19RF10016RFP.pdf
PDF 896 KB Posted
- Attached to
- NMAI-NY, Modernize Electronic Security Federal contract opportunity
- Solicitation number
- 33330219RF0010016
About this file
Solicitation #33330219RF0010016
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 33330219RF0010016,Amendment_Two.pdf | ||
| 33330219RF0010016,Amendment_One.pdf | ||
| RFP_19RF10016-Drawings.pdf | ||
| RFP_19RF10016-Specifications_.pdf | ||
| Company_Experience_Form.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
SMITHSONIAN INSTITUTION
P.O. BOX 37012
MRC 1200
Washington DC 20013-7012
OCON
Smithsonian Institution
Ofc. of Contracting & Personal Property Mgmt.
P.O. Box 37012, CCB 350, MRC 1200 Washington, DC 20013-7012
Jasmine Price 202-633-7284
1x 04/25/2019
33330219RF0010016
PAGES
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
This Procurement is for the Smithsonian Institution National Museum of the American
Indian's (NMAI) George Gustav Heye Center (GGHC) - Modernize Electronic Security, located in the Alexander Hamilton U.S. Custom House, 1 Bowling Green, New York, NY.
It is the intent of the Smithsonian Institution to award a firm fixed price contract to the Offeror whose price and technical proposal is most advantageous. The
Contractor receiving award shall provide all supervision, labor, material and equipment necessary to perform construction services to complete the work as described in the Drawing and Specifications for SF Project No. 1295606 dated
December 2, 2016.
This brief description shall not be construed as a limitation on the Contractor's obligation to comply with the contract requirements.
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 450 calendar days and complete it within ________________ ________________ calendar days after receiving
05/30/2019
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE
Thomas Dempsey
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
OF 73
Smithsonian Institution
Modernize Electronic Security, GGHC/NMAI, NY
A - Solicitation/Contract Form
See page 1 and 2 of SF 1442
INTRODUCTION:
The Smithsonian Institution National Museum of the American Indian (NMAI) is the only national museum dedicated to the Native peoples of North, South and Central America.
The George Gustav Heye Center (GGHC), located since 1994 in the landmark Alexander Hamilton U.S. Custom House (AHUSCH) in Lower Manhattan, is NMAI’s New York presence.
Today, it is generally considered to be the most comprehensive Native American collection ever assembled. The museum’s broad range of exhibitions and programs, both here and at the NMAI on the Mall in Washington, D.C., have built on this legacy, creating a Native place to explore the past, present and future of Native cultures.
The Alexander Hamilton US Custom House (AHUSCH) appears on the Nation Register of Historic Places and is also a designated New York State and City Landmark structure. All areas of the structure are considered to be historic fabric. All work associated with this project must be conducted in accordance with the Secretary of the Interior Standard for Historic Preservation and Rehabilitation. The Alexander Hamilton US Custom House is owned and operated by the General Services Administration: an independent agency of the United States government, established in 1949 to help manage and support the basic functioning of federal agencies. Additionally, the building houses numerous Federal Agencies, including the United States Bankruptcy Court. The Smithsonian Institution is a tenant in perpetuity within the AHUSCH
The Smithsonian Institution Office of Protection Services has a mission within the Smithsonian Institution to provide and ensure a safe and secure environment for all visitors, staff, and collections. OPS does this in the form of both physical and law enforcement and is recognized in the cultural and natural heritage protection field as a leader in risk management.
It is the intent of this project to upgrade and improve system architecture and hardware of the existing electronic security systems serving GGHC, NMAI-NY. This includes the removal and replacement of all existing electronic security components with new;
including required backbone support; programing and testing, Additionally, the project includes the upgrade of electronic security associated with historic and non-historic doors as well as all conduit, wiring, site work, infrastructure, restoration of finishes (both historic and non-historic) associated with a fully integrated and functioning electronic security system (ESS).
The Museum as well as the entire AHUSCH will remain fully occupied and operational for the duration of the work. This includes Smithsonian Institution exhibition, curatorial, public and staff areas as well as that of other Federal Agencies. The successful Offer is expected to coordinate all work of the Project so as reduce impact on occupants and daily building operations as well as maintaining a 100% functional ESS system.
TOUR OF THE SITE:
Offerors may attend a pre-solicitation meeting to be conducted at the site. Offerors are encouraged to inspect the site prior to submitting a proposal, as information concerning the site may be useful in preparing offers. Failure to visit the site will not constitute a basis for a claim for change in or differing the site conditions, when visiting the site would have provided the Offeror an opportunity to compare the physical site against the drawings and specifications. Offerors who are interested in a tour of the site after the pre-solicitation meeting may contact the Resident Engineer.
B - Supplies or Services/Prices
The Contractor shall provide all supervision, labor, materials, and coordination for the
George Gustav Heye Center National Museum of the American Indian Modernize
Electronic Security, located at the Alexander Hamilton US Customs House, New York, NY.
C - Description/Specification
C.1. The Smithsonian Institution is seeking offers to Modernize Electronic Security at
National Museum of the American Indian located at 1 Bowling Green, New York, NY , as described herein and in the Construction Documents (drawings and specifications) for
SF Project No. 1295606 dated December 2, 2016. All of the requirements that the successful Offeror must meet concerning this project are set forth in detail in the
Solicitation Documents included with the Request for Proposal. Upon the receipt of
Technical and Cost proposals and the selection of a successful Offeror, the Smithsonian
Institution will execute a Fixed Price Construction Contract.
C.2 This request for Proposal (RFP) is intended to provide all Offerors with sufficient information to enable them to prepare and submit offers for technical and cost review and consideration by the Smithsonian Institution. Offerors may, at their own expense, obtain drawings and specifications, the cost of which is nonrefundable..
C.3. It shall be the responsibility of the contractor to immediately notify the Smithsonian Institution, if the target dates and proposed packages of work described herein adversely affect the Contractor’s Critical Path Schedule for the final completion date of this project (four hundred fifty (450) calendar days from the Notice to Proceed).
Contractors may propose an alternate schedule which illustrates the completion of the project in advance of the completion date.
C.4. This solicitation neither commits the Smithsonian Institution to pay any proposal preparation costs nor obligates the Smithsonian Institution to procure or contract for construction or any other services. It shall not be construed as authorization to proceed with or be reimbursed for any of the costs for any of the work specified herein.
C.5. The Smithsonian Institution may cancel this RFP without prior notice.
C.6. Statement of Work
The Contractor shall provide all engineering; supervision, materials, and equipment necessary to complete the following work at the Smithsonian Institution, National Museum of the American Indian, 1 Bowling Green, New York, NY 10004. For the purposes of brevity, this facility will be referred throughout this document to as NMAI-
NY.
The Work includes, but is not limited to, all work specified in/on the Drawings and in Divisions One through Twenty Eight of the Specifications: The objective of this project is to improve, upgrade and refresh the electronic security systems in and around the George Gustav Heye Center - NMAI-NY. This work will also include coordination and installation of required conduit, wiring, infrastructure, finish restoration (both historic and non-historic), and work in occupied space; while maintaining 100% ESS functionally throughout.
D - Packaging and Marking
Not Used
E - Inspection and Acceptance
52.246-12 Inspection of Construction. (AUG 1996)
52.246-S0038 Smithsonian Institution Inspection and Acceptance (Jun 2000)
Inspection and acceptance may be made on a daily basis on work performed at the job site, by the Contracting Officers Technical Representative. All work shall be coordinated through the COTR for acceptance of work, payrolls and invoice(s).
52.246-S0039 Final Inspection and Tests (Jun 2000)
The requirements of the Inspection of Construction clause prescribed in FAR 52.246-12, are supplemented to provide that the Contractor shall give the Contracting Officer at least
10 calendar days advance written notice of the date the work will be fully completed and ready for final inspection and tests. Final inspection and tests will be started within 10 calendar days from the date specified in the aforesaid notice unless the Contracting
Officer determines that the work is not ready for final inspection and so informs the
Contractor.
52.246-S0057 Inspection
(a) Upon proper notice and during normal working hours, the Smithsonian Institution reserves the right to perform any inspections and tests as deemed necessary to assure that the Contractor is performing in accordance with the terms and specifications as set forth herein.
(b) Inspection may be at the Contractor's place of business or at any location where work is being performed in conjunction with this contract.
(c) Inspection by the Smithsonian Institution shall not relieve the Contractor of responsibility for any or all quality control aspects during the life of the contract. This shall include quality control for items covered by this contract that may be subcontracted.
52.246-S0058 Acceptance
(a) The supplies and services rendered under this contract will be accepted and approved by the Contracting Officer or a designated representative thereto. Such approval will indicate acceptability to the Smithsonian Institution of performance in accordance with the terms and conditions of this contract, and will be subject to applicable warranties. The
Smithsonian Institution reserves the right to reject works not conforming to prescribed contract requirements.
(b) Neither the Smithsonian Institution's reviews, approval, nor acceptance of services and/or supplies, nor payment for any of the services or supplies required under this contract shall be construed to operate as a waiver of action arising out of the performance of this contract. Furthermore, the Contractor shall be and remain liable to the
Smithsonian Institution in accordance with applicable law for all damages to the
Smithsonian Institution caused by the Contractor's negligent performance of any of the supplies or services furnished under this contract.
(c) Acceptance by the Smithsonian Institution does not relieve the Contractor of responsibility for correction of errors or omissions that may arise after such acceptance if the errors and omissions are clearly a fault in Contractor performance.
F - Deliveries or Performance
Clauses
52.211-S0025 Commencement, Prosecution, and Completion of Work (Jun 2000)
(a) Definitions.
(1) The Contract Time is the period of time allotted in the Contract Documents for Final
Completion of the Work as defined in this Construction Contract Clause, including authorized extensions thereto. The Contractor shall complete his Work within the
Contract Time as stated in the SF 1442, or as modified.
(2) The date of commencement of the Work is the date established in the Notice To
Proceed issued by the C.O. Submission by the Contractor of its Performance and
Payment Bonds, Preliminary Schedule and all Certificates of Insurance and their approval by the S.I. are conditions precedent to the issuance of the Notice to Proceed. The
Contractor shall not commence the Work or store materials or equipment on site until written Notice to Proceed is issued or until the Contractor otherwise receives the written consent of the C.O.
(3) The date of Substantial Completion of the Work or designated portion thereof is the date certified by the COTR when the Work or a designated portion thereof is sufficiently complete, in accordance with the Contract Documents, so the S.I. can fully occupy the
Work or designated portion thereof for the use for which it is intended, with all of the
Project's parts and systems operable as required by the Contract Documents. Only punch list work and any final cleaning beyond that needed for the S.I.'s full use may remain for
Final Completion.
(4) The date of Final Completion of the Work is the date certified by the COTR when the
Work is totally complete, to include punch list work and final clean up, in accordance with the Contract Documents and the S.I. may fully occupy and fully utilize the Work for the use for which it is intended.
(5) If a date or time of completion is included in the Contract, it shall be the Date of Final
Completion as defined in this Construction Contract Clause, including authorized extensions thereto, unless otherwise provided.
(6) The term Day as used in the Contract Documents shall mean calendar day unless otherwise specifically designated. All dates shall mean midnight of the indicated day unless otherwise stipulated.
(b) Progress and Completion.
(1) All time limits stated in the Contract Documents are of the essence of the Contract.
(2) The Contractor shall prosecute the Work diligently to Final Completion.
(c) Delays and Extensions of Time.
(1) The time during which the Contractor is delayed in the performance of the Work, by the acts or omissions of the S.I., the Architect, or their employees or agents, acts of God, unusually severe and abnormal climatic conditions, fires, floods, epidemics, quarantine restrictions, strikes, riots, civil commotion or freight embargoes, or other conditions beyond the Contractor's control and which the Contractor could not reasonably have foreseen and provided against, shall be added to the Contract Time; provided, however, that no claim by the Contractor for an extension of time for delays will be considered unless made in compliance with the requirements of this Article and other provisions of the Contract Documents.
(2) Neither the S.I., nor the Architect shall be obligated or liable to the Contractor for, and the Contractor hereby expressly waives any claims against the S.I. and the Architect on account of any indirect or direct damages, costs or expenses of any nature which the
Contractor, Subcontractors, of Suppliers or any other person may incur as a result of any delays, interference, changes in sequence or the like, which are reasonable, foreseeable, contemplated, or avoidable by the Contractor, arising from or out of any act or omission of the S.I. of the Architect, or their agents, employees, consultants, separate contractors or any governmental representative, it being understood and agreed that the Contractor's sole and exclusive remedy in any such events shall be an extension of the Contract Time, but only as determined in accordance with the provisions of the Contract Documents.
(3) The Contract Time shall be adjusted only for Change Orders pursuant to the
Construction Contract Clause entitled "Changes", excusable delays pursuant to
Construction Contract Clause entitled "Delays and Extensions of Time" and Construction
Contract Clause entitled "Smithsonian Institution's Right to Stop or to Suspend the
Work". In the event the Contractor requests an extension of the Contract Time, he shall furnish such justification and supporting evidence as the C.O. may deem necessary for a determination of whether the Contractor is entitled to an extension of time under the provisions of the Contract. The burden of proof to substantiate a claim for an extension of the Contract Time shall rest with the Contractor, including evidence that the cause was beyond his control. The C.O. shall base his findings of fact and decision on such justification and supporting evidence and shall advise the Contractor in writing thereof. If the C.O. finds that the Contractor is entitled to any extension of the Contract Time, the
C.O.'s determination of the total number of days' extension shall be based upon the currently approved Progress Schedule and on all data relevant to the extension. Such data will be incorporated into the Progress Schedule in the form of a revision thereto, accomplished in a timely manner. The Contractor acknowledges and agrees that actual delays (due to said changes, suspensions of work or excusable delays) in activities which, according to the Progress Schedule, do not affect the Contract Time, do not have any effect upon the Contract Time and therefore will not be the basis for a change therein.
The Contractor acknowledges and agrees that time extensions will be granted only to the extent that excusable delays exceed the available float in the Contractor's Progress
Schedule.
(4) Subject to other provisions of the Contract, the Contractor may be entitled to an extension of the Contract Time (but no increase in the Contract Price) for delays arising from unforeseeable causes beyond the control and without the fault or negligence of the
Contractor, his Subcontractors or Suppliers as follows:
(i) Labor disputes and strikes (including strikes affecting transportation), that do, in fact, directly and critically affect the progress of the Work; however, an extension of Contract time on account of an individual labor strike shall not exceed the number of days of said strike;
(ii) Acts of God, tornado, fire, hurricane, blizzard, earthquake, typhoon, or flood that damage completed work or stored materials.
(iii) Abnormal inclement weather; however, the Contract Time will not be extended due to normal inclement weather. The time for performance of this Contract, as stated in the
Contract Documents, includes an allowance for calendar days, which may not be available for construction out-of-doors; for the purposes of the Contract, the Contractor agrees that said number of calendar days per month are to be considered as normal inclement weather. Unless the Contractor can substantiate to the satisfaction of the S.I.
that there was greater than normal inclement weather considering the full term of the
Contract Time using a ten year average of accumulated record mean values from climatological data compiled by the U.S. Department of Commerce, National Oceanic and Atmospheric Administration for the locale of the Project and that such alleged greater than normal inclement weather actually delayed the Work or portions thereof which had an effect upon the Contract Time, the Contractor shall not be entitled to an extension of time. If the total accumulated number of calendar days lost due to inclement weather, from the start of Work until Final Completion, exceeds the total accumulated number to be expected for the same period from the aforesaid climatological data, time for completion will be extended by the number of calendar days needed to include the excess number of calendar days lost.
(iv) Acts of the public enemy, acts of the state, Federal or local government in its sovereign capacity, and acts of a separate contractor in the performance of its contract with the S.I. relating to the Project.
(5) The Contractor shall not be entitled to and hereby expressly waives any extension of time resulting from any conditions or cause unless said claim for extensions of time is made in writing to the C.O. within seven (7) days of the first instance of delay.
Circumstances and activities leading to such claim shall be indicated or referenced in a daily field inspection report for the day(s) affected; otherwise, all such claims are waived by the Contractor. In every such written claim, the Contractor shall provide the following information:
(i) Nature of the delay;
(ii) Date (or anticipated date) of commencement of delay;
(iii) Activities on the Progress Schedule affected by the delay, and/or new activities created by the delay and their relationship with existing activities;
(iv) Identification of person(s) or organizations(s) or event(s) responsible for the delay;
(v) Anticipated extent of the delay;
(vi) Recommended action to avoid or minimize the delay.
(d) Responsibility for Completion.
(1) The Contractor shall furnish such manpower, materials, facilities and equipment and shall work such hours, including night shifts, overtime operations and Sundays and holidays, as may be necessary to insure the progress and completion of the Work in accordance with the approved and currently updated Progress Schedule. If Work actually in place falls behind the currently updated and approved Progress Schedule and it becomes apparent from the current Progress Schedule that the Work will not be completed within the Contract Time, the Contractor agrees that he will, as necessary, take some or all of the following actions at no additional cost to the S.I., as required to eliminate substantially the backlog of the Work:
(i) Increase manpower in quantities and crafts necessary
(ii) Increase the number of work hours per shift, shifts per working day, working days per week, the amount of equipment, or any combination of the foregoing; and/or
(iii) Re-schedule activities to achieve maximum practical concurrence.
