This federal contract opportunity notice synopsizes an upcoming competitive solicitation to replace fire doors campus wide at the Canandaigua VA Medical Center. The solicitation will require contractors to provide all labor, materials, tools, equipment, and supervision necessary to remove and replace fire doors and hardware in seven buildings on the campus. Drawings will be provided as a general reference for door locations. The contractor must field verify all doors and supply fire rated stainless steel hardware compatible with the facility's seven pin Best Core keying system. The project magnitude is between $100,000 and $250,000. A 20% bid bond will be required. The solicitation will be set aside 100% for Service-Disabled Veteran-Owned Small Businesses and posted on the Federal Business Opportunities website around November 5, 2021. The NAICS code is 236220 with a $39.5 million small business size standard.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 21-509 Replace Fire Doors Specifications (Revised 12142021).pdf | ||
| 21-509 Replace Fire Doors Drawing Set (Revised 12142021).pdf | ||
| 36C24222B0009 0001.docx | DOCX document | |
| Specifications.pdf | ||
| S02 Wage Determination-Ontario.docx | DOCX document | |
| Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5.
REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE
DOCUMENTS (
Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL
SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
1. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than ____ ___________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C24222B0009 X 11-18-2021 528-22-1-5192-0003 528A5 21-509 Department of Veterans Affairs Network Contracting Office (NCO) 2 2875 Union Road Suite 3500 Cheektowaga NY 14227 Tanya Baldwin Department of Veterans Affairs Network Contracting Office (NCO) 2 2875 Union Road Cheektowaga NY 14427
BALDWIN, TANYA
N/A Contractor shall provide all labor, equipment, materials, and supervision necessary to perform all work required to Replace Fire Doors Campus Wide in accordance with all drawings, specifications, and the scope of work.
This project is located at VA Western New York Healthcare System, Canandaigua VAMC, 400 Fort Hill Avenue, Canandaigua, N.Y. 14424.
Project magnitude: between $100,000 and $250,000. The NAICS code is 236220. Small Business size standard is $39.5M.
In accordance with P.L. 109-461, this acquisition is 100% set aside for Service-Disabled Veteran Owned Small Business concerns. See VAAR 852.219-10, Notice of Total Service-Disabled Veteran Owned Small Business Set-Aside of this VERIFIED by the Department of Veterans Affairs Center for Verification and Evaluation (CVE) at time of submission of bid and at time of award. Failure to be both VERIFIED by CVE and VISIBLE in VetBiz prior to contract award will result in the bidder's proposal being deemed non-responsive. All offerors are urged to contact the CVE and submit the required documents to obtain CVE verification of their SDVOSB statusif they have not already done so.
In accordance with FAR 52.204-7, System for Award Management (SAM), prospective contractors shall be registered in the SAM database prior to award of a contract or agreement.
Offerors shall submit Experience Modification Rate (EMR) with bid. This EMR shall be equal to or less than 1.0 or the bidder will be ineligible for contract award.
See full solicitation text for information related to pre-bid si te visit, requests for information, bidding materials and public bid opening.
Note: In accordance with FAR 36.209 and VAAR 836.209, an A/E firm canno t be awarded any construction contract for which it provided design services unless approved by the head of the agency.
The site visit is schedule on Nov 29, 2021 at 11:00 A.M at the Can andaigua VAMC.
X X 52.211-10 X 10 days after award 13:00
EST
12-17-2021 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22.
AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c 41 U.S.C. 3304(a) ( 26.
ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No fu rther cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED
STATES OF AMERICA
31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copie s unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
528-3620162-5192-854200 Non-Recurring Ma-3223 Buildings and Facilities 23NRNR001 Department of Veterans Affairs Network Contracting Office (NCO) 2 2875 Union Road Suite 3500 Cheektowaga NY 14227 Tungsten Network https://www.tungsten-network.com/ customer-campaigns/veteransaffairs/
Tanya Baldwin Contracting Officer
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS | 7 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 10 |
| A.3 GWAC ORDER INTRODUCTORY LANGUAGE | 12 |
| A.4 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 12 |
| A.5 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 13 |
| A.6 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 15 |
| A.7 52.228-1 BID GUARANTEE (SEP 1996) | 16 |
| A.8 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021) | 17 |
| A.9 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 17 |
| A.10 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 17 |
| A.11 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 18 |
| REPRESENTATIONS AND CERTIFICATIONS | 19 |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020) (JUL 2020) (DEVIATION) | 19 |
| 3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (OCT 2020) | 22 |
| GENERAL CONDITIONS | 26 |
| 4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 26 |
| 4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (JUL 2018) | 26 |
| 4.3 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) | 27 |
| 4.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (SEP 2021) | 27 |
| 4.5 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020) | 31 |
| 4.6 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (FEB 2021) | 31 |
| 4.7 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 35 |
| 4.8 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020) | 36 |
| 4.9 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION) | 38 |
| 4.10 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018) | 40 |
| 4.11 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 40 |
| 4.12 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 42 |
| 4.13 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 43 |
| 4.14 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) | 43 |
| 4.15 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020) | 43 |
| 4.16 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 45 |
| 4.17 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008) | 46 |
SCOPE OF WORK
Project No. 528A5-21-509 Replace Fire Doors Campus Wide Canandaigua, VA Medical Center, 400 Fort Hill Avenue Canandaigua, NY 14424
The general scope of this project is to replace existing fire/smoke doors throughout the campus, as described within the contract documents, at the Canandaigua VAMC.
1.0 EXISTING CONDITIONS
The Canandaigua VAMC is a campus facility with more than 30 buildings located on over 120 acres. Many of the buildings on campus are considered historic, and where necessary the renovations will comply with the requirements of the NYS SHPO.
2.0 SCOPE OF WORK
The contractor is responsible for removing and replacing all fire doors and hardware in buildings 4, 5, 6, 7, 8, 36, and 37. The hardware is just for the coring system. The drawings included in this contract are to be utilized as a general reference for the doors called out for replacement. The contractor is responsible for field verification of all fire doors. The door hardware must support the 7 pin Best Core keying system, and fire rated stainless steel.
2.1 GENERAL
A. The contractor shall be responsible for all labor, supervision, and materials required to perform the work as indicated in the scope of work, specifications, and drawings. Where incidental work is required to accomplish work shown in the drawings, this work is implied and shall be included as part of the base bid.
B. It is anticipated that all the work will be performed during normal business hours, off tour work may be required at the discretion of the COR.
C. The contractor is responsible for all field measurements; the Government will not be held responsible for bidding errors made or the failure to adequately inspect the job site for existing conditions, dimensions and grades or existing utilities. The contractor is responsible for verifying all utilities through any resource necessary. All bidders are strongly encouraged to inspect the job site prior to submitting bids.
D. Any existing feature disturbed (removed, damaged, etc.) by the contractor during the performance of this contract shall be restored to similar or better condition by the contractor at the contractors’ expense. This includes walls, doorways, doors, trim work, and other miscellaneous items located in the building, sidewalks, grassed areas, and parking lots.
E. During the entire duration of work performed, the contractor shall always, maintain at least one lane for emergency traffic. This includes any placement of project equipment and anywhere work is being performed.
F. The VAMC Project COR shall govern all work done during project duration. Disputes shall be promptly referred to the Contracting Officer, (CO). The contractor will immediately correct any work which the Project COR deems unacceptable or work that is not in accordance with plans and/or specifications.
G. The contractor will not be allowed to stage material outside of the designated renovation area. All material will be stored in an approved location by the COR. All storage areas and refuse (roll offs) shall be fenced in with a minimum of 6’ high, chain link fence. The storage area shall be kept neat in appearance and shall be fully restored to existing conditions when complete.
H. The contractor shall receive all deliveries of materials, equipment, tools, or other goods off station, and bring them to the job site. The Canandaigua VA shall not accept deliveries for project purposes.
I. The contractor will always comply with the attached ICRA standards.
J. The contractor shall always provide a secure construction site. In any area that is closed due to construction, including any time the corridor is partially closed, a passage door with a handle that locks and is cored to a Best system X-6 must be installed and secured. These areas shall also include contractor storage areas with man door access. Construction supply trailers will always be padlocked and secured. Padlocks and hasps will not be allowed as a means of security. Also, the access door shall always be locked, even during construction.
