36C24818R0001-A00002000.docx

DOCX document 18 KB Posted

Attached to
Improve Patient Space 1A Federal contract opportunity
Solicitation number
36C24818R0001
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 8

About this file

36C24818R0001 A00002 36C24818R0001 A00002.docx

View the file

Other files for this federal contract opportunity

Other files attached to Improve Patient Space 1A, newest first.
File Type Posted
36C24818C0152-000.docx DOCX document
36C24818R0001-A00001001.docx DOCX document
36C24818R0001-001.docx DOCX document
36C24818R0001-013.pdf PDF
36C24818R0001-008.pdf PDF
36C24818R0001-011.docx DOCX document
36C24818R0001-003.docx DOCX document
36C24818R0001-004.docx DOCX document
36C24818R0001-012.pdf PDF
36C24818R0001-009.pdf PDF
36C24818R0001-002.docx DOCX document
36C24818R0001-010.pdf PDF
36C24818R0001-005.docx DOCX document
36C24818R0001-007.docx DOCX document
36C24818R0001-006.docx DOCX document
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE

OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

BY

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) A00002 03-14-2018 548-18-601 36C548 Department of Veterans Affairs West Palm Beach VA Medical Center 7305 North Military Trail Palm Beach Gardens

FL

33410-6400 36C548 Department of Veterans Affairs Network Contracting Office 8 (NCO 8) West Palm Beach VA Medical Center 7305 North Military Trail Palm Beach Gardens

FL

33410-6400 To all Offerors/Bidders

36C24818R0001 03-14-2018

X X X X The purpose of this amendment is to post the answers to the submitted RFI (Request for Information) questions.

Phase 1 RFI submission is closed. Proposal due date is unchanged and are due 3-19-2018, 4:00 PM EST.

Jose Delgado Contracting Officer

1. In the Original Solicitation, page 10 of 57, Factor 1 Technical Approach, we are required to describe technical methods and procedures we will employ to develop the project. In order to thoroughly describe our approach, we need to understand the basic intent for the remodeled 7000 square feet area. Is this area intended to be Patient reception and waiting, exam rooms, Radiology and/or MRI Testing, staff office space, nursing station, etc.? Depending on the intended use, certain construction preparation and approaches may be affected. Please describe the intended use of the 7000-square foot area to be remodeled.

Answer: The SOW was written to include “Programming”, for the A/E to provide the time and resource for this phase of the project.

2. Original Solicitation, page 5 of 57, item c states “at the end of each daily shift, spaces must be patient ready”. This won’t be possible in the 7000-square foot of remodeled areas requiring new walls, ceilings and mechanical electrical, etc. The other 20,000 square feet of renovated finishes can be occupied at the end of each work shift. Can the 7000 square feet of space be barricaded and contained under negative air for several weeks while it is being remodeled?

Answer: Answer in the SOW the A/E is required to provide a Phasing plan during the schematic phase of the project. This Phasing plan must reflect patient ready requirement.

3. In order to adequately describe our construction technical approach, will the 7000 square feet, composed of 2 separate areas (4200sf & 2600 sf respectively), need to be completed in different phases?

Answer: There are two separate areas that are shown as dotted area in the drawing that makes up the 7,000 sf of renovated space.

File details come from the government source that posted it.