36C24818Q0731-002.pdf

PDF 258 KB Posted

Attached to
Equipment: Boiler Plan Generator Federal contract opportunity
Solicitation number
36C24818Q0731
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 8

About this file

36C24818Q0731 Attachment B.pdf

View the file

Other files for this federal contract opportunity

Other files attached to Equipment: Boiler Plan Generator, newest first.
File Type Posted
-13796.docx DOCX document
36C24818Q0731-006.docx DOCX document
36C24818Q0731-000.docx DOCX document
36C24818Q0731-003.pdf PDF
36C24818Q0731-005.pdf PDF
36C24818Q0731-001.pdf PDF
36C24818Q0731-004.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment B

RFQ: 36C24818Q0731

Line Item Description Qty Unit

Unit Price

Total Price

New Permanent 150 kw, 480/277 VAC, 3 phase, diesel engine UL 2200 generator with exhaust/intake system, fuel system, electrical connection cabinet and Tier 3 equipped.

Includes:

1.Kirk key interlock system

2. External emergency stop switch

3. Local annunciator panel that meets the requirements ofNFPA99-10 with low oil pressure, high coolant temperature, overspeed, and over crank shutdowns.

4. Battery starting circuit with lead acid storage batteries. 10amp, 110-volt battery charger.

5. Anti-condensation heater, low coolant temperature alarm, and 2 kw, 240-volt jacket water heater

6. 4 Hour load bank at greater than or equal to 80 percent rated generator load meeting the requirements of NFPA 99, NFPA 70, and VHA directive1028. EA 1

Removal of existing 100 kw, 480/227

VAC, 3 phase emergency generator, intake and exhaust system, conduit and wiring.

Pictures of Existing Generator are located within Attachment E of this

Solicitation. EA 1

Provide and install 150 kw, 480/277

VAC, 3 phase portable generator during existing generator replacement. EA 1

Pump out existing 50-gallon day tank and replace with new fuel provided by

VA. EA 1

Install new external emergency stop switch on the outside wall of the facility. EA 1

Install kirk key interlock system on new generator electrical access door and existing electrical equipment. EA 1

0007 Install and Setup of New Generator EA 1

Total Cost