K. The contractor is responsible for providing the VA with a schedule that illustrates durations of work at each building. If the contractor requires to deviate from this schedule, they are to notify the COR for approval. Prior to work commencing in an area, the contractor shall notify the COR of his intention to work in the area and shall schedule a walkthrough with the COR to determine and document existing conditions. If requested by the COR, the contractor shall take pre-renovation survey photographs and provide to the VA COR in PDF format.
L. The contractor will always allow for facility occupant egress from the facility. If a doorway must be shut down during work, the contractor will coordinate with the COR prior to closure.
M. Any non-lead time materials will only be paid for when installed.
N. Any items identified as punch list items will be fixed prior to project closeout.
O. Work cleanliness must be adhered to throughout the project.
P. The contractor shall warranty all work including labor and materials for 1 year from the date of acceptance.
2.2 Demolition
A. Contractor is responsible for all costs associated with the demolition of this project, including removal of excess metals, and other miscellaneous items that may be encountered. All metal materials are to be returned to the VA after demolition.
3.0 Period of Performance
A. The period of performance for this contract shall be 180 days from NTP.
B. The contractor shall always be in coordination with other projects on going in the area and this coordination shall not affect the contract duration of this project.
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
(a) Bidding materials consisting of Invitation for Bids, drawings, specifications and contract forms will be available on http://www.Beta.Sam.gov in electronic format only. All interested parties (subs & primes) should register at http://www.Beta.Sam.gov as an “Interested Vendor” so that others will know of your interest in participating in this procurement. A Bidder’s mailing list WILL NOT BE prepared by the Contract Specialist. SOLICITATION AMENDMENTS: Amendments to the solicitation will be posted at http://www.Beta.Sam.gov. Paper copies of the amendments will NOT be individually mailed. By registering to “Receive Notification”, you will be notified by e-mail of any new amendments that have been issued and posted. No other notification of amendments will be provided. Offerors are reminded that they are responsible for obtaining and acknowledging all amendments to this solicitation prior to the time for receipt of offers.
(b) If bid exceeds $150,000 a bid bond must be submitted. A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.
(c) If the contract will exceed $150,000 (see FAR 28.102-1 for lesser amount), the bidder to whom award is made will be required to furnish two bonds, a Payment Bond, SF 25A, and a Performance Bond, SF 25, each in the penal sum as noted in the General Conditions of the Specification. Copies of SFs 25 and 25A may be obtained upon application to the issuing office.
(d) If the bid/offer is between $30,000 - $150,000 The bidder/offeror to whom award is made will be required to furnish a Payment Bond, Standard Form 25A or alternative payment protection which conforms to the requirements set forth in FAR Clause 52.228-13, Alternative Payment Protections, as noted in the General Conditions of this Specification. Copies of the Standard Form of Payment Bond may be obtained upon application to the Issuing Office.
PROJECT BID ITEMS
A single award will be made on the Base Bid.
BASE BID: All work required in the construction documents (including but not limited to drawings, specifications, addenda, and contract documents).
Fill in price SF 1442 BOX 17, BASE BID (use ink) The construction magnitude is between $100,000 and $250,000
BID SUBMISSION
The following documents are to be included in the bid submission:
(a) One (1) signed SF 1442 page 2, Offer page, with blocks 14-20c completed.
(b) Acknowledgment of all amendments must be accomplished either via entering data in block nineteen (19) of the SF1442 or completing blocks fifteen (15) a, b, and c of the amendment and attaching it to the SF 1442 Offer page.
(c) One (1) original completed/signed SF24 Bid Bond and Power of Attorney as required.
(d) Safety or Environmental Violations and Experience Modification Rate:
1) All Bidders/Offerors shall submit the following information pertaining to their past Safety and Environmental record. The information shall contain, at a minimum, a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.
2) All Bidders/Offerors shall submit information regarding their current Experience Modification Rate (EMR) equal to or less than 1.0. This information will be obtained from the bidder’s/offeror’s insurance company and be furnished on the insurance carrier’s letterhead.
3) Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead may obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR will obtain their EMR rating from their state run worker’s compensation insurance rating bureau.
(e) Bidders are responsible for ensuring and verifying their bid and all required bid documents are received at the address designated in block eight (8) of the SF 1442 solicitation and by the date and time specified in block thirteen (13)a of the SF 1442 solicitation (subject to amendment).
