This is a solicitation for smoke and fire damper repair services at the Salem, Virginia Veterans Affairs Medical Center. The solicitation seeks repair of smoke and fire dampers in four buildings onsite, with a period of performance from August 15, 2023 through October 31, 2023. The Department of Veterans Affairs Network Contracting Office 6 will administer the contract, which has a total estimated value of $16.5 million. The solicitation is a total small business set-aside for certified service-disabled veteran-owned small businesses. Responses are due by July 17, 2023 at 4:00pm EDT. Pricing will be on a firm fixed-price basis.

View the file

Other files for this federal contract opportunity

Other files attached to H312--Smoke and Fire Damper Repairs, newest first.
File Type Posted
2023 Fire and Smoke Damper Deficiency Tracker.xlsx XLSX spreadsheet
36C24623Q0976 0002.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C24623Q0976

PAGE 1 OF

1. REQUISITION NO.

2. CONTRACT NO.

3. AWARD/EFFECTIVE DATE

4. ORDER NO.

5. SOLICITATION NUMBER

6. SOLICITATION ISSUE DATE

a. NAME

b. TELEPHONE NO. (No Collect Calls)

8. OFFER DUE

DATE/LOCAL

TIME

9. ISSUED BY

CODE

10. THIS ACQUISITION IS

UNRESTRICTED OR

SET ASIDE:

% FOR:

SMALL BUSINESS

HUBZONE SMALL

BUSINESS

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

WOMEN-OWNED SMALL BUSINESS

(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

8(A)

NAICS:

SIZE STANDARD:

11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

12. DISCOUNT TERMS

13a. THIS CONTRACT IS A

RATED ORDER UNDER

DPAS (15 CFR 700)

13b. RATING

14. METHOD OF SOLICITATION

RFQ

IFB

RFP

15. DELIVER TO

CODE

16. ADMINISTERED BY

CODE

17a. CONTRACTOR/OFFEROR

CODE

FACILITY CODE

18a.

PAYMENT WILL BE MADE BY

CODE

TELEPHONE NO.

UEI:

EFT:

PHONE:

FAX:

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED

SEE

ADDENDUM

19.

20.

21.

22.

23.

24.

ITEM NO.

SCHEDULE OF SUPPLIES/SERVICES

QUANTITY

UNIT

UNIT PRICE

AMOUNT

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA

26.

TOTAL AWARD AMOUNT (For Govt. Use Only) 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA

ARE

ARE NOT ATTACHED.

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212

-4. FAR 52.212-5 IS ATTACHED. ADDENDA

ARE

ARE NOT ATTACHED

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________

29. AWARD OF CONTRACT: REF. ___________________________________ OFFER

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

DATED ________________________________. YOUR OFFER ON SOLICITATION

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED

SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:

30a. SIGNAT

URE OF OFFEROR/CONTRACTOR

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) 30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION

(REV. NOV 2021)

PREVIOUS EDITION IS NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.212

7. FOR SOLICITATION

INFORMATION CALL:

STANDARD FORM 1449

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL

PRODUCTS AND COMMERCIAL SERVICES

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

36C24623Q0976 David Hoover 07-17-2023 4:00pm

EDT

Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667 X X 238220 $16.5 Million N/A X Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667 Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667

Department of Veterans Affairs Financial Services Center

PO BOX 149971

Austin TX 78714-9971 512-460-5049 512-460-5221 X See CONTINUATION Page This is a firm fixed price service requirement for Fire Fire and Smoke Damper repair at the Salem, VA Veterans Administration Medical Center.

See CONTINUATION Page X X Byron Brown Table of Contents

SECTION A1
A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES1
SECTION B - CONTINUATION OF SF 1449 BLOCKS3
B.1 CONTRACT ADMINISTRATION DATA3
B.2 PRICE/COST SCHEDULE4
ITEM INFORMATION4
B.3 Performance Work Statement5
B.4 SPECIAL CONTRACT REQUIREMENTS8
SECTION C - CONTRACT CLAUSES11
C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (DEC 2022)11
C.2 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)15
C.3 VAAR 852.201-70 CONTRACTING OFFICER'S REP. (DEC 2022)15
C.4 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION)15
C.5 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION)17
C.6 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)19
C.7 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)19
C.8 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (MAR 2023)20
SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS25
D.1 DOL Wage Determination25
D.1 Quality Assurance Surveillance Plans (QASP)26
SECTION E - SOLICITATION PROVISIONS33
E.1 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (MAR 2023)33
E.3 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)39
E.4 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (DEC 2022)40

SECTION B - CONTINUATION OF SF 1449 BLOCKS

B.1 CONTRACT ADMINISTRATION DATA

1. Contract Administration: All contract administration matters will be handled by the following individuals:

a. CONTRACTOR:

b. GOVERNMENT: Contracting Officer 36C246

Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667

2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:

[X]
52.232-33, Payment by Electronic Funds Transfer—System For Award Management, or
[]
52.232-36, Payment by Third Party

3. INVOICES: Invoices shall be submitted in arrears:

a. Quarterly[]
b. Semi-Annually[]
c. Other[X] Monthly in arears

4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests.

ACKNOWLEDGMENT OF AMENDMENTS: The offeror acknowledges receipt of amendments to the Solicitation numbered and dated as follows:

AMENDMENT NO
DATE

B.2 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1.00
EA
__________________
__________________

1) Repair of Smoke and Fire Dampers in Building 2, 2A, 7, and 143 Contract Period: Base POP Begin: 08-15-2023 POP End: 10-31-2023

LOCAL STOCK NUMBER: SMOKE/FIRE DAMPER RPRS

GRAND TOTAL
__________________

B.3 Performance Work Statement

Repairs of Smoke and Fire Dampers Salem, VA, VAMC

1. General. The contractor shall provide all labor, supervision, tools, new parts, materials, equipment, transportation, and management necessary to perform Smoke and Fire Damper Repairs in Buildings 2, 2A, 7, 143 as follows:

· Repair and re-inspection of the fire dampers that previously failed during inspection.

· Install access to Dampers.

· Fire Dampers in the following areas that will be repaired are as follows:

2. Requirements. The Contractor shall provide a schedule for this Inspection of smoke and fire dampers. Upon award, the contractor shall schedule these services within 14 business days.

a. Unless specified elsewhere, all parts, labor, and other materials, required to perform this contract will be provided by the contractor.

b. Upon completion of repair work, contractor shall provide a detailed field report outlining work completed during the visit including any repairs or adjustments that were performed, and a list of parts used and labor hours/monetary cost.

Fire Dampers that need access installed to test have not been accessed or tested and may need an additional scope of work to repair/replace and pass. We cannot provide a complete and comprehensive repair until access is first made to the damper. We will not proceed with additional work until it has been approved and authorized. Dampers found needing to be replaced after we have made access are not included in this scope of work and proposal.

A. Required Re-test after Repairs: In accordance with code 19.5.4 all fire dampers must be re-tested after repairs.

B. Fire Dampers that apply to this contract: In these areas, it is possible that there are more dampers installed than appear on the drawings or the facilities’ records. This contract applies to the known, marked, or previously labeled fire dampers.

C. Smoke Dampers:

Any smoke dampers will require the partnership of the alarm/smoke detector control agency to actuate these dampers while we test/verify operation. Costs for having the alarm/controls company on site to assist are not included in this proposal. Otherwise, air or electronic actuated dampers will be visibly inspected for component operability.

3. The Federal Government will not be responsible for any Unauthorized Goods or Services.

4. Government Furnished Equipment. This is a full-service contract with the contractor providing all necessary items required to accomplish this performance work statement.

5. Site Visits and Proposals. Perspective Contractors are encouraged to accomplish a site visit. Site visits will be consolidated, scheduled, and coordinated through the Contracting Officer. Unannounced site visits will not be honored. The Federal Government will not incur any costs associated with site visits.

6. Clean-up. The contractor will remove all debris, containers, and other materials, on a daily basis, resulting from his work and leave the premises clean. All debris, containers and other materials must be removed from the limits of the Facility and not be placed in government-owned dumpsters, except with prior approval of the COR. All handprints, grease smears, etc., are to be removed. Any paint chipped, scratched, or damaged will be repaired to the satisfaction of the COR.

