUSH
VA MEDICAL CENTER
RENOVATION
AREA
NOTE:
PROVIDE FIRE STOPPING AT ALL NEW PENETRATIONS OF FLOOR. PATCH ALL
ABANDONED OPENINGS AND MAINTAIN FIRE RATING OF FLOOR. FLOOR FIRE RATING IS
2 HOURS. REFER TO ARCHITECTURAL DRAWINGS FOR ADDITIONAL INFORMATION.
NOTE:
CONTRACTOR IS TO PROTECT ALL ADJACENT SPACES, EQUIPMENT, AND FINISHES
DURING CORE DRILLING AND OTHER WORK. COORDINATE AND SCHEDULE ALL CORE
DRILLING AND SHUTDOWNS WITH COR.
NOTE:
PROVIDE VALVE TAGS ON ALL VALVES INDICATING THE SERVICE AND A NUMBER.
PROVIDE A CORRESPONDING VALVE TAG CHART MOUNTED ON THE WALL AT A
LOCATION TO BE DETERMINED BY THE VA.
P
DO
W N
RAMP
DOWN
UPDO
W
N
ELEC
EL
EC
PANEL PANEL
IT
RA
CK
2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER 1HR FIRE BARRIER 1HR FIRE BARRIER 1HR FIRE BARRIER 1HR FIRE BARRIER 1HR FIRE BARRIER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
SWITCH PATCH
TELECOM
C-B022
UPS
C-B017
EXISTING
IMS ENTRY
EXISTING
IMS
C-B027A
EXISTING
IMS MECH
C-B027
6 6
99 9
10 10
2020 E. Washington Boulevard Suite 200 Fort Wayne, Indiana 46803
PH: 260.424.4830
www.viridian-design.netV IRIDIAN
ARCHITECTURAL DESIGN INC.
All concepts, ideas, design elements, plans, and details as shown on this document are the sole property of Viridian Architectural Design Inc. and shall not be used for any purpose without prior expressed written consent. The Contracting Officer Representative shall be permitted to retain copies for information and reference.
SCALE: 1/4" = 1'-0"
MECHANICAL - PLAN - PARTIAL BASEMENT FLOOR 1
MH101B
1. ALL CONTRACTORS SHALL CLEAN SITE THOROUGHLY AT THE END OF EACH WORK DAY.
2. ALL CONTRACTORS TO VERIFY STAGING AND STORAGE LOCATIONS OF ALL MATERIALS
AND EQUIPMENT WITH CONTRACTING OFFICER REPRESENTATIVE (COR) PRIOR TO
BEGINNING OF CONSTRUCTION.
3. ALL CONTRACTORS ARE RESPONSIBLE FOR ANY DAMAGES CAUSED BY THEM DURING
THE CONSTRUCTION PROCESS. IN THE EVENT OF ANY DAMAGES, CONTRACTOR IS TO
CONTACT THE COR IMMEDIATELY.
1 INSTALL NEW VOLUME DAMPER ON EACH NEW SUPPLY GRILLE NEAR FLOOR. VOLUME
DAMPERS ARE TO BE CLOSED. COORDINATE COOLING REQUIREMENTS WITH VA.
CONNECT NEW HWS AND HWR TO EXISTING.
CONNECT NEW 8"x6" EXHAUST DUCT TO EXISTING AND EXTEND AS INDICATED.
PROVIDE AND INSTALL COLD AISLE END ROW PLASTIC CURTAIN WALL. REFER TO
ARCHITECTURAL DRAWINGS.
PROVIDE AND INSTALL SIGN ON WALL NEXT TO DOOR INDICATING MAXIMUM
AVAILABLE COMBINED COOLING CAPACITY OF AIR CONDITIONING EQUIPMENT IN
ROOM.
PROVIDE AND INSTALL MANUAL CHANGEOVER SWITCH TO ALLOW UNITS TO BE
SWITCHED FROM CHILLED WATER TO CITY WATER SUPPLY. PROVIDE SIGNAGE TO
INDICATE ONLY A LIMITED NUMBER OF UNITS CAN OPERATE ON CITY WATER AT THE
SAME TIME. REFER TO SEQUENCE OF OPERATION ITEM 2. E. ON DRAWING MG001
AND SIGNAGE DIAGRAM ON DRAWING MG002. COORDINATE LOCATION WITH VA.
PROVIDE AND INSTALL 24 VOLT WIRING FROM TERMINAL ON AC UNIT TO FIRE PANEL
FOR REMOTE SHUTDOWN OF UNIT. COORDINATE INSTALLATION WITH OTHER TRADES.
PROVIDE AND INSTALL THREE RACK-MOUNTED SENSORS AND THE ASSOCIATED
WIRING ON THE RACKS WITHIN THE CONTAINMENT CURTAIN. EACH SENSOR IS TO
CONTROL THE ASSOCIATED IN-ROW AIR CONDITIONER.
INSTALL NEW VOLUME DAMPER IN EACH NEW TRANSFER AIR GRILLE NEAR CEILING.
MECHANICAL CONTRACTOR TO COORDINATE ROUTING OF NEW DUCT RUNS WITH
EXISTING CONSTRUCTION AND OTHER TRADES TO ALLOW FOR CEILING HEIGHT
ADJUSTMENT IN THIS AREA. VERTICAL OFFSETS WILL BE REQUIRED TO ROUTE ABOVE
AND BELOW EXISTING BUILDING ELEMENTS IN THE AREA.
NOT TO SCALE
BASEMENT KEY PLAN
N
RICHARD L. ROUDEBUSH
VA MEDICAL CENTER
RENOVATION
AREA
NOTE:
PROVIDE FIRE STOPPING AT ALL NEW PENETRATIONS OF FLOOR. PATCH ALL
ABANDONED OPENINGS AND MAINTAIN FIRE RATING OF FLOOR. FLOOR FIRE RATING IS
2 HOURS. REFER TO ARCHITECTURAL DRAWINGS FOR ADDITIONAL INFORMATION.
NOTE:
CONTRACTOR IS TO PROTECT ALL ADJACENT SPACES, EQUIPMENT, AND FINISHES
DURING CORE DRILLING AND OTHER WORK. COORDINATE AND SCHEDULE ALL CORE
DRILLING AND SHUTDOWNS WITH COR.
NOTE:
PROVIDE VALVE TAGS ON ALL VALVES INDICATING THE SERVICE AND A NUMBER.
PROVIDE A CORRESPONDING VALVE TAG CHART MOUNTED ON THE WALL AT A
LOCATION TO BE DETERMINED BY THE VA.
EXISTING
LOBBY
EXISTING
ELEVATOR P1
EXISTING
ELEVATOR P2
EXISTING
ELEVATOR P3
EXISTING
ELEVATOR P4
EXISTING
SERVICE
ELEVATOR S6
EXISTING
SERVICE
ELEVATOR S5
EXISTING
CORRIDOR
CB-35EXISTING
PAPER
STORAGE
C-B177
EXISTING
TELECOM
C-B178
EXISTING
MECH
C-B021
EXISTING
CORRIDOR
CB-36
EXISTING
CORRIDOR
CB-38
EXISTING
CLOSET
C-B018
EXISTING
SWITCH GEAR
C-B019
EXISTING
MECH
C-B020
EXISTING
STAIR-1
UPDO
W
N
EXISTING
UPS
C-BO17
EXISTING
REPAIR AND
DEVELOPMENT
C-B031
EXISTING
OI&T SYSTEMS
C-B026
EXISTING
OI&T SUPERVISOR
C-B028
H R F
IR
E
B A R R
IE
R
2HR FIRE BARRIER 2HR FIRE BARRIER 2HR FIRE BARRIER
H R F
IR
E
B A R R
IE
R
1HR FIRE BARRIER 1HR FIRE BARRIER 1HR FIRE BARRIER 1HR FIRE BARRIER 1HR FIRE BARRIER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H
R
FIR
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H
R
FIR
E / S
M
OK
E
BA
RR
IER
1H R
FIR
E
/ S M
OK
E
BA
RR
IER
1H R
FIR
E
BA
RR
IER
F F
C OSFA
FA
C
F
F
FAFA
F F
F
F F F WIFI
W
F
S
F W
F
FF
W
T
F
F
WIFI
F FA
FA
FA
FA
2 2
2 2
1 11
3 2
EXISTING
TELECOM
C-BO22
EXISTING
IMS ENTRY
EXISTING
IMS
C-B027A
EXISTING
IMS MECH
C-B027
SCALE: 1/1" = 1'-0"
FIRE PROTECTION - DEMOLITION PLAN - PARTIAL BASEMENT FLOOR1
FD901
All concepts, ideas, design elements, plans, and details as shown on this document are the sole property of Viridian Architectural Design Inc. and shall not be used for any purpose without prior expressed written consent. The Contracting Officer Representative shall be permitted to retain copies for information and reference.
2020 E. Washington Boulevard Suite 200 Fort Wayne, Indiana 46803
PH: 260.424.4830
www.viridian-design.netVIRIDIAN
ARCHITECTURAL DESIGN INC.
THESE NOTES APPLY TO ALL DEMOLITION DRAWINGS AND TO ALL CONTRACTORS AND /
OR SUBCONTRACTORS THAT WORK WITHIN THIS BUILDING.
1. ALL MATERIALS INDICATED AS DASHED ARE TO BE REMOVED. THIS INCLUDES ALL
FINISHES AND MATERIALS NOT SPECIFICALLY CALLED OUT BUT PERTAINING TO THE
INTENDED SCOPE.
2. CONTRACTORS SHALL BE RESPONSIBLE FOR VISITING THE SITE TO BECOME FAMILIAR
WITH THE EXISTING CONDITIONS. THESE DEMOLITION SHEETS SHALL SERVE TO AID THE
CONTRACTOR…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .