36C10A-19-R-0008-017.pdf
PDF 225 KB Posted
- Attached to
- Enterprise Satellite Communications Operations Federal contract opportunity
- Solicitation number
- 36C10A19R0008
About this file
36C10A-19-R-0008 S06 36C10A-19-R-0008 0001.pdf
View the file
Other files for this federal contract opportunity
Show all 45
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
TAC-Austin
1 8
Department of Veterans Affairs
Technology Acquisition Center - Austin
1701 Directors Blvd, Suite 600
Austin TX 78744
Y
Department of Veterans Affairs
Technology Acquisition Center - Austin
1701 Directors Blvd, Suite 600
Austin TX 78744
To all Offerors/Bidders
36C10A-19-R-0008
X
X X
The purpose of this amendment is to make changes to the solicitation documents and respond to the attached questions.
Revise and replace RFP 36C10A19R0008 with the attached Conformed RFP 36C10A19R0008, which incorporates changes through this amendment. Revise and replace the PWS with the attached conformed PWS, which incorporates changes per this amendment. (See revised attachment A).
The closing date for acceptance is not extended.
A Summary of Changes is provided on the next page.
LINO VERA
SUMMARY OF CHANGES
Solicitation 36C10A19R0008
B.4 Table of Deliverables is amended to reflect the correct the PWS references for the deliverable in tasks 5.2.3. Table is amended read as follows:
Task Deliverable ID Deliverable Description
5.1.1 A
Contractor Project Management Plan Due Thirty (30) days after contract (DAC) and updated monthly thereafter.
Electronic submission to: VA PM, COR, CO.
Inspection: destination Acceptance: destination
5.1.2 A Monthly Progress Report
Due the fifth day of each month throughout the period of performance (PoP).
Electronic submission to: VA PM, COR, CO
5.1.3 A Quality Control Plan
Due 14 days after contract award Electronic submission to: VA PM, COR, CO
5.1.4 A Kick-Off Meeting Minutes
Due 2 days after Kick-Off Meeting Electronic submission to: VA PM, COR, CO
5.1.6.1 A Phase-In Transition Plan
Due 14 days after exercising task.
Electronic submission to: VA PM, COR, CO
5.1.6.2 A Phase-Out Plan (Optional Task)
Due 10 business days after optional task is exercised.
Electronic submission to: VA PM, COR, CO
5.2 A Proof of Encryption Configuration and Certification
Certificate 10 business days after contract award. Configuration due upon first VSAT terminal installed.
Electronic submission to: VA PM, COR, CO
5.2.1 A Proof of satellite coverage statement
Due 10 business days after contract award Electronic submission to: VA PM, COR, CO
5.2.2 A Maintenance Plan
Due 14 days after contract award Electronic submission to: VA PM, COR, CO
5.2.2 B Installation Plan
Due 14 days contract award Electronic submission to: VA PM, COR, CO
5.2.3 A VSAT Operational Test Plan
Due 30 days contract award Electronic submission to: VA PM, COR, CO
5.2.3 B 229 VSAT Terminals
Due incrementally, total 229 no later than 160 calendar days after December 1, 2019.
Electronic submission to: VA PM, COR, CO updated 5.2.3
C VSAT Equipment Acceptance Checklist Due 5 days after delivery and training Electronic submission to: VA PM, COR, CO
5.2.3.3 A 40 ea. Ruggedized Storage Containers
Due 90 days after contract award Electronic submission to: VA PM, COR, CO
5.4.1 A Monthly Help Desk Report
Due 5 days after new month.
Electronic submission to: VA PM, COR, CO
5.4.1 B Quarterly Enterprise SatCom Inventory Reports
Due 95 days after contract award.
Electronic submission to: VA PM, COR, CO
5.4.2 A Quarterly Hub Failover Test Report
Due 5 days after quarterly failover test.
Electronic submission to: VA PM, COR, CO
5.4.2 B Quarterly Change Report
Due every 95 days Electronic submission to: VA PM, COR, CO
5.4.2 C Enterprise SatCom Network Operations Document
Due 90 days after contract award.
Electronic submission to: VA PM, COR, CO
5.4.2 D Enterprise SatCom Implementation Diagram Document
Electronic submission to: VA PM, COR, CO
5.4.2 E Enterprise SatCom Network Security Overview Document
Electronic submission to: VA PM, COR, CO
5.4.3 A Monthly Enterprise SatCom Utilization and Operations Reports Due 5 days after next month starts.
Electronic submission to: VA PM, COR, CO
5.4.3 B List of Passwords for VSAT Units
Due When unit is deployed and 120 days thereafter if there are any changes.
Electronic submission to: VA PM, COR, CO
5.4.3 C List of Phone Numbers
Due when systems are deployed and updated every 30 days if there are changes.
Electronic submission to: VA PM, COR, CO
5.4.5.1 A National Drill Enterprise SatCom After-Action Report Due 14 days after National Drill Electronic submission to: VA PM, COR, CO
5.4.5.2 A Field Operations After-Action Report
Due 14 days after Field Operations Electronic submission to: VA PM, COR, CO
5.5 A Quarterly Operations and Maintenance Report
Due 95 days after contract award Electronic submission to: VA PM, COR, CO
5.5 B Annual End-of-Life/End-of-Support Report
Due 11 months after contract award Electronic submission to: VA PM, COR, CO
5.5 C Annual Life Cycle Refresh Plan
Due 11 months after contract award Electronic submission to: VA PM, COR, CO
5.6
A ATO Documentation
Drafts due 90 days after contract award Electronic submission to: VA PM, COR, CO
5.7.1 A VSAT Type Specific Training Manuals
VSATS Training Manual to be delivered 90 days after award and requires VSAT PM approval. Manuals delivered with each unit upon delivery.
Electronic submission to: VA PM, COR, CO
5.7.1 B Training Schedule
Due 90 days contract award.
Electronic submission to: VA PM, COR, CO
5.7.1 C Signed Complete Inventory at time of training
Due 14 days after training.
Electronic submission to: VA PM, COR, CO
5.7.1 D Individual Training Completion Certificates
Due 10 days after training.
Electronic submission to: VA PM, COR, CO
5.7.2 A Annual Refresher VSAT Unit Specific Training Manuals
Due upon training if equipment changes occurred.
Electronic submission to: VA PM, COR, CO
5.7.2 B VSAT Refresher Training Schedule
Due 120 days after contract award.
Electronic submission to: VA PM, COR, CO
5.7.2 C Signed Complete Inventory at time of training
Due 14 days after refresher training Electronic submission to: VA PM, COR, CO
5.7.2 D Annual Individual Training Completion Certificates
Due 10 days after training.
Electronic submission to: VA PM, COR, CO
5.8.1 A Increase Terrestrial Link to 50MB (Optional Task)
Due 48 hours after exercising optional task.
Electronic submission to: VA PM, COR, CO
5.8.2 A Increase Terrestrial Link to 100MB (Optional Task)
Due 48 hours after exercising optional task.
Electronic submission to: VA PM, COR, CO
5.8.3 A Up to Ten (10) Additional VMU Satellite Terminals (Optional Task) Due upon delivery Electronic submission to: VA PM, COR, CO
5.8.3 B Up to Ten (10) ea. VMU VSAT Terminal Equipment Acceptance Checklist (Optional Task) Due upon delivery Electronic submission to: VA PM, COR, CO
5.8.4 A Additional First-Responder Satellite Terminals (Optional Task)
Electronic submission to: VA PM, COR, CO
5.8.4 B Additional FRU Equipment Acceptance Checklist (Optional Task)
Electronic submission to: VA PM, COR, CO
5.8.5 A 6MHz additional VSAT bandwidth (Optional Task)
Due upon request Electronic submission to: VA PM, COR, CO
5.8.6 A 8MHz additional VSAT bandwidth (Optional Task)
Due upon request Electronic submission to: VA PM, COR, CO
5.8.57 A 12MHz additional VSAT bandwidth (Optional Task)
Due upon request Electronic submission to: VA PM, COR, CO
6.2.2 A Contractor Staff Roster
Due 3 days after contract award and updated throughout the PoP.
Electronic submission to: VA PM, COR, CO.
Section D 1. Performance Work Statement is changed to reflect the revised PWS updated on August 9, 2019.
Specifically, paragraph 5.2.3 has been amended to reflect the correct number of terminals, and to clarify that the three deliverables identified are applicable to ALL types of VSATs.
Section E.1 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL ITEMS (OCT
2018), 2. PROPOSAL FILES
Paragraph b is amended to limit the size of the proposals received via email.
Paragraph b now reads as follows:
File Packaging. All of the proposal files may be compressed (zipped) into one file entitled “proposal.zip” using WinZip version 6.2 or later version or the proposal files may be submitted individually. It is recommended that no email exceed 5MB. Due to this size limitation, offerors may submit proposals via separate emails. However, the total number of emails submitted for each offeror shall not exceed five.
Paragraph c., the table is amended to increase the size limitation of Volume I Technical.
Table now reads as follows:
Volume Number Factor File Name Page Limitations*
Volume I Technical Volume1Tech.pdf 30 pages
Volume II Past Performance Volume2PastPerf.pdf None
Volume III Price/Cost** Volume3Price.xls None
Volume IV Solicitation, Offer & Award Documents, Certifications & Representations
Volume4OfrRep.pdf None
File details come from the government source that posted it.