7. Final Services. The contractor will provide a written report on work performed, along with a statement, as to the final condition of the equipment. The final services report is to be received by the Contracting Office before final payment is made. Any manuals should be returned to the COR and remain the property of the Government.

8. Electric Work. All electrical work will conform to the latest requirements of the National Electrical Code.

9. Other Station Rules and Guidelines. The contractor will adhere to the following station rules.

9.1 All work will be accomplished to industry standards and compliant with all current CODE requirements (Life Safety, NFPA, Electrical, and Building). All Department of Veteran Affairs, Federal regulations, and codes will be complied with.

9.2 This is a hospital environment. The Contractor and his personnel are expected to be appropriately dressed (preferably uniformed) and to conduct themselves professionally, with a minimum amount of noise.

9.3 This is a federal facility as well as a medical center. As such, there is NO tobacco usage allowed inside any federal building or on the grounds. The Safety Service will brief the Contractor as to the designated smoking areas prior to commencement of the contract. Failure to follow these regulations can result in removal of the worker or Contractor from the facility and/or a US Magistrate’s ticket and fine.

9.4 Parking will be in designated lots. Consult with the VA police as to allowable parking and material drop-off when you arrive on station. Valet parking is only for patients and should not be utilized.

9.5 The Contractor will be responsible for ensuring that all the employees and other personnel visiting the work site have and are using the appropriate Personal Protective Equipment (PPE) that addresses the particular hazards found at the site. The Contractor will be responsible for the upkeep, issue, and training for the PPE used and maintaining all required documentation. Full compliance with OSHA regulations regarding PPE is expected.

9.6 The Contractor shall provide copies of the Safety Data Sheets (SDS) for any chemicals brought onto the Station for this project to the Safety Office.

9.7 Any work requiring a shutdown or utility outage will be requested in advance and scheduled by the COR prior to the work being accomplished.

9.8 The contractor will coordinate his activities with the COR to identify any smoke or fire barriers that must be penetrated or disrupted as a result of this contract and shall restore the fire barrier to its rating through the use of fire-stopping. The contractor and his personnel shall be trained and certified to use and apply fire-stopping prior to its application and at the contractor’s expense.

9.9 The contractor will exercise extreme care while working to maintain the integrity of the roof in the area of his/her work. Damage to the roof by the contractor due to negligence will become the responsibility of the contractor to repair. The COR and Contractor will inspect the work site together to establish a record of preexisting faults or damage prior to the contractor commencing work.

10. Deliverables. The contractor shall provide a detailed field report outlining work completed during each visit including any repairs or adjustments that were performed, and a list of parts needed and labor hours.

11. Key Personnel: Key personnel will be identified at the time of project award and shall be considered key personnel essential for the successful completion of the work performed under the contract. The contractor agrees that such personnel shall not be removed, diverted, or replaced from the work without prior written approval of the Contracting Officer. The contractor shall submit written notice of proposed personnel changes to the Contracting Officer for approval at least thirty (30) business days in advance.

B.4 SPECIAL CONTRACT REQUIREMENTS

A. WORK HOURS

The services covered by this contract shall be furnished by the contractor as defined herein. The contractor shall not be required, except in case of emergency, to furnish such services on Federal Holidays or during off duty hours as described below.

The following terms have the following meanings:

2.1. Normal working hours: Monday through Friday, 7:30 a.m. – 4:00 p.m., excluding federal holidays. The 11 holidays observed by the Federal Government are:

New Year’s DayBirthday of Martin Luther King, Jr.
Washington’s BirthdayMemorial Day
Juneteenth National Independence DayIndependence Day
Labor DayColumbus Day
Veterans DayThanksgiving Day

Christmas Day Work outside these hours must be prescheduled and approved by the COR.

When one of the holidays falls on Sunday, the following Monday shall be observed as a Federal Holiday. When a holiday falls on a Saturday, the preceding Friday shall be observed as a Federal Holiday.

Smoking Policy Per VHA Directive 1085 Dated 3/15/19 All VA Health Care Facilities shall be smoke free. This directive applies to all patients, visitors, contractors, volunteers, and vendors.

B. BILLING AND PAYMENT

To allow time for review and acceptance of reports and all services, the Contractor shall invoice semi-annually, December for November services, and in July for May and June services.

Invoices shall include at a minimum:

· Date of invoice

· Contract Number

· Purchase Order Number

· Vendor Name

· Invoice Number

· CLIN & Date of service

C. CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM (CPARS)

(a) FAR 42.1502 direct all Federal agencies to collect past performance information on contracts. The Department of Veterans Affairs has implemented use of the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15

(b) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.

(c) Please furnish the Contracting Officer with the name, position title, phone number, and email address for each person designated to have access to your firm’s past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official. The report information must be protected as source selection sensitive information not releasable to the public.

(d) When your Contractor Representative(s) (Past Performance Points of Contact) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, system requirements, and training information for CPARS are available at www.cpars.gov. The CPARS User Manual, registration for online training for Contractor Representatives may be found at this site.

(e) Within 60 days after the end of a performance period, the Contracting Officer will complete an interim or final past performance evaluation and the report will be accessible at www.cpars.gov Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment. Comments are limited to the space provided in Block 22. Your comments should focus on objective facts in the Assessing Official’s narrative and should provide your views on the causes and ramifications of the assessed performance. In addition to the ratings and supporting narratives, blocks 1-17 should be reviewed for accuracy, as these include key fields that will be used by the Government to identify your firm in future source selection evaluations. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating, “No Comment” in Block 22, and then signing and dating Block 23 of the form. Without a statement in Block 22, you will be unable to sign and submit the evaluation back to the Government. If you do not sign and submit the CPAR within 30 days, it will automatically be returned to the Government and will be annotated: “The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment.” Your response is due within 30 calendar days after receipt of the CPAR.

(f) The following guidelines apply concerning your use of the past performance evaluation:

(1) Protect the evaluation as “source selection information.” After review, transit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the Contracting Officer for instructions.

(2) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.

(3) Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determination, production readiness reviews, or other similar purposes.

(g) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the Contracting Officer no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 30-day review period.

(h) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been completed.

D. QUALITY CONTROL

The Contractor shall develop a Quality Assurance Plan (QAP) which will provide the Contractor’s strategy for monitoring performance internally, providing performance information to the Government, and reporting in compliance with the PWS. Within the QAP, the Contractor shall propose and maintain an established reporting system to promptly notify VA of any problems, issues, risks, or concerns with workflow performance, programmatic improvement, security, and schedule adherence. Quality control is the exclusive responsibility of the Contractor.

The final plan shall be submitted to the CO and COR within 30 days of contract award.

E. QUALITY ASSURANCE SURVEILLANCE PLAN

The Government intends to utilize a Quality Assurance Surveillance Plan (QASP) to monitor the quality of the contractor’s performance. The oversight provided for in the order and in the QASP will help to ensure that service levels reach and maintain the required levels throughout the contract term. Further, the QASP provides the COR with a proactive way to avoid unacceptable or deficient performance and provides verifiable input for the required Past Performance Information Assessments. The QASP will be finalized immediately following award. The QASP is a living document and may be updated by the Government as necessary.

F. BACKGROUND INVESTIGATIONS

A full background check is not required for this position; however, all contract employees must bring photo identification and advance notice from the requiring service to obtain a VA Badge in order to work on a VA Facility.

Upon award, the CO shall provide the contractor with detailed instructions on fulfilling security requirements

G. CONTRACT ADMINISTRATION

Notwithstanding the Contractor's responsibility for total management during the performance of this contract, the administration of the contract will require maximum coordination between the Government and the Contractor.

The Contracting Officer is the only person authorized to approve changes or modify any of the requirements of this contract. The Contractor shall communicate with the Contracting Officer on all matters pertaining to contract administration. Only the Contracting Officer is authorized to make commitments or issue changes that shall affect price, quantity, or quality of performance of this contract.

The COR shall be responsible for the overall technical administration of this contract as outlined in the COR Delegation of Authority.

IN THE EVENT THE CONTRACTOR EFFECTS ANY SUCH CHANGE AT THE DIRECTION OF

ANY PERSON OTHER THAN THE CONTRACTING OFFICER WITHOUT AUTHORITY, NO ADJUSTMENT SHALL BE MADE IN THE CONTRACT PRICE TO COVER AN INCREASE IN COSTS INCURRED AS A RESULT THEREOF

POINTS OF CONTACT

Contracting Officer’s (CO)Contracting Specialist (CS)
Byron Brown, Branch Chief, Services 1David Hoover, Services 1
Department of Veterans AffairsDepartment of Veterans Affairs
Network Contracting Office (NCO) 6Network Contracting Office (NCO) 6
100 Emancipation Drive, building 27100 Emancipation Drive, Building 27
Hampton, Virginia 23667Hampton, Virginia 23667
david.hoover5@va.gov

Contracting Officer’s Representative (COR)

TBD

SECTION C - CONTRACT CLAUSES

C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (DEC 2022)

(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights—

(1) Within a reasonable time after the defect was discovered or should have been discovered; and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.

(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.

(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at Federal Acquisition Regulation (FAR) 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.

(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.

(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.

(g) Invoice.

(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include—

(i) Name and address of the Contractor;

(ii) Invoice date and number;

(iii) Contract number, line item number and, if applicable, the order number;

(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;

(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;

(vi) Terms of any discount for prompt payment offered;

(vii) Name and address of official to whom payment is to be sent;

(viii) Name, title, and phone number of person to notify in event of defective invoice; and

(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.

(x) Electronic funds transfer (EFT) banking information.

(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.

(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer—Other Than System for Award Management), or applicable agency procedures.

(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.

(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.

(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.

(i) Payment.—

(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.

(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.

(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.

(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.

(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—

(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—

(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);

(B) Affected contract number and delivery order number, if applicable;

(C) Affected line item or subline item, if applicable; and

(D) Contractor point of contact.

(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.

(6) Interest.

(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.

(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.

(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if—

(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;

(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or

(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).

(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.

(v) Amounts shall be due at the earliest of the following dates:

(A) The date fixed under this contract.

(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.

(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—

(A) The date on which the designated office receives payment from the Contractor;

(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or

(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.

(vii) The interest charge made under this clause may be reduced under the procedures prescribed in FAR 32.608-2 in effect on the date of this contract.

(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:

(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or

(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.

(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.

(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.

(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.

(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.

(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.

(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.

(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 41 U.S.C. 4712 and 10 U.S.C. 4701 relating to whistleblower protections; 49 U.S.C. 40118, Fly American; and 41 U.S.C. chapter 21 relating to procurement integrity.

(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:

(1) The schedule of supplies/services.

(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;

(3) The clause at 52.212-5.

(4) Addenda to this solicitation or contract, including any license agreements for computer software.

(5) Solicitation provisions if this is a solicitation.

(6) Other paragraphs of this clause.

(7) The Standard Form 1449.

(8) Other documents, exhibits, and attachments

(9) The specification.

(t) [Reserved]

(u) Unauthorized Obligations.

(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:

(i) Any such clause is unenforceable against the Government.

(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an “I agree” click box or other comparable mechanism (e.g., “click-wrap” or “browse-wrap” agreements), execution does not bind the Government or any Government authorized end user to such clause.

(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.

(2) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.

(v) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.

(End of Clause) ADDENDUM to FAR 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES Clauses that are incorporated by reference (by Citation Number, Title, and Date), have the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available.

The following clauses are incorporated into 52.212-4 as an addendum to this contract:

C.2 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

https://www.acquisition.gov/browse/index/far https://www.va.gov/oal/library/vaar/ (End of Clause)

FAR Number
Title
Date
52.204-13
SYSTEM FOR AWARD MANAGEMENT MAINTENANCE
OCT 2018
52.204-18
COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE
AUG 2020
852.203-70
COMMERCIAL ADVERTISING
MAY 2018

C.3 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)

The Contracting Officer reserves the right to designate representatives to act for him/her in furnishing technical guidance and advice or generally monitor the work to be performed under this contract. Such designation will be in writing and will define the scope and limitation of the designee’s authority. A copy of the designation letter shall be furnished to the Contractor.

(End of Clause)

C.4 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION)

(a) Definition. for the Department of Veterans Affairs, ‘‘Service-disabled Veteran-owned small business concern or SDVOSB’’:

(1) Means a small business concern—

(i) Not less than 51 percent of which is owned by one or more service-disabled Veterans or, in the case of any publicly owned business, not less than 51 percent of the stock of which is owned by one or more service-disabled Veterans or eligible surviving spouses (see VAAR 802.201, Surviving Spouse definition);

(ii) The management and daily business operations of which are controlled by one or more service-disabled Veterans (or eligible surviving spouses) or, in the case of a service-disabled Veteran with permanent and severe disability, the spouse or permanent caregiver of such Veteran;

(iii) The business meets Federal small business size standards for the applicable North American Industry Classification System (NAICS) code identified in the solicitation document;

(iv) The business has been certified for ownership and control pursuant to 38 U.S.C. 8127, 13 CFR 128, and is listed as certified in the SBA certification database at https://veterans.certify.sba.gov/; and

(v) The business agrees to comply with VAAR subpart 819.70 and Small Business Administration (SBA) regulations regarding small business size, government contracting, and the Veteran Small Business Certification Program at 13 CFR parts 121, 125, and 128.

(2) The term ‘‘Service-disabled Veteran’’ means a Veteran, as defined in 38 U.S.C. 101(2), with a disability that is service-connected, as defined in 38 U.S.C. 101(16).

(3) The term ‘‘small business concern’’ has the meaning given that term under section 3 of the Small Business Act (15 U.S.C. 632).

(4) The term ‘‘small business concern owned and controlled by Veterans with service-connected disabilities’’ has the meaning given the term ‘‘small business concern owned and controlled by service-disabled veterans’’ under section 3(q)(2) of the Small Business Act (15 U.S.C. 632(q)(2)).

(5) The term “SDVOSB participant” or certified SDVOSB means a small business that has been certified in the SBA Veteran Small Business Certification Program and listed in the SBA certification database (see 13 CFR 128.102).

(b) General. In order for a concern to submit an offer and be eligible for the award of an SDVOSB set-aside or sole source contract, the concern must qualify as a small business concern under the size standard corresponding to the NAICS code assigned to the contract and be listed as an SDVOSB participant in the SBA certification database as set forth in 13 CFR 128.

(1) Offers received from entities that are not certified SDVOSBs and listed in the SBA certification database at the time of offer shall not be considered.

(2) Any award resulting from this solicitation shall be made to a certified SDVOSB listed in the SBA certification database who is eligible at the time of submission of offer(s) and at the time of award.

(3) The requirements in this clause apply to any contract, order or subcontract where the firm receives a benefit or preference from its designation as an SDVOSB, including set-asides, sole source awards, and evaluation preferences.

(c) Representation. Pursuant to 38 U.S.C. 8127(e), only certified SDVOSBs listed in the SBA certification database are considered eligible to receive award of a resulting contract. By submitting an offer, the prospective contractor represents that it is an eligible and certified SDVOSB as defined in this clause, 13 CFR 121, 125, and 128, and VAAR subpart 819.70.

(d) Agreement/LOS certification. When awarded a contract action, including orders under multipleaward contracts, an SDVOSB agrees that in the performance of the contract, the SDVOSB shall comply with requirements in VAAR subpart 819.70 and SBA regulations on small business size, and government contracting programs at 13 CFR part 121 and part 125, including the non-manufacturer rule and limitations on subcontracting (LOS) requirements in 13 CFR 121.406(b) and 13 CFR 125.6. For the purpose of limitations on subcontracting, only certified SDVOSBs listed in the SBA certification database (including independent contractors) shall be considered eligible and/or ‘‘similarly situated’’ (i.e., a firm that has the same small business program status as the prime contractor). An otherwise eligible firm further agrees to comply with the required LOS certification requirements in this solicitation (see 852.219–75 or 852.219–76 as applicable). These requirements are summarized as follows:

(1) Services. In the case of a contract for services (except construction), the SDVOSB prime contractor will not pay more than 50% of the amount paid by the government to the prime for contract performance to firms that are not certified SDVOSBs listed in the SBA certification database (excluding direct costs to the extent they are not the principal purpose of the acquisition and the SDVOSB/ VOSB does not provide the service, such as airline travel, cloud computing services, or mass media purchases). When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract.

(2) Supplies/products.

(i) In the case of a contract for supplies or products (other than from a non-manufacturer of such supplies), the SDVOSB prime contractor will not pay more than 50% of the amount paid by the government to the prime for contract performance, excluding the cost of materials, to firms that are not certified SDVOSBs listed in the SBA certification database. When a contract includes both supply and services, the 50 percent limitation shall apply only to the supply portion of the contract.