DELIVERY OF BIDS
Due to COVID-19 concerns and direction from the NYS Governor for social distancing, there will not be a face-to-face public bid opening. In accordance with FAR 14.202-8, send all submission documents via email to Tanya.Baldwin@va.gov no later than (NLT) 1:00 PM (Eastern), Friday, December 17, 2021. Bids received after this time may be rejected.
All Contractors providing an electronic bid submission must still meet all requirements listed under “Bid Submission” in the solicitation. The bid opening and public reading of the bids will be via OfficeTeams/Conference call. Bidders may call 1 347-566-4838 at 1:15PM EST and enter phone conference ID 293 226 349# to join.
**The bid submission emails will be kept in an electronic folder unread until 1:15 PM when they will be opened and read to the public**
**NOTE: PLEASE ALLOW AT LEAST 30 MINUTES FOR BIDS TO ARRIVE IN EMAIL**
After all bids have been read, the apparent low bidder shall submit the signed original copy of the bid and all required documents, including bonds via mail to:
Tanya Baldwin, Department of Veterans Affairs, Network Contracting Office NCO2, 2875 Union Road, Suite 3500, Cheektowaga, NY 14227.
Files should be in Adobe* PDF (Portable Document Format) Files: Size: Maximum size of the e-mail message shall not exceed five (5) megabytes. If the size limits are exceeded, the VA may not receive the file and/or you may not be considered. Only one email is permitted. This email should contain at least three separate attachments:
· One (1) signed SF1442 with amendments acknowledged.
· Include response to FAR 52.204-8(2) (i) or (ii) Annual Representations and Certifications
· Response to FAR 52.209-13(b)(1) or (2) Violation of Arms Controls Treaties or Agreements
· One (1) complete signed SF 24 Bid Bond and Power of Attorney.
· One (1) safety or environmental violations and experience modification rate.
Any exception to the terms and conditions of this Invitation for Bid (IFB) will result in a nonresponsive bid.
Failure to provide a definitive price will result in a nonresponsive bid.
Receipt of bids must be in accordance with terms and conditions of this IFB.
Bidders must acknowledge (in writing only) amendments to this solicitation, otherwise a bid may be determined nonresponsive.
The winning bidder must be determined as "responsible" by the Contracting Officer in accordance with FAR Part 9, Contractor Qualifications.
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
Contractor will provide services to include all tools, labor, materials, equipment, services, and supervision necessary for the “Replace Fire Doors Campus Wide” at 400 Fort Hill Avenue, Canandaigua, N.Y. 14424, for Project 528A5-21-509.
SITE VISIT
Bidders are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of performing these services. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
There will only be one (1) organized site visit. It will be held on Monday, November 29, 2021 @ 11:00 AM (Eastern). Participants will meet at the Canandaigua VAMC, Building 118, Engineering Conference Room Attendance is not mandatory; however, all bidders are strongly encouraged to attend.
REQUESTS FOR INFORMATION (RFI):
To obtain clarifications and/or additional information concerning the contract requirements or specifications, submit a written RFI via email to Tanya.Baldwin@va.gov.
RFIs will be responded to as necessary in amendment format which will be posted on https://beta.sam.gov/.
The deadline for submission of RFIs for this solicitation is Friday, December 3, 2021 at 3:30 PM (Eastern). No questions will be answered after this date/time unless determined to be in the best interest of the Government as determined by the Contracting Officer. Telephone RFIs will not be accepted or returned.
BASIS FOR AWARD
Contract award will be made to the responsive, responsible bidder submitting the lowest price in accordance with FAR Part 14 – Sealed Bidding.
RESPONSIBILITY REQUIREMENTS
A Determination of Responsibility shall be accomplished for the apparent awardee prior to processing the award. The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases will be used to make the Determination of Responsibility. Failure to affirm being within the guidelines above or submit this information may result in a determination of “Non-Responsibility” for the bidder/offeror. NOTE: Any information received by the Government that would cause for a negative Determination of Responsibility may make the bidder/offeror ineligible for award.
This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.
VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors
1. Contractor employees who work in or travel to VHA locations must comply with the following:
1. Documentation requirements:
0. If fully vaccinated, shall show proof of vaccination.
0. NOTE: Acceptable proof of vaccination includes a signed record of immunization from a health care provider or pharmacy, a copy of the COVID-19 Vaccination Record Card (CDC Form MLS-319813_r, published on September 3, 2020), or a copy of medical records documenting the vaccination.
0. If unvaccinated and granted a medical or religious exception, shall show negative COVID-19 test results dated within three calendar days prior to desired entry date. Test must be approved by the Food and Drug Administration (FDA) for emergency use or full approval. This includes tests available by a doctor’s order or an FDA approved over-the-counter test.
0. Documentation cited in this section shall be digitally or physically maintained on each contractor employee while in a VA facility and is subject to inspection prior to entry to VA facilities and after entry for spot inspections by Contracting Officer Representatives (CORs) or other hospital personnel.
0. Documentation will not be collected by the VA; contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.
1. Contractor employees are subject to daily screening for COVID-19 and may be denied entry to VA facilities if they fail to pass screening protocols. As part of the screening process contractors may be asked screening questions found on the COVID-19 Screening Tool. Check regularly for updates.
1. Contractor employees who work away from VA locations, but who will have direct contact with VA patients shall self-screen utilizing the COVID-19 Screening Tool, in advance, each day that they will have direct patient contact and in accordance with their person or persons who coordinate COVID-19 workplace safety efforts at covered contractor workplaces. Contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.
1. Contractor must immediately notify their COR or Contracting Officer if contract performance is jeopardized due to contractor employees being denied entry into VA Facilities.
| FAR Number |
| Title |
| Date |
| 52.203-3 |
| GRATUITIES |
| APR 1984 |
| 52.203-5 |
| COVENANT AGAINST CONTINGENT FEES |
| MAY 2014 |
| 52.203-8 |
| CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY |
| MAY 2014 |
| 52.203-14 |
| DISPLAY OF HOTLINE POSTER(S) |
| JUN 2020 |
| 52.203-16 |
| PREVENTING PERSONAL CONFLICTS OF INTEREST |
| JUN 2020 |
A.3 GWAC ORDER INTRODUCTORY LANGUAGE
The terms and conditions of the contractor's GWAC contract (including any contract modifications) apply to all task or delivery orders issued under the contract. When a lower price has been established, or when the delivery terms, FOB terms, or ordering requirements have been modified by the task/delivery order, those modified terms will apply to all purchases made pursuant to it and take precedence over the GWAC contract. Any unique terms and conditions of an order issued under the contract that are not a part of the applicable GWAC contract will govern. In the event of an inconsistency between the terms and conditions of a task/delivery order and the Contractor's GWAC terms, other than those identified above, the terms of the GWAC contract will take precedence.
| FAR Number |
| Title |
| Date |
| 52.203-17 |
| CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS |
| JUN 2020 |
| 52.204-1 |
| APPROVAL OF CONTRACT |
| DEC 1989 |
| 52.211-13 |
| TIME EXTENSIONS |
| SEP 2000 |
A.4 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision) A.5 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
| Goals for minority participation for each trade |
| Goals for female participation for each trade |
| % |
| 6.9 % |
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is
(End of Provision) [52.223-99 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors.
ENSURING ADEQUATE COVID-19 SAFETY PROTOCOLS FOR FEDERAL
CONTRACTORS (OCT 2021) (DEVIATION)
(a) Definition. As used in this clause - United States or its outlying areas means—
(1) The fifty States;
(2) The District of Columbia;
(3) The commonwealths of Puerto Rico and the Northern Mariana Islands;
(4) The territories of American Samoa, Guam, and the United States Virgin Islands; and
(5) The minor outlying islands of Baker Island, Howland Island, Jarvis Island, Johnston Atoll, Kingman Reef, Midway Islands, Navassa Island, Palmyra Atoll, and Wake Atoll.
(b) Authority. This clause implements Executive Order 14042, Ensuring Adequate COVID Safety Protocols for Federal Contractors, dated September 9, 2021 (published in the Federal Register on September 14, 2021, 86 FR 50985).
(c) Compliance. The Contractor shall comply with all guidance, including guidance conveyed through Frequently Asked Questions, as amended during the performance of this contract, for contractor workplace locations published by the Safer Federal Workforce Task Force (Task Force Guidance) at https:/www.saferfederalworkforce.gov/contractors/.