(2) The COTR may require the Contractor to submit a Recovery Schedule in accordance with the Supplementary Construction Contract Clause, demonstrating his program and proposed plan to make up the lag in scheduled progress and to ensure completion of the
Work within the Contract Time. If the COTR finds the proposed plan not acceptable, he may require the Contractor to submit a new plan. If the actions taken by the Contractor or the second plan proposed are not satisfactory, the COTR may require the contractor to take any of the actions set forth in this Construction Contract Clause without additional costs to the S.I., to make up the lag in scheduled progress.
(3) Failure of the Contractor to comply substantially with the requirements of this
Construction Contract Clause may be considered grounds for a determination by the S.I., pursuant to the Construction Contract Clause entitled "Default", that the Contractor is failing to prosecute the Work with the sufficient diligence to ensure its completion with the Contract Time.
52.236-S0036 Smithsonian Institution's Right to Stop or to Suspend the Work (Jun
2000)
(a) If the Contractor fails to correct defective Work as required by the Construction
Contract Clause entitled "Correction of Work", or fails to carry out the Work or supply labor and materials in accordance with the Contract Documents, the C.O. by a written order may order the Contractor to stop the Work, or any portion thereof, without monetary compensation to the Contractor until the cause for such order has been eliminated.
(b) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the Work for such period of time as he may determine to be appropriate for the convenience of the S.I.
(c) If the performance of all or any part of the Work is, for an unreasonable period of time, suspended, delayed, or interrupted by the S.I. or its authorized representatives in the administration of this Contract, or by failure of any one of them to act within the time specified in this Contract (or if no time is specified, within a reasonable time), an adjustment shall be made for an increase in the actual time required for performance of the Work by the Contractor, due solely to such unreasonable suspension, delay, or interruption and the Contract modified in writing accordingly. However, no claim for an extension of time shall be made under this Construction Contract Clause for any suspension, delay, or interruption pursuant to this Construction Contract Clause, or for which claim is provided or excluded under any other provision of this Contract. No claim under this Construction Contract Clause shall be allowed for any claim for an extension of time required for performance, unless within twenty (20) days after the act or failure to act involved, the Contractor submits to the COTR a written statement setting forth, as then practicable, the extent of such claimed time extension and unless the claim for an extension of time is asserted in writing as soon as practicable after the termination of such suspension, delay, or interruption. No claim shall be made for direct or indirect costs incurred by Contractor as a result of the events described in this Construction Contract
Clause, a time extension being the Contractor's sole remedy.
(d) A claim under this clause shall not be allowed (1) for any costs incurred more than twenty (20) days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order), and (2) unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.
(e) In the event of a suspension of work or delay or interruption of work, the Contractor will and will cause his subcontractors to protect carefully his, and their materials and work against damage or injury from the weather and maintain completed and uncompleted portions of the work as required by the Contract Documents. If, in the opinion of the COTR, any work or material shall have been damaged or injured by reason of failure on the part of the Contractor or any of his subcontractors to so protect same, such work and materials shall be removed and replaced at the expense of the Contractor.
(f) No claim by the Contractor for an equitable adjustment under the Construction
Contract Clause entitled "Equitable Adjustments", shall be allowed if asserted after Final
Payment under this Contract.
52.246-S0041 Additional Warranties and Guarantees (Jun 2000)
(a) The Contractor guarantees and warrants to the S.I. all work as follows:
(1) That all materials and equipment furnished under this Contract will be new and the best of its respective kind unless otherwise specified;
(2) That all Work will be first-class quality and free of omissions and faulty, poor quality, imperfect or defective material or workmanship;
(3) That where no standard is specified for such workmanship or materials, they shall be the best of their respective kinds;
(4) That the Work shall be entirely watertight and leak-proof in accordance with all applicable industry customs and practices, and shall be free of shrinkage and settlement, (normal shrinkage inherent in the specified materials is acceptable);
(5) That the Work, including but not limited to, mechanical and electrical machines, devices and equipment shall be fit and fully usable for its intended and specified purpose and shall operate satisfactorily with ordinary care;
(6) That consistent with requirements of the Contract Documents the Work shall be installed and oriented in such a manner as to facilitate unrestricted access for the operation and maintenance of fixed equipment;
(7) That the Work will be free of abnormal or unusual deterioration which occurs because of poor quality materials, workmanship or unsuitable storage.
(b) All work not conforming to guarantees and warranties specified in the Contract
Documents, including substitutions not properly approved and authorized, may be considered defective. If required by the COTR, the Contractor shall furnish satisfactory evidence as to the kind and quality of materials and equipment. This warranty is not limited by the provisions of the Construction Contract Clauses entitled "Uncovering of
Work" and "Correction of Work".
(c) The warranties set forth in this Construction Contract Clause entitled "Additional
Warranties and Guarantees" and elsewhere in the Contract Documents shall survive Final
Completion of the Work under the Construction Contract Clause entitled "Payments and
Completion".
(d) If, within one year after the Date of Final Completion of the Work or designated portion thereof or within one year after acceptance by the S.I. of designated equipment or within such longer period of time as may be prescribed by law or by the terms of any applicable special warranty required by the Contract Documents, any of the Work is found to be defective, not in accordance with the Contract Documents, or not in accordance with the guarantees and warranties specified in the Contract Documents, the
Contractor shall correct it within five (5) working days, or such other period as mutually agreed, after receipt of a written notice from the COTR to do so.
(e) Any materials or other portions of the Work, installed, furnished or stored on site which are not of the character or quality required by the specifications, or are otherwise not acceptable to the COTR, shall be immediately removed and replaced by the
Contractor to the satisfaction of the COTR, when notified to do so by the COTR.
(f) If the Contractor fails to correct defective or nonconforming Work as required by the
Construction Contract Clause entitled "Correction of Work", or if the Contractor fails to remove defective or nonconforming Work from the site, as required by the Construction
Contract Clause entitled "Uncovering of Work", the S.I. may elect to either correct such work in accordance with the Construction Contract Clause entitled "Smithsonian
Institution's Right to Carry Out The Work", or remove and store materials and equipment at the expense of the Contractor.
(g) The Contractor shall bear the cost of making good all work of the S.I., separate contractors or others, destroyed or damaged by such correction or removal required under this Construction Contract Clause or the Construction Contract Clauses entitled
"Uncovering of Work" and "Correction of Work", or elsewhere in the Contract
Documents.
G - Contract Administration Data
Clauses
52.202-S0059 Contract Management
Notwithstanding the Contractor's responsibility for total management during the performance of this contract, the administration of the contract will require maximum coordination between the Smithsonian and the Contractor. The following individuals will be the Smithsonian points of contact during the performance of the contract.
52.202-S0060 Contracting Officer
All contract administration will be effected by the Contracting Officer. Communications pertaining to contractual administrative matters will be addressed to the Contracting
Officer. No changes in or deviation from the scope of work shall be effected without a written modification to the contract executed by the Contracting Officer authorizing such changes.
52.202-S0061 Contracting Officer's Technical Representative (COTR) (Apr 1988)
(a) The Contracting Officer's Technical Representative (COTR) Janice Slivko, or her authorized representative shall act for and on behalf of the Contracting Officer in the administration of any resultant contract with respect to:
1. Resolution of issues that may arise between the Contractor and the Smithsonian
Institution in connection with such matters as acceptability of workmanship and other technical requirements;
2. Evaluation on an overall basis of the acceptability of workmanship and Contractor's compliance with technical requirements; and
3. The approval and acceptance of work performed under this contract.
(b) This delegation does not authorize the modification of any of the contract's provisions, terms or conditions. All authorities not herein delegated are reserved to the
Contracting Officer.
(c) The Contractor shall make available such records, reports and facilities as may be required to carry out this assignment.
52.202-S0062 Authorities
The Contractor is advised that only the Contracting Officer can change or modify the terms of this contract or take any other action which obligates the Smithsonian and then such action must be set forth in a formal modification to the Contract. The authority of the COTR is strictly limited to the specific duties set forth in her letter of appointment, a copy of which will be furnished the Contractor. Contractors who rely on direction from persons other than the Contracting Officer (or a COTR acting within the strict limits of his/her responsibilities as set forth in his/her letter of appointment) do so at their own risk and expense, as such actions do not bind the Smithsonian contractually. All questions concerning the authority of a Smithsonian employee to direct the Contractor contractually should be referred to the Contracting Officer.
52.213-S0094 Application for Payment
The Contractor shall submit Application for Payment in triplicate copies and in accordance with the Construction Contract Clauses. All Applications for Payment shall identify the Contract Number and Project Title and shall be submitted to the COTR at the address specified by the Work Order.
Note: The Prompt Payment Act (31 U.S.C. Section 3901) is not applicable to the
Smithsonian Institution. The Smithsonian Institution shall take all reasonable measures to ensure that payment for invoice(s) properly documented and submitted shall be paid within thirty (30) days from receipt of an approved proper invoice.
52.215-S0002 Authorized Negotiators (Apr 1984)
The offeror or quoter represents that the following persons are authorized to negotiate on its behalf with the Government in connection with this request for proposals or quotations: [list names, titles, and telephone numbers of the authorized negotiators].
H - Special Contract Requirements
Clauses
52.202-S0010 Use of Smithsonian Name (Jun 2000)
It is recognized and acknowledged that Contractor shall have no right to use the name
"Smithsonian" or "Smithsonian Institution", or the name of any Smithsonian Museum or part thereof, including the Facilities, in connection with any of its own advertising, marketing or promotion. However, any marketing or promotional programs concerning the Smithsonian or the Project shall be submitted to the Smithsonian for review and approval prior to any implementation thereof. The Smithsonian may withhold any approval required hereunder as it wishes.
The Prime Contractor shall be responsible for compliance by any subcontractor or supplier or lower tier subcontractor or lower tier supplier with this clause. After award of the contract and upon request of the Contracting Officer, the Prime Contractor shall deliver a written statement acknowledging that this clause has been included in contracts with all subcontractors and suppliers.
52.203-S0004 Advertising of Award Smithsonian Institution
The Contractor shall not refer to the Smithsonian or to any of its museums, organizations, or facilities in any manner or through any medium, whether written, oral or visual, for any purpose whatsoever, including advertising, marketing, and promotion.
52.215-S0008 Contracting Officer's Technical Representative (Apr 1988)
Contracting Officer's Technical Representative (herein referred to as the COTR) will be the Contracting Officer's (CO) exclusive representative to the Contractor with respect to the Project during construction and until Final Payment and Release of Claims. The term
COTR is referred to throughout the Contract Documents as if singular in number and masculine in gender. The Smithsonian Institution's communications with the Contractor shall be exclusively through the COTR, who will have full authority to act on behalf of the C.O. with regard to all aspects of the Project except that the C.O. must approve all
Modifications and payments to the Contractor and is the final authority for all disputes under any Clause of this Contract. All of the Contractor's communications to the S.I. shall be exclusively through the COTR. All of the COTR's actions with regard to this Project will be as the representative of the C.O.
52.215-S0009 Information, Services and Rights of the Smithsonian (Apr 1988)
(a) The S.I., through the C.O. and COTR, will provide administration of the contract as hereinafter described.
(b) The S.I. or its authorized representatives shall at all times have access to the Work whenever it is in preparation or progress. The Contractor shall provide safe facilities for such access.
(c) The S.I. or its authorized representatives shall not be responsible for or have control or charge of the construction means, methods, techniques, sequences, or procedures, or for safety precautions and program in connection with the Work, and will not be responsible for the Contractor's failure to carry out the Work in accordance with the
Contract Documents.
(d) The COTR shall have authority to reject Work when in his opinion, the Work does not conform to the Contract Documents.
(e) Whenever in the COTR's reasonable opinion it is considered necessary or advisable for the implementation of the intent of the Contract Documents, the COTR will have authority to require special inspection or testing of the Work in accordance with the provisions of the Contract Documents whether or not such Work be then fabricated, installed or completed.
(f) The COTR shall have the authority and discretion to call, schedule, and conduct job meetings to be attended by the Contractor, representatives of his Subcontractors, and the
Architect to discuss such matters as procedures, progress, problems, payments and scheduling.
(g) The COTR will establish procedures to be followed for processing all Shop Drawings, catalogs, and other project reports and other documentation, test reports, and maintenance manuals.
(h) The COTR will review all requests for changes and shall implement the processing of
Change Orders, including applications for extension of the Contract Time.
(1) The COTR will review and process all Progress Payments including the Final
Payment.
(2) The Smithsonian Institution or its authorized representatives shall not be responsible or liable to the Contractor for the acts, errors or omissions of the Contractor, any separate
Subcontractor, any separate contractor or any contractor's or subcontractor's agents or employees, or any other persons performing any of the Work.
(k) Unless otherwise provided in the Contract Documents, the Contractor will be furnished, free of charge, ten copies of full size Drawings and Specifications reasonably necessary for the execution of the Work.
(l) The foregoing rights are in addition to other rights of the S.I. enumerated herein and those provided by law.
52.223-S0070 Dissemination of Information
There shall be no dissemination or publication of information, except between the
Contractor and any subcontractors, of information developed under this contract or any task orders awarded under the terms of this contract or contained in reports to be furnished pursuant to this contract without the prior written approval of the Contracting
Officer.
52.236-S0030 Availability and Use of Utility Services (Jun 2000)
(a) The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. These services shall be furnished without charge to the Contractor. The Contractor shall carefully conserve any utilities furnished without charge.
(b) The Contractor, at its expense and in a workmanlike manner satisfactory to the
Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, and associated paraphernalia.
52.236-S0031 Use of Site (Jun 2000)
The Contractor shall confine operations at the site to areas permitted by law, ordinances, permits, easements, right-of-way agreements and the Contract Documents. The
Contractor shall not unreasonably encumber the site, in the opinion of the COTR, with any materials, equipment or trailers nor shall he block the entrances or otherwise prevent reasonable access to the site, other working and parking areas, completed portions of the
Work and/or other properties, storage areas, loading dock and other areas of the work site or areas that are adjacent to the work site. If the Contractor fails or refuses to move said materials, equipment or trailers within 24 hours of notification by the COTR to so do, the
COTR shall have the right, without further notice, to remove, at the Contractor's expense, any material, equipment and/or trailers which the COTR deems are in violation of this
Construction Contract Clause entitled "Use of Site".
52.242-S0020 Historic & Archeological Rights (Jun 2000)
(a) If during the excavation of the site items of historic and archeological significance are found, the contractor shall stop work and notify the COTR immediately. Subsequent excavation work shall proceed as directed by the COTR.
(b) All items considered by the Smithsonian Institution to have historic or archaeological significance are the property of the Smithsonian Institution.
I - Contract Clauses
Clauses
52.203-3 Gratuities. (APR 1984)
52.203-5 Covenant Against Contingent Fees. (MAY 2014)
52.203-7 Anti-Kickback Procedures. (MAY 2014)
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper
Activity. (MAY 2014)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity. (MAY 2014)
52.203-12 Limitation on Payments to Influence Certain Federal Transactions. (OCT
2010)
52.204-2 Security Requirements. (AUG 1996) - Alternate II (APR 1984)
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper.
(MAY 2011)
52.204-7 System for Award Management. (OCT 2018)
(a) Definitions. As used in this provision-
Electronic Funds Transfer (EFT) indicator means a four-character suffix to the unique entity identifier. The suffix is assigned at the discretion of the commercial, nonprofit, or Government entity to establish additional System for Award
Management records for identifying alternative EFT accounts (see subpart 32.11) for the same entity.
Registered in the System for Award Management (SAM) means that-
(1) The Offeror has entered all mandatory information, including the unique entity identifier and the EFT indicator, if applicable, the
Commercial and Government Entity (CAGE) code, as well as data required by the Federal Funding Accountability and Transparency Act of
2006 (see subpart 4.14) into SAM;
(2) The offeror has completed the Core, Assertions, and Representations and Certifications, and Points of Contact sections of the registration in
SAM;
(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal
Revenue Service (IRS). The offeror will be required to provide consent for
TIN validation to the Government as a part of the SAM registration process; and
(4) The Government has marked the record "Active".
Unique entity identifier means a number or other identifier used to identify a specific commercial, nonprofit, or Government entity. See www.sam.gov for the designated entity for establishing unique entity identifiers.
(b)(1) An Offeror is required to be registered in SAM when submitting an offer or quotation, and shall continue to be registered until time of award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.
(2) The Offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation "Unique Entity Identifier" followed by the unique entity identifier that identifies the Offeror's name and address exactly as stated in the offer. The Offeror also shall enter its EFT indicator, if applicable. The unique entity identifier will be used by the
Contracting Officer to verify that the Offeror is registered in SAM.
(c) If the Offeror does not have a unique entity identifier, it should contact the entity designated at www.sam.gov for establishment of the unique entity identifier directly to obtain one. The Offeror should be prepared to provide the following information:
(1) Company legal business name.
(2) Tradestyle, doing business, or other name by which your entity is commonly recognized.
(3) Company physical street address, city, state, and Zip Code.
(4) Company mailing address, city, state and Zip Code (if separate from physical).
(5) Company telephone number.
(6) Date the company was started.
(7) Number of employees at your location.
(8) Chief executive officer/key manager.
(9) Line of business (industry).
(10) Company headquarters name and address (reporting relationship within your entity).
(d) Processing time should be taken into consideration when registering. Offerors who are not registered in SAM should consider applying for registration immediately upon receipt of this solicitation. See https://www.sam.gov for information on registration.
(End of provision)
52.209-6 Protecting the Government's Interest When Subcontracting With
Contractors Debarred, Suspended, or Proposed for Debarment. (OCT 2015)
52.215-8 Order of Precedence - Uniform Contract Format. (OCT 1997)
52.219-28 Post-Award Small Business Program Representation. (JUL 2013)
(a) Definitions. As used in this clause-
Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern means a concern, including its affiliates that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.