36C24618R0239-001.docx

DOCX document 61 KB Posted

Attached to
Replace Windows Bldg 1 Federal contract opportunity
Solicitation number
36C24618R0239
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6

About this file

36C24618R0239 36C24618R0239_2.docx

View the file

Other files for this federal contract opportunity

Other files attached to Replace Windows Bldg 1, newest first.
File Type Posted
36C24618R0239-00003000.docx DOCX document
36C24618R0239-00002000.docx DOCX document
36C24618R0239-00001001.pdf PDF
36C24618R0239-00001000.docx DOCX document
36C24618R0239-003.pdf PDF
36C24618R0239-002.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FedBizOpps Combined Synopsis/Solicitation Notice

CLASSIFICATION CODE

SUBJECT

CONTRACTING OFFICE'S

ZIP-CODE

SOLICITATION NUMBER

RESPONSE DATE (MM-DD-YYYY)

ARCHIVE

DAYS AFTER THE RESPONSE DATE

RECOVERY ACT FUNDS

SET-ASIDE

NAICS CODE

CONTRACTING OFFICE

ADDRESS

POINT OF CONTACT

(POC Information Automatically Filled from User Profile Unless Entered)

DESCRIPTION

See Attachment

AGENCY'S URL

URL DESCRIPTION

AGENCY CONTACT'S EMAIL

ADDRESS

EMAIL DESCRIPTION

ADDRESS

POSTAL CODE

COUNTRY

ADDITIONAL INFORMATION

GENERAL INFORMATION

PLACE OF PERFORMANCE

* = Required Field FedBizOpps Combined Synopsis/Solicitation Notice Rev. March 2010 Z Replace Windows Bldg 1 28301 36C24618R0239 N 236220 Department of Veterans Affairs Network Contracting Office 6 201 Hay Street, Suite 304 Fayetteville NC 28301 Frank A. Fogg frank.fogg@va.gov 910-488-2120 x 5250 Fayetteville VAMC 2300 Ramsey St.

Fayetteville Bldg. 1

NC

28301 Frank.Fogg@va.gov Frank.Fogg@va.gov

1. SOLICITATION NO.

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NO.

5. REQUISITION/PURCHASE REQUEST NO.

6. PROJECT NO.

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

A. NAME

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12B.)

12B. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 4-85)

STANDARD FORM 1442

Prescribed by GSA YFAR (48 CFR) 52.236-1(d)

NSN 7540-01-155-3212

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See _____________________________.)

YES

NO

A.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due B.

An offer guarantee is, is not required.

C.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference D.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C24618R0239 X 04-09-2018

TBD

TBD

565-13-207 Department of Veterans Affairs Network Contracting Office 6 2300 Ramsey St Fayetteville NC 28301 Department of Veterans Affairs Network Contracting Office 6 ATTN: Frank A. Fogg 201 Hay St., Suite 305 Fayetteville NC 28301 Frank Fogg 910-488-2120 X 5250 Project Title: 565-13-207 Replace Windows BLDG. 1

The Contractor shall provide all supervision, labor, materials, and equipment necessary to complete Project 565-13-207 Replace BLDG. 1 windows at the Fayetteville VAMC in accordance with the plans and specifications Performance of this work shall meet all State, Federal, and Veterans Affairs regulations and

SDVOSB set aside for NAICS code 236220

Site Visit is scheduled for: Monday April 16, 2018 at 10:00 AM local at the Fayetteville VAMC

Final day for RFIs: Thursday April 19, 2018 at 4:00 PM local

Proposals Due Date:

Tuesday May

, 2018 at 4:00 PM local

X X 52.211-10 X N/A N/A X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NO.

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER

20B. SIGNATURE

20C. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 253(c) (

26. ADMINISTERED BY

CODE

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation, is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work, requisitions identified award consummates the contract. which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED

31A. NAME OF CONTRACTING OFFICER

TO SIGN

30B. SIGNATURE

30C. DATE

31B. UNITED STATES OF AMERICA

BY

OFFER

AWARD

STANDARD FORM 1442(REV. 4-85)BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14) (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

(The offeror acknowledges receipt of amendments to the solicitation - give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

Base Bid :$___________________________ Bid Alt Item I : $___________________________ Bid Alt Item II : $___________________________ Bid Alt Item III $___________________________ Department of Veterans Affairs Network Contracting Office 6 201 Hay St., Suite 304 Fayetteville NC 28301 Department of Veterans Affairs Financial Services Center

PO BOX 149971

Austin TX 78714-9971 Frank A. Fogg NCO 6 Contracting Officer

Table of Contents

PART I - THE SCHEDULE (R$PG1)2
SECTION A - SOLICITATION/CONTRACT FORM (R$PG#)2
SF 1442 SOLICITATION, OFFER, AND AWARD(I$DESC1-26) (Construction, Alteration, or Repair)(I$DESC2-26)2
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS8
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)14
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)14
2.3 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY 2014) ALTERNATE I (MAY 2014) AND ALTERNATE II (JUN 2009)14
2.4 52.228-1 BID GUARANTEE (SEP 1996)15
2.5 52.233-2 SERVICE OF PROTEST (SEP 2006)16
2.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)16
GENERAL CONDITIONS17
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)18
4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)19
4.3 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY 2014) ALTERNATE I (MAY 2014)19
4.4 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)23
4.5 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)24
4.6 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2012)24

Statement of Proposal Items The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within one-hundred and twenty (120) calendar days after the date offers are due.

BID ITEM I (Base Bid): Contractor shall provide all labor, materials, tools, equipment, and supervision, and perform all operations necessary for demolition, general construction, and alterations. The work includes modifications to the existing Surgical Suite in Building 1 area including removal and replacement of the indicated windows, repair, patching, and repainting of damaged surrounding walls, flashings and sealants and other work as necessary for a complete installation and as indicated and/or specified. All work to be completed in strict accordance with the attached drawings and specifications. All work, including final cleanup and completion of any punch list items, shall be performed within 270 calendar days after the date of receipt of notice to proceed.

BID ITEM I $_______________________________

BID ITEM II (Deduct Alternate 1): Contractor shall provide all labor, materials, tools, equipment, and supervision, and perform all operations necessary for the completion of Bid Item I (Base Bid), except Delete window removal and replacement for the “Awing “north elevation levels basement through level four in Building 1as identified on the drawings and/or designated in the specifications as Deduct Alternate #01: . All work to be completed in strict accordance with the attached drawings and specifications. All work, including final cleanup and completion of any punch list items, shall be performed within 270 calendar days after the date of receipt of notice to proceed.

BID ITEM II $_______________________________

NOTE: Offerors must submit an itemized breakdown of costs (Attachment A) for all Proposal Items, in sufficient detail to permit a complete analysis of labor burden, materials, equipment, transportation, supervision, disposal costs, overhead and profit and shall cover all work involved in the Task Order.

BID ITEM III (Deduct Alternate 2): Contractor shall provide all labor, materials, tools, equipment, and supervision, and perform all operations necessary for the completion of Bid Item I (Base Bid), minus Delete window removal and replacement for “C-wing “south elevation level 1 through level 5 in building 1 as identified on the drawings. and/or designated in the specifications . All work to be completed in strict accordance with the attached drawings and specifications. All work, including final cleanup and completion of any punch list items, shall be performed within 270 calendar days after the date of receipt of notice to proceed.

BID ITEM III $_______________________________

NOTE: Offerors must submit an itemized breakdown of costs (Attachment A) for all Proposal Items, in sufficient detail to permit a complete analysis of labor burden, materials, equipment, transportation, supervision, disposal costs, overhead and profit and shall cover all work involved in the Task Order.

BID ITEM IV (Deduct Alternate 3): Contractor shall provide all labor, materials, tools, equipment, and supervision, and perform all operations necessary for the completion of Bid Item I (Base Bid), except Delete brick removal and replacement for “A-wing “north elevation windows in building 1 as identified on the drawings. All work to be completed in strict accordance with the attached drawings and specifications. All work, including final cleanup and completion of any punch list items, shall be performed within 270 calendar days after the date of receipt of notice to proceed.

BID ITEM IV $_______________________________

NOTE: Offerors must submit an itemized breakdown of costs (Attachment A) for all Proposal Items, in sufficient detail to permit a complete analysis of labor burden, materials, equipment, transportation, supervision, disposal costs, overhead and profit and shall cover all work involved in the Task Order.

Submitted for:

Company Name __________________________________________

Submitted by:

Authorized Signature ___________________________________Date: ________________

Printed Name: _________________________________________

(This individual must be a legally authorized signatory of the company)

ACKNOWLEDGMENT OF AMENDMENTS

The person submitting the proposal on behalf of the offeror shall sign the area below titled “Acknowledged by” and shall initial/date in the space(s) below to acknowledge any Amendment(s).

NOTE: Failure to acknowledge Amendments may render your offer unacceptable.

CERTIFICATION

I/we have received and considered the following Amendment(s) in the submitted proposal for this project.

Amendment Number
None
A00001
A00002
A00003
A00004
A00005

Date

Initials

Acknowledged by: ________________________________________

Printed Name: ___________________________________________

STATEMENT OF WORK

January 22, 2018 VAMC Fayetteville, NC

I. PROJECT DATA:

TITLE: Replace Windows Bldg. 1

PROJECT No: 565-13-207 Contracting Officer’s Representative (COR): Tysun Dostie, Facilities Management Service (910-488-2120 x5604) Requestor: Wendy Gillis, Chief, Facilities Management Service (910-822-7933)

Construction duration: 270 Days

II. Outline of Scope of Work:

The Contractor shall provide all supervision, labor, materials, and equipment necessary to complete Project 565-13-207, Replace Windows Bldg 1 at the Fayetteville Veteran Affairs Medical Center. The project encompasses the replacement of exterior windows throughout Building 1 from the basement level to the attic level, 7 levels total. Renovation work is detailed by the construction plans and specifications.

Performance of work will meet all State, Federal and VA regulations and requirements as indicated in the VA national specifications. The CA requirements do not apply. A security Accreditation Package is not required. Specific duties will include but are not limited to the following:

1. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and perform work as required by the plans and specifications.

2. Visits to the site by Bidders may be made only by appointment with the VISN 6 Centralized Acquisition Services Contracting Specialist or his designated Contracting Officer’s Representative (COR).

3. Wear identification badges while working on station (ID card request form will be provided by the Contracting Officer’s Representative (COR) prior to commencing any work).

4. VA Warehouse will not receive or store any project related equipment of materials.

5. Hours of Operation: All work shall be performed between the hours of 730am-400pm Monday-Friday. Some weekend work and after hour work is required; if needed, some work can be performed at different hours but must be approved by the COR.

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

Point of Contact: Frank A. Fogg Email: frank.fogg@va.gov

SUBMISSION OF BIDS

The bidder shall submit the following in response to this Invitation for Bids:

(a) A completed and signed Standard Form 1442.

(b) A completed copy of the Representations and Certifications (See FAR 52.204-8 Annual Representations and Certifications (MAR 2012)).

(c) A fully executed bid bond.

(d) Documentation of their safety record.

(e) All forms and/or certifications as directed in the solicitation, including the specifications.

SAFETY AND ENVIRONMENTAL RECORD: In order to be eligible for consideration and award, the contractor shall have no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years and have an Experience Modification Rate (EMR) of equal to or less than 1.0.

All Bidders/Offerors shall submit the following information pertaining to their past Safety and Environmental record with their bid. All references to “Bid” or “Bidder” shall be understood to mean “Offer” or “Offeror”.

1. A self-certification on company letterhead that the bidder has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years. Bidders shall submit copies of their OSHA logs (OSHA Form 300A) for the past three years with their bid. If the firm has been in business for less than three years, they shall submit copies of their OSHA logs for the period of time they have been in business.

1. Information regarding their current Experience Modification Rate (EMR) equal to or less than 1.0. This information shall be obtained from the bidder’s/offeror’s insurance company and be furnished on the insurance carrier’s letterhead.

Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state-run worker’s compensation insurance rating bureau.

DESCRIPTION OF WORK: See SCOPE OF WORK and BID ITEM LIST.

MAGNITUDE OF CONSTRUCTION: between $1,000,000.00 - $5,000,000.00 NAICS: The NAICS Code for this procurement is 236220, Commercial and Institutional Construction, with a maximum small business size standard of $36.5 million.

COMPLETION TIME: BID ITEM LIST for completion times for the Base Bid and for each Deduct Alternate bid item.

SDVOSB SET-ASIDE: Effective June 20, 2007, Public Law 109-461, the Veterans Benefits, Health Care, and Information Technology Act of 2006 allow procurements to be set-aside for SDVOSBs and VOSBs. This procurement is 100% set-aside for Service-Disabled, Veteran-Owned Small Business (SDVOSB). Bids are solicited only from SDVOSB concerns and bids received from concerns that are not SDVOSB concerns shall be rejected. In order to be considered, the firm must be shown in the Center for Business Enterprise (VetBiz) website as verified at the time of submission of their bid. No award can be made unless the vendor is registered.

Plans/Drawings/Specifications: Drawings and specifications are attached in electronic format to this solicitation. Offerors are responsible for downloading and printing their own bid sets. The VA will not provide hard copies of the drawings and specifications to any offeror. Contractors are responsible for ensuring that any construction document package used for bidding or construction is complete and up-to-date.

RESIDENT PROJECT ENGINEER: All reference to "Resident Project Engineer" in the solicitation will be changed to "Contracting Officer’s Representative" or “COR.”

GENDER: Wherever masculine gender is used in the solicitation and contract documents, it shall be considered to include both masculine and feminine.

DEPARTMENT OF VETERANS AFFAIRS: All reference to "Veteran's Administration" or "VA" in the solicitation will be changed to Department of Veterans Affairs".

METRIC PRODUCTS: Products manufactured to metric dimensions will be considered on an equal basis with those manufactured using inch-pound units, providing they fall within the tolerances specified using conversion tables and contained in the latest revision of Federal Standard No. 376, and all other requirements of this document are met.

If a product is manufactured to metric dimensions and those dimensions exceed the tolerances specified in inch-pound units, a request should be made to the Contracting Officer, in writing, to determine if the product is acceptable. The Contracting Officer, in concert with the Contracting Officer’s Representative (COR), will accept or reject the product.

CONTRACTOR RESPONSIBILITY: Contractor shall be required to complete all contract work and schedule a final inspection within the specified contract performance period. Should the Contractor fail to complete the contract work (including scheduling of the final inspection), and it is determined by the Government to be a Contractor-caused delay, the Contractor shall be in default status. If the Government determines it to be in the best interest of the Government to allow the Contractor to continue to perform contract work, the Contractor shall provide equitable consideration to the Government for additional time granted for completion of contract work. Such agreement shall not be deemed a waiver of the Government’s right to terminate this contract in the event the Contractor fails to complete the contract work (including scheduling of the final inspection) on or before the completion date.

TRAINING: Effective July 1 2005, all employees of the general contractor and subcontractors shall have the 10-hour OSHA certified construction safety course and/or other relevant competency training, as determined by the COTR with input from the ICRA (Infection Control Risk Assessment) team. The General Contractor’s competent person shall have completed the 30-hour OSHA certified construction safety course. Documentation of training shall be submitted to the Contracting Officer for review and approval prior to any work being performed. No ID badge will be issued to an employee who does not provide this documentation. There shall be no exceptions to this requirement.

TB TESTING: It is the responsibility of the contractor to provide TB training annually and a PPD test annually for any employee(s) providing services at VAMC, Richmond, Virginia. The Government reserves the right to review the contractor’s records.

PRE-BID CONFERENCE: A pre-bid conference (Site Visit) has been scheduled for Monday 04/16/2018 at 10:00 a.m in the Main Medical Center (Bldg. 1), 1st Floor, historical lobby VA Medical Center, Fayetteville NC. This pre-bid conference will be the only opportunity for potential bidders to visit the site.

All potential bidders, subcontractors, and suppliers are strongly encouraged to attend this pre-bid conference.

REQUESTS FOR INFORMATION: Requests for Information (RFIs) shall be submitted by the prime contractor, through Email to the Point of Contact listed above. No telephone RFIs will be accepted. The cutoff for submission of RFIs is Thursday 4/19/2018 12:00 AM, EST. Responses will be provided in a Question & Answer format on or about 04/25/2018. Do not send RFIs via the vendor portal-this is not an acceptable method and will not be responded to by the Contracting Officer.

KEYS: All keys provided the Contractor for use during the project shall be returned to the Contracting Officer's Representative (COR) at completion of the work or upon request. No keys shall be reproduced by the Contractor. There shall be a charge of $10.00 for each key that is lost or not returned to the COR. Payment shall be made to the VA Medical Center, Richmond, Virginia upon receipt of a Bill of Collection.

PREPARATION OF BIDS/OFFERS/PROPOSALS: Neither the VAMC nor the VISN 6 NCO will pay for any costs incurred in preparation and submission of bids or proposals.

PRIVACY AND CONFIDENTIALITY: Contractors to the Department of Veteran Affairs may be unintentionally exposed to sensitive information. Information may be overheard, seen on documents or electronic devices, or observed that could potentially violate the privacy and confidentiality of our veterans, employees, volunteers, and their families. Regulations such as, but not limited to the Health Insurance Portability and Accountability Act of 1996 (HIPAA), Freedom of Information Act (FOIA) and Privacy Act of 1974 have been enacted to protect sensitive information from being improperly disclosed. Information should not be divulged or released to anyone unless specifically authorized by this contract or its’ attached documents in accordance with the contracted services. Failure to comply with applicable statutes and regulation can result in the termination of this contract and civil and criminal penalties, including fines and imprisonment. All suspected or actual breeches of privacy and confidentiality should be reported immediately to the Contracting Officer, Contracting Officer’s Representative (COR) or the Facility Privacy Officer.

The C&A requirements do not apply and a Security Accreditation Package is not required. If the contractor opts to use a computer or computer system for processing contract documents, the requirements of FIPS 140-2 for encryption of contract documents must be met.

VETS 100: Title 38, USC Section 4212(d) and Public Law 105-339, requires that federal contractors report, at least annually, the number and category of veterans who are within their workforce. Submission of the VETS 100 reporting information can be done electronically at: http://vets100.cudenver.edu. Award cannot be made unless the awardee has filed their VETS 100 report; therefore, all bidders/offerors are encouraged to file every year.

SYSTEM FOR AWARD MANAGEMENT (SAM): Federal Acquisition Regulations require that federal contractors register in the System for Award Management (SAM) database at http://www.sam.gov and enter all mandatory information into the system. Award cannot be made until the contractor has registered. Bidders are encouraged to ensure that they are registered in SAM prior to submitting their bid.

PROPOSAL SUBMISSION: All proposals shall be submitted by the prime contractor, through Email to the Point of Contact listed above. HARD COPY PROPOSALS WILL BE ACCEPTED ONLY ON THE CONDITION THAT EMAIL PARAMITERS DO NOT ALLOW COMPLETE SUBMISSION, HOWEVER THIS WILL NOT EXTEND THE PROPOSAL DUE TIME. All proposals are due by 5/1/2018 4:00 PM, EST.

NOTE: To be considered and accepted as timely the proposal must be uploaded in its entirety prior to the deadline. Failure to provide a proposal in its entirety prior to the deadline will render the proposal noncompliant.

BASIS FOR AWARD: See attached Basis of Award

TECHNICAL PROPOSAL: A technical proposal is required.

Basis of Award Project 565-13-207: Replace windows BLDG 1 at the Fayetteville VAMC

A. BASIS FOR AWARD.

Award will be made to the lowest priced, technically acceptable responsible offeror, whose proposal conforms to all stated terms, conditions, representations, certifications, and any other information required by this solicitation. Technical tradeoff will not be made and no additional credit will be given for exceeding the minimum requirements. In the event an offeror’s proposal is determined to be unacceptable in any of these factors, the entire proposal will be considered unacceptable and the offeror will be ineligible for award.

To be considered technically acceptable for award each offeror must provide with their submitted offer:

1. Technical Approach - Technical approach to complete the project in accordance with the sow, drawings, specifications, and general requirements. Offerors shall submit a capability statement demonstrating a clear understanding of the statement of work, including operations and maintenance problems presented therein. The offeror should provide evidence of sufficient planning to show that work will be accomplished as required and on schedule, utilizing all available resources to meet requirements. At a MINIMUM, shall include with proposal the following:

· Provide confirmation capability of meeting the entire Project Scope.

· Registered as Service Disabled Veteran Owned–Small Business Vendor

· https://www.vip.vetbiz.gov/

· Active Sam at the time of submission

· Provide organizational Key Personnel

2. Management/Quality Control Approach - Proposal shall address your Management/Quality Control Approach to complete the project in accordance with the sow, drawings, specifications, and general requirements. Please provide:

· Safety plan

· Quality control plan

· Osha Cert Person Name and Credentials

· Scheduling Methodology

3. Relevant Experience/Past Performance – The Relevant Experience/Past Performance evaluation will assess the relative risks associated with an offeror's likelihood of success in performing the solicitation's requirements as indicated by that offeror's record of Relevant Experience/Past Performance.

· Offerors must provide a reference and a successfully completed contract that demonstrate recent and relevant record of performance in supplying services that meet the requirements described in the RFP. Provide description of projects, dollar value, and Point of Contact(s) including phone/FAX numbers.

4. Price. All CLIN items to include base and alternate deducts in the Price Schedule must include a price to include Offerors cost breakdown in sufficient detail to permit a complete analysis of labor, burden, materials, equipment, transportation, supervision, and disposal. The total evaluated price will consist of the offeror’s proposed price and the government’s independent cost estimate. The Government may determine that an offer is technically acceptable; however, the prices are significantly unbalanced. Price reasonableness will be performed by the Contracting Officer If, during evaluation, it is determined that discussions are necessary, offerors’ Final Proposal Revisions (FPR) after discussions will be considered in making the source selection decision.

B. EVALUATION METHODOLOGY. The award decision will be based on the "Lowest Price, Technically Acceptable" Evaluation Standards Acceptable /Go ALL the minimum acceptable criteria are clearly met and demonstrated by the proposal. The offeror's proposal meets the performance and technical capability requirements defined in the sow, drawings, specifications, and general requirements.

Unacceptable /No-go Not all the minimum acceptable criteria are met by the proposal. An unacceptable proposal contains one or more deficiencies. Proposal fails to meet specified minimum performance and technical capability requirements defined in the SOW, or provide the minimum required documentation with proposal.

NOTE: Once the proposals have been determined to be "technically acceptable," award will based on cost/price only.

The following table will be used for each proposal received to score each LPTA factor as to whether it is Acceptable or Unacceptable.

Non- Cost/Price Factors
Offeror
Technically Acceptable/ Go/ No-Go

Technical Approach

Management/Quality control Approach

Past Performance

SSEB INSTRUCTIONS:

The SSEB establish the requirements of acceptability, and will evaluate proposals in accordance with the factors stated in the RFP and Basis of Award. In evaluating the technical portion of the proposals, the SSEB will evaluate utilizing the above methodology to establish acceptability. The attached template is provided to assist the SSEB in evaluating these factors. Each factor will be scored as Acceptable/Go or Unacceptable/No Go as defined above. Each proposal will be evaluated against the sow, drawings, specifications, and general requirements and the stated evaluation criteria. Each proposal is evaluated using the same standards.

2.1 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.3 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY 2014) ALTERNATE I (MAY 2014) AND ALTERNATE II (JUN 2009)

(a) Definitions. "Bahrainian, Mexican, or Omani construction material," "commercially available off-the-shelf (COTS) item," "construction material," "designated country construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials Under Trade Agreements" (Federal Acquisition Regulation (FAR) clause 52.225-11).

(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute shall submit the request with its offer, including the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction materials, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(4)(i) of FAR clause 52.225-11.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign construction material, except foreign construction material from a designated country other than Bahrain, Mexico, or Oman that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-11, the offeror also may submit an alternate offer based on use of equivalent domestic or designated country construction material other than Bahrainian, Mexican, or Omani construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of FAR clause 52.225-11 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of FAR clause 52.225-11 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic or designated country construction material other than Bahrainian, Mexican, or Omani construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.4 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000.00, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of Provision)

2.5 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Frank A. Fogg NCO 6 Contracting Officer Hand-Carried Address:

Department of Veterans Affairs Contracting Office Network Contracting Office 6 201 Hay St Fayetteville NC 28301 Mailing Address:

Department of Veterans Affairs Contracting Office Network Contracting Office 6 201 Hay st.

Fayetteville NC 28301

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of Provision)

2.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for— April 16, 2018 at 10:00am (local time)

(c) Participants will meet at— Fayetteville VAMC, Bldg 1 2300 Ramsey St., Fayetteville, NC (End of Provision)

GENERAL CONDITIONS

REGISTRATION WITH CONTRACTOR PERFORMANCE ASSESSMENT SYSTEM (CPARS)

a. As prescribed in Federal Acquisition Regulation (FAR) Part 42.1502 and 42.1503, the Department of Veterans Affairs (VA) evaluates contractor past performance on all contracts that exceed $100,000. The FAR requires that the Contractor be provided an opportunity to comment on past performance evaluations prior to each report closing. To fulfill this requirement VA uses an online database, Contractor Performance Assessment System (CPARS), which is maintained by the Naval Sea Logistics Center in Portsmouth, Virginia. CPARS has connectivity with the Past Performance Information Retrieval System (PPIRS) database, which is available to all Federal agencies. PPIRS is the system used to collect and retrieve performance assessment reports used in source selection determinations and completed CPARS report cards transferred to PPIRS. CPARS also includes access to the Federal Awardee Performance and Integrity Information System (FAPIIS). FAPIIS is a web-enabled application accessed via CPARS for contractor responsibility determination information.

b. The Contractor will have an opportunity to review their ratings/comments, under the step “Contractor Comments” in CPARS. You will be notified via email by the CPARS system to review the report and provide comments. Each contractor whose contract award is estimated to exceed $100,000 may register with CPARS database at the following web address: www.cpars.gov in order to review the past performance evaluations. Help in registering can be obtained by contacting Customer Support Desk @ DSN: 684-1690 or COMM: 207- 438-1690. Registration should occur no later than thirty days after contract award, and must be kept current should there be any change to the Contractor's registered representative.

Notification to Contractor

CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM

(a) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of Veterans Affairs has implemented use of the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15
(b) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.

(c) Please furnish the Contracting Officer with the name, position title, phone number, and email address for each person designated to have access to your firm’s past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official. The report information must be protected as source selection sensitive information not releasable to the public.

(d) When your Contractor Representative(s) (Past Performance Points of Contact) are registered in CPARS, they will receive an automatically-generated email with detailed login instructions. Further details, system requirements, and training information for CPARS are available at www.cpars.gov. The CPARS User Manual, registration for online training for Contractor Representatives may be found at this site.

(e) You have 14 calendar days following the Assessing Official signature date to submit comments before the evaluation is made available in the Past Performance Information Retrieval System (PPIRS). You have a total of 60 calendar days following the Assessing Official signature date to submit comments. Any comments that you submit will be posted to PPIRS. If you do not sign and return the evaluation within 60 calendar days the evaluation will be returned to the Assessing Official, you will no longer be able to provide comments and the evaluation will be annotated as follows: 'The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this evaluation.' Partially completed comments that were not signed and returned to the Government within 60 calendar days will be removed from the evaluation.

(f) The following guidelines apply concerning your use of the past performance evaluation:

(1) Protect the evaluation as “source selection information.” After review, transit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the Contracting Officer for instructions.
(2) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
(3) Prohibit the use of or reference to evaluation data for advertising, promotional material, preaward surveys, responsibility determination, production readiness reviews, or other similar purposes.

(g) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the Contracting Officer no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.

(h) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been completed.

(End of Notice)

4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) The Contractor's representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.

(End of Clause)

4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 270 calendar days after receipt of the Notice to Proceed (NTP). The time stated for completion shall include final cleanup of the premises.

(End of Clause)

4.3 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY 2014) ALTERNATE I (MAY 2014)

(a) Definitions. As used in this clause— "Bahrainian, Mexican, or Omani construction material" means a construction material that—

(1) Is wholly the growth, product, or manufacture of Bahrain, Mexico or Oman; or

(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in Bahrain, Mexico, or Oman into a new and different construction material distinct from the materials from which it was transformed.

"Caribbean Basin country construction material" means a construction material that—

(1) Is wholly the growth, product, or manufacture of a Caribbean Basin country; or

(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a Caribbean Basin country into a new and different construction material distinct from the materials from which it was transformed.

"Commercially available off-the-shelf (COTS) item"— (1) Means any item of supply (including construction material) that is—

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Component" means an article, material, or supply incorporated directly into a construction material.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

"Cost of components" means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

"Designated country" means any of the following countries:

(1) A World Trade Organization Government Procurement Agreement country (Armenia, Aruba, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Netherlands, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan, or United Kingdom);

(2) A Free Trade Agreement country (Australia, Bahrain, Canada, Chile, Colombia, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Oman, Panama, Peru, or Singapore);

(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or

(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, Bonaire, British Virgin Islands, Curacao, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Saba, St. Kitts and Nevis, St. Lucia, St. Vincent and the Grenadines, Sint Eustatius, Sint Maarten, or Trinidad and Tobago).

"Designated country construction material" means a construction material that is a WTO GPA country construction material, an FTA country construction material, a least developed country construction material, or a Caribbean Basin country construction material.

"Domestic construction material" means—

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if—

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.