(d) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (d), in subcontracts at any tier that exceed the simplified acquisition threshold, as defined in Federal Acquisition Regulation 2.101 on the date of subcontract award, and are for services, including construction, performed in whole or in part within the United States or its outlying areas.
(End of clause)] A.6 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
A.7 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be percent of the bid price or , whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
A.8 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)
(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—
(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and
(2) Standard Form 28, Affidavit of Individual Surety.
(b) The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228–1, Bid Guarantee, or as otherwise established by the Contracting Officer.
(c) The Contracting Officer may release the security interest on the individual surety’s assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.
(End of Provision)
A.9 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for— Monday, November 29, 2021 at 11:00 AM EST
(c) Participants will meet at— Building 118, Engineering Conference Room (End of Provision)
A.10 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/
(End of Provision)
| FAR Number |
| Title |
| Date |
| 52.204-7 |
| SYSTEM FOR AWARD MANAGEMENT |
| OCT 2018 |
| 52.204-16 |
| COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING |
| AUG 2020 |
| 52.204-22 |
| ALTERNATIVE LINE ITEM PROPOSAL |
| JAN 2017 |
| 52.214-3 |
| AMENDMENTS TO INVITATIONS FOR BIDS |
| DEC 2016 |
| 52.214-4 |
| FALSE STATEMENTS IN BIDS |
| APR 1984 |
| 52.214-5 |
| SUBMISSION OF BIDS |
| DEC 2016 |
| 52.214-6 |
| EXPLANATION TO PROSPECTIVE BIDDERS |
| APR 1984 |
| 52.214-7 |
| LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS |
| NOV 1999 |
| 52.214-18 |
| PREPARATION OF BIDS—CONSTRUCTION |
| APR 1984 |
| 52.214-19 |
| CONTRACT AWARD—SEALED BIDDING—CONSTRUCTION |
| AUG 1996 |
| 52.214-34 |
| SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE |
| APR 1991 |
| 52.214-35 |
| SUBMISSION OF OFFERS IN U.S. CURRENCY |
| APR 1991 |
| 52.223-6 |
| DRUG-FREE WORKPLACE |
| MAY 2001 |
A.11 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) Prime contractors are encouraged to assist service-disabled veteran-owned and veteran-owned small business potential subcontractors in obtaining bonding, when required. Mentor firms are encouraged to assist protégé firms under VA's Mentor-Protégé Program in obtaining acceptable bid, payment, and performance bonds, when required, as a prime contractor under a solicitation or contract and in obtaining any required bonds under subcontracts.
(End of Clause)
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020) (JUL 2020) (DEVIATION) (a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.
(2) The small business size standard is $39.5 Million.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204–7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
[ ] (i) Paragraph (d) applies.
[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.204-26, Covered Telecommunications Equipment or Services—Representation. This provision applies to all solicitations.
(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.
(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.
(x) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(C) The provision with its Alternate II applies to solicitations that will result in a multiple-award contract with more than one NAICS code assigned.
(xiii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.
(xiv) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.
(xvi) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.
(xvii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.
(xviii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.
(xix) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.)
(xx) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.
(xxi) 52.225-4, Buy American—Free Trade Agreements—Israeli Trade Act Certificate. (Basic, Alternates II and III.) This provision applies to solicitations containing the clause at 52.225-3.
(A) If the acquisition value is less than $50,000, the basic provision applies.
(B) If the acquisition value is $50,000 or more but is less than $83,099, the provision with its Alternate II applies.
(C) If the acquisition value is $83,099 or more but is less than $100,000, the provision with its Alternate III applies.
(xxii) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.
(xxiii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan—Certification. This provision applies to all solicitations.
(xxiv) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certifications. This provision applies to all solicitations.
(xxv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.
(A) Solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions; and
(B) For DoD, NASA, and Coast Guard acquisitions, solicitations that contain the clause at 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns.
(2) The following representations or certifications are applicable as indicated by the Contracting Officer:
[X](i) 52.204-17, Ownership or Control of Offeror.
[X](ii) 52.204-20, Predecessor of Offeror.
[](iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.
[](iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment—Certification.
[](v) 52.222-52, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services—Certification.
[](vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA-Designated Products…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .