3.c_WORK ITEM 26 SPEC.pdf
PDF 114 KB Posted
- Attached to
- --REMOVE & INSTALL INSULATION ON CG45601 Federal contract opportunity
- Solicitation number
- 70Z02722RPORT0002
About this file
CG Spec
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 7.m_WAGE DETERMINATION.pdf | ||
| 3.c_SOW 45601 INSULATION.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCG 45601 (RB-M-45) DRYDOCK AVAILABILITY FY2022
123 (Rev-0)
63500_AKP_0121_45RBM
WORK ITEM 26: Interior Hull Insulation, Renew
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew the interior hull insulation selected in Table 1.
TABLE 1- HULL INSULATION LOCATION
SELECT DESCRIPTION LOCATION APPROXIMATE SQFT
TO BE REPLACED
Bulkhead or Overhead Pilothouse XX Forward Bulkhead Survivors Cabin 7 XX Machinery Space Machinery Space to also include PORT and STBD demister housings
XX Inside lining Pyro Locker 0.5
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 45 RB-M 635-002, Rev C, Insulation Details
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
124 (Rev-0)
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
Sheathing
Bulkhead insulation
Piping
Electrical wiring
CAUTION
The insulation currently installed in the 45 RB-M engine room and engine room ventilation supply ducts are made up of two layers of fiberglass with a thin layer of lead sheathing in the middle. Lead is a recognized health hazard.
Lead may adversely affect the peripheral and central nervous systems, as well as the red blood cells, kidneys, reproductive and endocrine systems.
3.2 Removal. The Contractor must remove the interior insulation and associated fastening hardware selected in Table 1. Refer to Coast Guard Drawing 45 RB-M 635-002 and SFLC Std Spec 0000 for guidance.
3.2.1 Disposal. The Contractor must dispose of all removed materials, in accordance with all applicable Federal, state, and local regulations.
3.3 Substrate inspection - visual inspection. Upon removal of existing insulation, the Contractor must visually inspect the exposed surfaces for corrosion, pitting and any other visible defects. Submit a CFR.
3.4 Installation. The Contractor must install the new insulation in accordance with Coast Guard Drawing 45 RB-M 635-002 and SFLC Std Spec 0000.
NOTE
Lead sheet is no longer authorized for installation.
3.4.1 Engine Room Specific Insulation. The Contractor must renew the engine room insulation as follows:
3.4.1.2 The Contractor must provide all installation material and fasteners:
Sound attenuation barrier: Pyrotek "Quadzero", P/N 17763007
Hullboard: Owens Corning 2 inch Foil -Faced "Insul-Quick" insulation.
3.4.1.3 The Contractor must replace up to 20 percent of the welded studs and caps.
125 (Rev-0)
3.4.1.3.1 The Contractor must weld all insulation mounting studs.
3.4.1.4 The Contractor must install the insulation as follows starting at the bulkhead/hull in the following sequence.
Quadzero
Insulation Speed Washer
2 inch Insul-Quick Hullboard
Insulation Speed Washer
Trim Pin (as required)
Insulation Cap
Tape all boundaries
4. NOTES
This section is not applicable to this work item.