36C25019B0017-026.docx
DOCX document 104 KB Posted
- Attached to
- REPLACE SURGERY SUBSTATION 541-19-504 Federal contract opportunity
- Solicitation number
- 36C25019B0017
About this file
36C25019B0017 36C25019B0017_1.docx
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25019C0189-000.docx | DOCX document | |
| 36C25019B0017-0002001.docx | DOCX document | |
| 36C25019B0017-0002000.docx | DOCX document | |
| 36C25019B0017-0001000.docx | DOCX document | |
| 36C25019B0017-028.pdf | ||
| 36C25019B0017-030.docx | DOCX document | |
| 36C25019B0017-027.pdf | ||
| 36C25019B0017-029.pdf | ||
| 36C25019B0017-031.docx | DOCX document | |
| 36C25019B0017-000.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25019B0017
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE
DOCUMENTS (
Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C25019B0017 X 03-2 -2019 541-19-1-5986-0013 541-19-504 Department of Veterans Affairs Network Contracting Office (NCO) 10 6150 Oak Tree Blvd., Suite 300 Independence OH 44131 Department of Veterans Affairs ATTN: 36C25019B0017, Brian Kish 2780 Airport Drive, Suite 340 Columbus OH 43219
DIANA J. PITTMAN
269-223-5177
REPLACE SURGERY SUB
STA
TION PROJECT 541-19-504
CONTRACTOR SHALL PROVIDE ALL LABOR, EQUIPMENT, SUPPLIES, & SUPERVISION NECESSARY TO REPLACE THE SURGERY SUBSTATION
AT THE LOUIS STOKES CLEVELAND VAMC, 10701 EAST BLVD., CLEVELAND, OH 44106-1702.
THE NAICS CODE FOR THIS PROJECT IS 236220. THE BUSINESS SIZE STANDARD IS $36.5 MILLION.
THE PROJECT MAGNITUDE FOR THIS PROJECT IS BETWEEN $1,000,000 AND $5,000,000.
ALL WORK SHALL BE CONDUCTED IN COMPLETE ACCORDANCE WITH THESTATEMENT OF WORK, DRAWINGS, AND TERMS OF THE CONTRACT.
ALL WORK SHALL BE COORDINATED WITH THE VA CONTRACTING OFFICER AND THE CONTRACTING OFFICER'S REPRESENTATIVE (COR).
YOU SHALL INSERT YOUR BID(S) IN THE APPROPRIATE BLOCK(S) ON THE ATTACHED SHEET TITLED "SF 1442 CONTINUATION".
BIDS WILL BE EVALUATED ON PRICE AND PRICE RELATED FACTORS.
SITE VISIT AND PLACE OF PERFORMANCE IS AT THE LOUIS STOKES CLEVELAND VAMC.
AN ORGANIZED SITE VISIT WILL BE CONDUCTED - SEE SOLICITATION SECTION TITLED "SITE VISIT INFORMATION".
CUT-OFF DATE AND TIME TO SUBMIT REQUESTS FOR INFORMATION (RFI) IS APRIL
, 2019 AT 2:00 P.M. ET. RFIs SHALL BE
EMAILED TO
SHELTON BEASLEY
AT
Shelton.Beasley@va.gov
. USING THE ATTACHED RFI FORM.
THIS PROJECT IS A 100% SET-ASIDE FOR A SERVICE DISABLED VETERAN OWNED SMALL BUSINESS (SDVOSB). ALL BIDDERS MUST BE VERIFIED IN VETBIZ AND REGISTERED IN SAM AT THE TIME OF THEOFFER DUE DATE AND THE TIME OF AWARD IN ORDER TO BE ELIGIBLE FOR AWARD. FOR ELIGIBILITY UNDER THIS NAICS, SEE VAAR 852.219-10 PARAGRAPH (c)(3) FOR PERFORMANCE REQUIREMENTS.
FAR 52.222-37 (EMPLOYMENT REPORTS ON VETERANS) IS INCORPORATED BY REFERENCE IN THIS SOLICITATION. PUBLIC LAW 105-339, SECTION 1354 PROVIDES "NO AGENCY MAY ENTER INTO A CONTRACT WITH A CONTRACTOR WHO HAS NOT FILED A VETS-4212 REPORT FOR THE PRECEEDING FISCAL YEAR UNDER TITLE 38 SECTION 4212 (d).
X
FAR
52.211-10 X
2:00 PM
-2019 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
See attached document titled "SF 1442 Block 17 Continuation" 541-3690162-5986-854200 Non-Recurring Ma-3220 Buildings and Facilities-23NRNR000 Department of Veterans Affairs Network Contracting Office (NCO) 10 6150 Oak Tree Blvd., Suite 300 Independence OH 44131 Department of Veterans Affairs Financial Services Center P.O. Box 149971 Austin TX 78714-9971
DIANA J. PITTMAN
Contract Officer
SF 1442 BLOCK 17 (CONTINUATION)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within ______calendar days after the date offers are due (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.).
| Contractor’s Name: | _______________________________ | ||
| CAGE Code: | _______________________________ | ||
| DUNS: | _______________________________ |
The following bids are submitted in lieu of completing block 17 on the attached SF 1442:
Bid Item 1 (Base Bid): ___________________________________________
Table of Contents
| SF 1442 BLOCK 17 (CONTINUATION) | 3 |
| STATEMENT OF BID ITEM(S) | 6 |
| SITE VISIT INFORMATION | 7 |
| INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS | 7 |
| NOTICE-SAFETY COMPLIANCE REQUIREMENT | 8 |
| NOTICE - REQUIRED REGISTRATION WITH CONTRACTOR PERFORMANCE ASSESSMENT SYSTEM (CPARS) | 8 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 10 |
| 2.1 FAR 52.216-1 TYPE OF CONTRACT (APR 1984) | 10 |
| 2.2 FAR 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 10 |
| 2.3 FAR 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 10 |
| 2.4 FAR 52.228-1 BID GUARANTEE (SEP 1996) | 11 |
| 2.5 FAR 52.233-2 SERVICE OF PROTEST (SEP 2006) | 12 |
| 2.6 FAR 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 12 |
| 2.7 FAR 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 13 |
| 2.8 FAR VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 13 |
| 2.9 FAR VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS-CPM) (NOV 2018) | 14 |
| 2.10 FAR VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018) | 17 |
| 2.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018) | 17 |
| 2.12 FAR VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008) | 18 |
| REPRESENTATIONS AND CERTIFICATIONS | 19 |
| 3.1 FAR 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (OCT 2018) | 19 |
| 3.2 FAR 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 22 |
| 3.3 FAR 52.209-13 VIOLATION OF ARMS CONTROLS TREATIES OR AGREEMENTS—CERTIFICATION (JUN 2018) | 23 |
| GENERAL CONDITIONS | 26 |
| 4.1 FAR 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 26 |
| 4.2 FAR 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (JUL 2018) | 26 |
| 4.3 FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) | 27 |
| 4.4 FAR 52.211-12 LIQUIDATED DAMAGES—CONSTRUCTION (SEPT 2000) | 27 |
| 4.5 FAR 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013) | 28 |
| 4.6 FAR 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014) | 29 |
| 4.7 SUPPLEMENTAL INSURANCE REQUIREMENTS | 32 |
| 4.8 FAR 52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984) | 32 |
| 4.9 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 33 |
| 4.10 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 35 |
| 4.11 VAAR 852.219-9 VA SMALL BUSINESS SUBCONTRACTING PLAN MINIMUM REQUIREMENTS (DEC 2009) | 36 |
| 4.12 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2016)(DEVIATION) | 36 |
| 4.13 VAAR 852.219-76 SUBCONTRACTING PLANS MONITORING AND COMPLIANCE (JUL 2018) | 37 |
| 4.14 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008) | 38 |
| 4.15 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (JUL 2002) | 38 |
| 4.16 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (JUL 2002) | 38 |
| 4.17 VAAR 852.236-74 INSPECTION OF CONSTRUCTION (JUL 2002) | 39 |
| 4.18 VAAR 852.236-76 CORRESPONDENCE (APR 1984) | 39 |
| 4.19 VAAR 852.236-77 REFERENCE TO "STANDARDS" (JUL 2002) | 39 |
| 4.20 VAAR 852.236-78 GOVERNMENT SUPERVISION (APR 1984) | 39 |
| 4.21 VAAR 852.236-79 DAILY REPORT OF WORKERS AND MATERIAL (APR 1984) | 40 |
| 4.22 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 1984) | 40 |
| 4.23 VAAR 852.236-84 SCHEDULE OF WORK PROGRESS (NOV 1984) | 40 |
| 4.24 VAAR 852.236-85 SUPPLEMENTARY LABOR STANDARDS PROVISIONS (APR 1984) | 41 |
| 4.25 VAAR 852.236-86 WORKER'S COMPENSATION (JAN 2008) | 41 |
| 4.26 VAAR 852.236-87 ACCIDENT PREVENTION (SEP 1993) | 41 |
| 4.27 VAAR 852.236-88 CONTRACT CHANGES--SUPPLEMENT (JUL 2002) | 42 |
| 4.28 VAAR 852.236-89 BUY AMERICAN ACT (JAN 2008) | 44 |
| 4.29 VAAR 852.236-91 SPECIAL NOTES (JUL 2002) | 44 |
| BID PACKET SUBMISSION CHECKLIST | 45 |
| LIST OF ATTACHMENTS | 45 |
STATEMENT OF BID ITEM(S)
BID ITEM 1 (Base Bid):
This project will replace the existing Surgery substation located in room 105. The new substation is to be designed in the surgery penthouse 3B-162D. The penthouse will need to be modified to facilitate all necessary fire partitions, flooring and clearances as required by code for the new substation. The new double ended substation will be two sections with a tie breaker.
All work to be completed within 180 calendar days from date of receipt of Notice to Proceed.
SITE VISIT INFORMATION
The ONLY site visit that will occur for this project is scheduled for:
Date: APRIL 5, 2019
Time: 10:00 A.M. EASTERN STANDARD TIME (EST)
Facility location: Department of Veterans Affairs Louis Stokes Cleveland VAMC VA Admin Building, Room 6M-661 10701 East Blvd.
Cleveland, Ohio 44106
Meeting location: VA Admin Building, Room 6M-661
No other site visits will be scheduled- all interested offerors are strongly encouraged to attend.
Any questions concerning the statement of work, specifications and/or drawings (technical and/or non-technical) shall be submitted electronically to the project Contract Officer (Diana.Pittman@va.gov). Please include the complete title of the project in your email subject line.
Page 1 of Page 1 of
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
(a) Bidding materials consisting of drawings, specifications and contract forms may be obtained by qualified General (Prime) Contractors interested in submitting bids direct to the Department of Veterans Affairs directly from the website at www.fbo.gov.
(b) A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000.00. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.
(c) If the contract will exceed $150,000.00 (see FAR 28.102-1 for lesser amount), the bidder to whom award is made will be required to furnish two bonds, a Payment Bond, SF 25A, and a Performance Bond, SF 25, each in the penal sum as noted in the General Conditions of the Specification. Copies of SFs 25 and 25A may be obtained upon application to the issuing office.
Offices of Perspectus Architecture as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
Cost Range: $1,000,000.00 - $5,000,000.00
NOTICE-SAFETY COMPLIANCE REQUIREMENT
Safety or Environmental Violations and Experience Modification Rate All Bidders/Offerors shall submit the following information pertaining to their past Safety and Environmental record: (The information as outlined below shall be submitted at the time the sealed bid or request for proposal is submitted. For sealed bids, information shall be submitted in a separate sealed envelope identified by the solicitation number, company name, and identified as “Safety Compliance Information”)
1. VIOLATION INFORMATION: The information shall contain, at a minimum, a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.
2. EXPERIENCE MODIFICATION RATE: All Bidders/Offerors shall submit information regarding their current Experience Modification Rate (EMR) equal to or less than 1.0. This information shall be obtained from the bidder’s/offeror’s insurance company and be furnished on the insurance carrier’s letterhead.
Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state run worker’s compensation insurance rating bureau.
DETERMINATION OF NON-RESPONSIVE--
All bids/offers in response to this solicitation will be reviewed for responsiveness to the solicitation. Failure to provide documentation as outlined above, at date and time set for bid opening or receipt of proposal, may deem the bid/proposal Non-Responsive.
Post award, this requirement is applicable to all subcontracting tiers, and prospective prime contractors will be responsible for determining the suitability of their prospective subcontractors. Information concerning any subcontractors will be provided to the Contracting Officer, in the same form and format as outlined above, prior to the prospective subcontractors commencing work under any resulting contract.
NOTICE - REQUIRED REGISTRATION WITH CONTRACTOR PERFORMANCE ASSESSMENT SYSTEM (CPARS)
(a) as prescribed in Federal Acquisition Regulation (FAR) Part 42.15, the Department of Veterans Affairs (VA) evaluates contractor past performance on all contracts that exceed $150,000, and shares those evaluations with other Federal Government contract specialists and procurement officials. The FAR requires that the contractor be provided an opportunity to comment on past performance evaluations prior to each report closing. To fulfill this requirement VA uses an online database, CPARS, which is maintained by the Naval Seal Logistics Center in Portsmouth, Virginia. CPARS has connectivity with the Past Performance Information Retrieval System (PPIRS) database, which is available to all Federal agencies. PPIRS is the system used to collect and retrieve performance assessment reports used in source selection determinations and completed CPARS report cards transferred to PPIRS. CPARS also includes access to the federal awardee performance and integrity information system (FAPIIS). FAPIIS is a web-enabled application accessed via CPARS for contractor responsibility determination information.
(b) Each contractor whose contract award is estimated to exceed $150,000 is required to register with CPARS database at the following web address: www.cpars.csd.disa.mil. Help in registering can be obtained by contacting Customer Support Desk @ DSN: 684-1690 or COMM: 207-438-1690. Registration should occur no later than thirty days after contract award, and must be kept current should there be any change to the contractor’s registered representative.
(c) For contracts with a period of one year or less, the contracting officer will perform a single evaluation when the contract is complete. For contracts exceeding one year, the contracting officer will evaluate the contractor’s performance annually. Interim reports will be filed each year until the last year of the contract, when the final report will be completed. The report shall be assigned in CPARS to the contractor’s designated representative for comment. The contractor representative will have thirty days to submit any comments and re-assign the report to the VA contracting officer.
(d) Failure to have a current registration in the CPARS database, or to re-assign the report to the VA contracting officer within those thirty days, will result in the Government’s evaluation being placed on file in the database with a statement that the contractor failed to respond.”
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 FAR 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.2 FAR 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
| FAR Number |
| Title |
| Date |
| 52.222-23 |
| NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION |
| FEB 1999 |
2.3 FAR 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.4 FAR 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3 Million, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
2.5 FAR 52.233-2 SERVICE OF PROTEST (SEP 2006)
Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:
Diana J. Pittman, Contract Officer diana.pittman@va.gov Hand-Carried Address:
ATTN: Diana J. Pittman, Contract Officer Network Contracting Office (NCO) 10 5500 Armstrong Rd.
Building 9, Room 107 Battle Creek MI 49037 Mailing Address:
ATTN: Diana J. Pittman, Contract Officer Network Contracting Office (NCO) 10 5500 Armstrong Rd.
Building 9, Room 107 Battle Creek MI 49037
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of Provision)
2.6 FAR 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for—
SEE SECTION TITLED "SITE VISIT INFORMATION"
(c) Participants will meet at—
SEE SECTION TITLED "SITE VISIT INFORMATION"
(End of Provision)
2.7 FAR 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/
(End of Provision)
| FAR Number |
| Title |
| Date |
| 52.204-7 |
| SYSTEM FOR AWARD MANAGEMENT |
| OCT 2018 |
| 52.204-16 |
| COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING |
| JUL 2016 |
| 52.204-22 |
| ALTERNATIVE LINE ITEM PROPOSAL |
| JAN 2017 |
| 52.211-6 |
| BRAND NAME OR EQUAL |
| AUG 1999 |
| 52.214-3 |
| AMENDMENTS TO INVITATIONS FOR BIDS |
| DEC 2016 |
| 52.214-4 |
| FALSE STATEMENTS IN BIDS |
| APR 1984 |
| 52.214-5 |
| SUBMISSION OF BIDS |
| DEC 2016 |
| 52.214-6 |
| EXPLANATION TO PROSPECTIVE BIDDERS |
| APR 1984 |
| 52.214-7 |
| LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS |
| NOV 1999 |
| 52.214-18 |
| PREPARATION OF BIDS—CONSTRUCTION |
| APR 1984 |
| 52.214-19 |
| CONTRACT AWARD—SEALED BIDDING—CONSTRUCTION |
| AUG 1996 |
| 52.214-34 |
| SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE |
| APR 1991 |
| 52.214-35 |
| SUBMISSION OF OFFERS IN U.S. CURRENCY |
| APR 1991 |
2.8 FAR VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) Prime contractors are encouraged to assist service-disabled veteran-owned and veteran-owned small business potential subcontractors in obtaining bonding, when required. Mentor firms are encouraged to assist protégé firms under VA's Mentor-Protégé Program in obtaining acceptable bid, payment, and performance bonds, when required, as a prime contractor under a solicitation or contract and in obtaining any required bonds under subcontracts.
(End of Clause)
2.9 FAR VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS-CPM) (NOV 2018)
(a) Retainage:
(1) The contracting officer may retain funds—
(i) Where performance under the contract has been determined to be deficient or the Contractor has performed in an unsatisfactory manner in the past; or
(ii) As the contract nears completion, to ensure that deficiencies will be corrected and that completion is timely.
(2) Examples of deficient performance justifying a retention of funds include, but are not restricted to, the following—
(i) Unsatisfactory progress as determined by the Contracting Officer;
(ii) Failure to meet schedule in Schedule of Work Progress;
(iii) Failure to present submittals in a timely manner; or
(iv) Failure to comply in good faith with approved subcontracting plans, certifications, or contract requirements.
(3) Any level of retention shall not exceed 10 percent either where there is determined to be unsatisfactory performance, or when the retainage is to ensure satisfactory completion. Retained amounts shall be paid promptly upon completion of all contract requirements, but nothing contained in this paragraph (a)(3) shall be construed as limiting the Contracting Officer’s right to withhold funds under other provisions of the contract or in accordance with the general law and regulations regarding the administration of Government contracts.
(b) The Contractor shall submit a schedule of cost to the Contracting Officer for approval within 30 calendar days after date of receipt of notice to proceed. Such schedule will be signed and submitted in triplicate. The approved cost schedule will be one of the bases for determining progress payments to the Contractor for work completed. This schedule shall show cost by the work activity/event for each building or unit of the contract, as instructed by the resident engineer.
(1) The work activities/events shall be subdivided into as many sub-activities/events as are necessary to cover all component parts of the contract work.
(2) Costs as shown on this schedule must be true costs and the resident engineer may require the Contractor to submit the original estimate sheets or other information to substantiate the detailed makeup of the schedule.
(3) The sums of the sub-activities/events, as applied to each work activity/event, shall equal the total cost of such work activity/event. The total cost of all work activities/events shall equal the contract price.
(4) Insurance and similar items shall be prorated and included in the cost of each branch of the work.
(5) The cost schedule shall include separate cost information for the systems listed in the table in this paragraph (b)(5). The percentages listed below are proportions of the cost listed in the Contractor’s cost schedule and identify, for payment purposes, the value of the work to adjust, correct and test systems after the material has been installed. Payment of the listed percentages will be made only after the Contractor has demonstrated that each of the systems is substantially complete and operates as required by the contract.
VALUE OF ADJUSTING, CORRECTING, AND TESTING SYSTEM
| System |
| Percent |
| Pneumatic tube system |
| 10 |
| Incinerators (medical waste and trash) |
| 5 |
| Sewage treatment plant equipment |
| 5 |
| Water treatment plant equipment |
| 5 |
| Washers (dish, cage, glass, etc.) |
| 5 |
| Sterilizing equipment |
| 5 |
| Water distilling equipment |
| 5 |
| Prefab temperature rooms (cold, constant temperature) |
| 5 |
| Entire air-conditioning system (Specified under 600 Sections) |
| 5 |
| Entire boiler plant system (Specified under 700 Sections) |
| 5 |
| General supply conveyors |
| 10 |
| Food service conveyors |
| 10 |
| Pneumatic soiled linen and trash system |
| 10 |
| Elevators and dumbwaiters |
| 10 |
| Materials transport system |
| 10 |
| Engine-generator system |
| 5 |
| Primary switchgear |
| 5 |
| Secondary switchgear |
| 5 |
| Fire alarm system |
| 5 |
| Nurse call system |
| 5 |
| Intercom system |
| 5 |
| Radio system |
| 5 |
| TV (entertainment) system |
| 5 |
(c) In addition to this cost schedule, the Contractor shall submit such unit costs as may be specifically requested. The unit costs shall be those used by the Contractor in preparing its bid and will not be binding as pertaining to any contract changes.
(d) The Contracting Officer will consider for monthly progress payments material and/or equipment procured by the Contractor and stored on the construction site, as space is available, or at a local approved location off the site, under such terms and conditions as the Contracting Officer approves, including but not limited to the following—
(1) The materials or equipment are in accordance with the contract requirements and/or approved samples and shop drawings;
(2) The materials and/or equipment are approved by the resident engineer;
(3) The materials and/or equipment are stored separately and are readily available for inspection and inventory by the resident engineer;
(4) The materials and/or equipment are protected against weather, theft and other hazards and are not subjected to deterioration; and
(5) The Contractor obtains the concurrence of its surety for off-site storage.
(e) The Government reserves the right to withhold payment until samples, shop drawings, engineer’s certificates, additional bonds, payrolls, weekly statements of compliance, proof of title, nondiscrimination compliance reports, or any other requirements of this contract, have been submitted to the satisfaction of the Contracting Officer.
(f) The Contracting Officer will notify the Contractor in writing within 10 calendar-days of exercising retainage against any payment in accordance with FAR clause 52.232-5(e). The notice shall disclose the amount of the retainage in value and percent retained from the payment, and provide explanation for the retainage.
(End of Clause)
2.10 FAR VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)
(a) Any protest filed by an interested party shall—
(1) Include the name, address, fax number, email and telephone number of the protester;
(2) Identify the solicitation and/or contract number;
(3) Include an original signed by the protester or the protester’s representative and at least one copy;
(4) Set forth a detailed statement of the legal and factual grounds of the protest, including a description of resulting prejudice to the protester, and provide copies of relevant documents;
(5) Specifically request a ruling of the individual upon whom the protest is served;
(6) State the form of relief requested; and
(7) Provide all information establishing the timeliness of the protest.
(b) Failure to comply with the above may result in dismissal of the protest without further consideration.
(c) Bidders/offerors and Contracting Officers are encouraged to use alternative dispute resolution (ADR) procedures to resolve protests at any stage in the protest process. If ADR is used, the Department of Veterans Affairs will not furnish any documentation in an ADR proceeding beyond what is allowed by the Federal Acquisition Regulation.
(End of Provision)
2.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)
(a) As an alternative to filing a protest with the Contracting Officer, an interested party may file a protest by mail or electronically with: Executive Director, Office of Acquisition and Logistics, Risk Management and Compliance Service (003A2C), Department of Veterans Affairs, 810 Vermont Avenue NW, Washington, DC 20420 or Email: EDProtests@va.gov.
(b) The protest will not be considered if the interested party has a protest on the same or similar issue(s) pending with the Contracting Officer.
(End of Provision) PLEASE NOTE: The correct mailing information for filing alternate protests is as follows:
| Deputy Assistant Secretary for Acquisition and Logistics, |
| Risk Management Team, Department of Veterans Affairs |
| 810 Vermont Avenue, N.W. |
| Washington, DC 20420 |
Or for solicitations issued by the Office of Construction and Facilities Management:
| Director, Office of Construction and Facilities Management |
| 811 Vermont Avenue, N.W. |
| Washington, DC 20420 |
2.12 FAR VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)
The contracting officer reserves the right to designate representatives to act for him/her in furnishing technical guidance and advice or generally monitor the work to be performed under this contract. Such designation will be in writing and will define the scope and limitation of the designee's authority. A copy of the designation shall be furnished to the contractor.
(End of Provision)
REPRESENTATIONS AND CERTIFICATIONS
3.1 FAR 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (OCT 2018)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.
(2) The small business size standard is $36.5 Million.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204–7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
[ ] (i) Paragraph (d) applies.
[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.
(vii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(viii) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.
(ix) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(x) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(xi) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(xii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.
(xiii) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xiv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.
(xv) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.
(xvi) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.
(xvii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.
(xviii) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.)
(xix) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.
(xx) 52.225-4, Buy American—Free Trade Agreements—Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225-3.
(A) If the acquisition value is less than $25,000, the basic provision applies.
(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.
(C) If the acquisition value is $50,000 or more but is less than $80,317, the provision with its Alternate II applies.
(D) If the acquisition value is $80,317 or more but is less than $100,000, the provision with its Alternate III applies.
(xxi) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.
(xxii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan—Certification. This provision applies to all solicitations.
(xxiii) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certifications. This provision applies to all solicitations.
(xxiv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.
(A) Solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions; and
(B) For DoD, NASA, and Coast Guard acquisitions, solicitations that contain the clause at 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns.
(2) The following representations or certifications are applicable as indicated by the Contracting Officer:
[X](i) 52.204-17, Ownership or Control of Offeror.
[X](ii) 52.204-20, Predecessor of Offeror.
[](iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.
[](iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment—Certification.
[](v) 52.222-52, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services—Certification.
[](vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA-Designated Products (Alternate I only).
[](vii) 52.227-6, Royalty Information.
[](A) Basic.
[](B) Alternate I.
[](viii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.
(d) The Offeror has completed the annual representations and certifications electronically in SAM accessed through https://www.sam.gov. After reviewing the SAM information, the Offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.
| FAR Clause # |
| Title |
| Date |
| Change |
Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.
(End of Provision)
3.2 FAR 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)
(a) Definitions. As used in this provision— "Administrative proceeding" means a non-judicial process that is adjudicatory in nature in order to make a determination of fault or liability (e.g., Securities and Exchange Commission Administrative Proceedings, Civilian Board of Contract Appeals Proceedings, and Armed Services Board of Contract Appeals Proceedings). This includes administrative proceedings at the Federal and State level but only in connection with performance of a Federal contract or grant. It does not include agency actions such as contract audits, site visits, corrective plans, or inspection of deliverables.
"Federal contracts and grants with total value greater than $10,000,000" means—
(1) The total value of all current, active contracts and grants, including all priced options; and
(2) The total value of all current, active orders including all priced options under indefinite-delivery, indefinite-quantity, 8(a), or requirements contracts (including task and delivery and multiple-award Schedules).
"Principal" means an officer, director, owner, partner, or a person having primary management or supervisory responsibilities within a business entity (e.g., general manager; plant manager; head of a division or business segment; and similar positions).
(b) The offeror [ ] has [ ] does not have current active Federal contracts and grants with total value greater than $10,000,000.
(c) If the offeror checked "has" in paragraph (b) of this provision, the offeror represents, by submission of this offer, that the information it has entered in the Federal Awardee Performance and Integrity Information System (FAPIIS) is current, accurate, and complete as of the date of submission of this offer with regard to the following information:
(1) Whether the offeror, and/or any of its principals, has or has not, within the last five years, in connection with the award to or performance by the offeror of a Federal contract or grant, been the subject of a proceeding, at the Federal or State level that resulted in any of the following dispositions:
(i) In a criminal proceeding, a conviction.
(ii) In a civil proceeding, a finding of fault and liability that results in the payment of a monetary fine, penalty, reimbursement, restitution, or damages of $5,000 or more.
(iii) In an administrative proceeding, a finding of fault and liability that results in—
(A) The payment of a monetary fine or penalty of $5,000 or more; or
(B) The payment of a reimbursement, restitution, or damages in excess of $100,000.
(iv) In a criminal, civil, or administrative proceeding, a disposition of the matter by consent or compromise with an acknowledgment of fault by the Contractor if the proceeding could have led to any of the outcomes specified in paragraphs (c)(1)(i), (c)(1)(ii), or (c)(1)(iii) of this provision.
(2) If the offeror has been involved in the last five years in any of the occurrences listed in (c)(1) of this provision, whether the offeror has provided the requested information with regard to each occurrence.
(d) The offeror shall post the information in paragraphs (c)(1)(i) through (c)(1)(iv) of this provision in FAPIIS as required through maintaining an active registration in the System for Award Management, which can be accessed via https://www.sam.gov (see 52.204-7).
(End of Provision)
3.3 FAR 52.209-13 VIOLATION OF ARMS CONTROLS TREATIES OR AGREEMENTS—CERTIFICATION (JUN 2018)
(a) This provision does not apply to acquisitions below the simplified acquisition threshold or to acquisitions of commercial items as defined at FAR 2.101.
(b) Certification. [Offeror shall check either (1) or (2).]
(1) The Offeror certifies that—
(i) It does not engage and has not engaged in any activity that contributed to or was a significant factor in the President’s or Secretary of State’s determination that a foreign country is in violation of its obligations undertaken in any arms control, nonproliferation, or disarmament agreement to which the United States is a party, or is not adhering to its arms control, nonproliferation, or disarmament commitments in which the United…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.