(ii) In the case of a contract for supplies from a non-manufacturer, the SDVOSB prime contractor will supply the product of a domestic small business manufacturer or processor, unless a waiver as described in 13 CFR 121.406(b)(5) has been granted. Refer to 13 CFR 125.6(a)(2)(ii) for guidance pertaining to multiple item procurements.

(3) General construction. In the case of a contract for general construction, the SDVOSB prime contractor will not pay more than 85% of the amount paid by the government to the prime for contract performance, excluding the cost of materials, to firms that are not certified SDVOSBs listed in the SBA certification database.

(4) Special trade construction contractors. In the case of a contract for special trade contractors, no more than 75% of the amount paid by the government to the prime for contract performance, excluding the cost of materials, may be paid to firms that are not certified SDVOSBs listed in the SBA certification database.

(5) Subcontracting. An SDVOSB subcontractor must meet the NAICS size standard assigned by the prime contractor and be certified and listed in the SBA certification database to count as similarly situated. Any work that a first tier SDVOSB subcontractor further subcontracts will count towards the percent of subcontract amount that cannot be exceeded. For supply or construction contracts, the cost of materials is excluded and not considered to be subcontracted. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the portion of the contract with the preponderance of the expenditure upon which the assigned NAICS is based. For information and more specific requirements, refer to 13 CFR 125.6.

(e) Required limitations on subcontracting compliance measurement period. An SDVOSB shall comply with the limitations on subcontracting as follows:

[] By the end of the base term of the contract or order, and then by the end of each subsequent option period; or [] By the end of the performance period for each order issued under the contract.

(f) Joint ventures. A joint venture may be considered eligible as an SDVOSB if the joint venture complies with the requirements in 13 CFR 128.402 and the managing joint venture partner makes the representations under paragraph (c) of this clause. A joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph (d) of this clause will be performed by the aggregate of the joint venture participants.

(g) Precedence. The VA Veterans First Contracting Program, as defined in VAAR 802.101, subpart 819.70, and this clause, takes precedence over any inconsistencies between the requirements of the SBA Veteran Small Business Certification Program and the VA Veterans First Contracting Program.

(h) Misrepresentation. Pursuant to 38 U.S.C. 8127(g), any business concern, including all its principals, that is determined by VA to have willfully and intentionally misrepresented a company’s SDVOSB status is subject to debarment from contracting with the Department for a period of not less than five years (see VAAR 809.406–2 Causes for Debarment).

(End of Clause)

C.5 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION)

(a) Pursuant to 38 U.S.C. 8127(l)(2), the offeror certifies that—

(1) If awarded a contract (see FAR 2.101 definition), it will comply with the limitations on subcontracting requirement as provided in the solicitation and the resultant contract, as follows:

(i) [] Services. In the case of a contract for services (except construction), the contractor will not pay more than 50% of the amount paid by the government to it to firms that are not certified SDVOSBs listed in the SBA certification database as set forth in 852.219–73 or certified VOSBs listed in the SBA certification database as set forth in 852.219–74. Any work that a similarly situated certified SDVOSB/VOSB subcontractor further subcontracts will count towards the 50% subcontract amount that cannot be exceeded. Other direct costs may be excluded to the extent they are not the principal purpose of the acquisition and small business concerns do not provide the service as set forth in 13 CFR 125.6.

(ii) [] General construction. In the case of a contract for general construction, the contractor will not pay more than 85% of the amount paid by the government to it to firms that are not certified SDVOSBs listed in the SBA certification database as set forth in 852.219–73 or certified VOSBs listed in the SBA certification database as set forth in 852.219–74. Any work that a similarly situated certified SDVOSB/VOSB subcontractor further subcontracts will count towards the 85% subcontract amount that cannot be exceeded. Cost of materials are excluded and not considered to be subcontracted.

(iii) [X] Special trade construction contractors. In the case of a contract for special trade contractors, the contractor will not pay more than 75% of the amount paid by the government to it to firms that are not certified SDVOSBs listed in the SBA certification database as set forth in 852.219–73 or certified VOSBs listed in the SBA…