2of2 W9128F21Q0033 - Specifications for Zebra Mussel Mitigation at Ft Randall Dam in SD.pdf
PDF 760 KB Posted
- Attached to
- Zebra Mussel Mitigation, Fort Randall Federal contract opportunity
- Solicitation number
- W9128F21Q0033
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Am0002 - Drawings - FR Zebra Mussel.pdf | ||
| Am0002 - W9128F21Q0033 - FR Zebra Mussel Mitigation.pdf | ||
| Am0002 - Specifications - FR Zebra Mussel.pdf | ||
| Amd 01 for W9128F21Q0033 - FR Zebra Mussel Mitigation.pdf | ||
| 1of2 W9128F21Q0033 - Zebra Mussel Mitigation at Ft Randall Dam in SD.pdf | ||
| Redacted Justification for EarthTec QZ_Redacted.pdf | ||
| Zebra Mussel Mitigation Drawings.PDF |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS
(Purchase Order)
Solicitation Number W9128F21Q0033
Zebra Mussel Mitigation System
Fort Randall Dam, SD
April 2021
US Army Corps of Engineers Omaha District
This page was intentionally left blank for duplex printing.
Zebra Mussel Mitigation System Fort Randall Dam, SD
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 73 00 SUPPLEMENTARY CONDITIONS (SPECIAL CONTRACT
REQUIREMENTS)FOR PURCHASE ORDERS
DIVISION 01 - GENERAL REQUIREMENTS
01 22 00 MEASUREMENT AND PAYMENT
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 57 20.00 10 ENVIRONMENTAL PROTECTION
DIVISION 43 - PROCESS GAS AND LIQUID HANDLING, PURIFICATION, AND STORAGE
EQUIPMENT
43 32 69 LIQUID COPPER BASED PESTICIDE (CBP) DISTRIBUTION SYSTEM
FOR ZEBRA MUSSEL MITIGATION
-- End of Project Table of Contents --
Zebra Mussel Mitigation System, Fort Randall Dam, SD FRH2
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 73 01
SUPPLEMENTARY CONDITIONS (SPECIAL CONTRACT REQUIREMENTS)FOR PURCHASE ORDERS
2/19
PART 1 GENERAL
1.1 SCOPE
1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK.
1.3 CONTRACT DRAWING AND SPECIFICATIONS
1.4 SUBMITTALS
1.5 CONTRACTOR QUALITY CONTROL (CQC).
1.5.1 Responsibility of the Contractor
1.6 GUARANTEE
1.7 ACCIDENT PREVENTION
1.8 PROTECTION OF EXISTING FACILITIES AND WORKS
1.9 CONTRACT DRAWINGS AND SPECIFICATIONS
1.9.1 NOTIFICATION OF DISCREPANCIES
1.9.2 OMISSIONS
1.10 PAYMENT
1.10.1 PROMPT PAYMENT ACT
1.10.2 PAYMENTS FOR MODIFICATIONS
1.11 AVAILABILITY OF UTILITY SERVICES
1.12 PROFIT
1.13 AS-BUILT DRAWINGS
1.14 PORTABLE TOILETS
1.15 FEDERAL HOLIDAYS AND WORKING HOURS
1.16 ANTITERRORISM (AT)/OPERATIONS SECURITY (OPSEC) PROVISIONS
1.17 USE OF GOVERNMENT EQUIPMENT
1.17.1 Powerhouse Crane Operation
1.17.2 Working Hours
1.17.3 Hours of Use and Overtime Payment
1.18 COORDINATION AND OUTAGES
1.19 GAS, VAPOR, FUME, DUST, SLURRY AND MIST CONTROL IN POWERHOUSE
PART 2 NOT USED
PART 3 NOT USED
-- End of Section Table of Contents --
DOCUMENT 00 73 00 Page 1
SECTION 00 73 01
SUPPLEMENTARY CONDITIONS (SPECIAL CONTRACT REQUIREMENTS)FOR PURCHASE ORDERS
2/19
PART 1 GENERAL
1.1 SCOPE
The Contractor is to provide four (4) complete sets of the LIQUID COPPER BASED PESTICIDE (CBP)-EarthTec QZ (EPA-registered molluscicide for prevention and control of quagga and zebra mussels)- DISTRIBUTION SYSTEM to control / prevent zebra mussel infestation in four (4) of the 14" raw water intake piping serving various cooling systems in the powerhouse. The required work also includes on site welding work to install various instrumentations in the existing 14" raw water piping, to provide chemical distribution system piping, pumping skid, controls, and the electrical connections at a minimum.
1.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK.
The Contractor shall commence work under this contract within ten (10) calendar days after the date of receipt by him of Notice to Proceed, prosecute said work diligently, and complete the entire work ready for use not later than 90 calendar days after receipt of Notice to Proceed. The time stated for completion shall include final cleanup of the premises.
(FAR 52.211-10)
1.3 CONTRACT DRAWING AND SPECIFICATIONS
The Contractor shall be responsible for making his own copies of specifications, drawings and any amendments, as needed for the duration of the project, from the electronic files provided.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
AT Level I Training Sign In Sheets;
Sign In Sheets for all employee training required for AT Level I Training, see paragraphs 1.16, subparagraph 1
Security Personnel List; G-PO
Security Personnel list as described in Access and General Protection/Security Policy and Procedures paragraph 1.16, subparagraph 2.1.
iWATCH and/or CorpsWatch Training Sign In Sheets;
DOCUMENT 00 73 00 Page 2
Sign In Sheets for all employee training required for iWATCH and/or CorpsWatch Training, see paragraphs 1.16, subparagraph 4
OPSEC Training Sign In Sheets;
Sign In Sheets for all employee training required for OPSEC Training, see paragraphs 1.16, subparagraph 7
1.5 CONTRACTOR QUALITY CONTROL (CQC).
1.5.1 Responsibility of the Contractor
Except for isolated tests or other items of work specified to be performed by the Government, the quality of all work shall be the responsibility of the Contractor. Sufficient inspections and tests of all items of work, including that of subcontractors, to ensure conformance to applicable specifications and drawings with respect to the quality of materials, workmanship, construction, finish, functional performance, and identification shall be performed on a continuing basis.
1.6 GUARANTEE
The equipment and supplies to be furnished under this contract shall be guaranteed for a period of one (1) year from the date of acceptance thereof, either for beneficial use or final acceptance, whichever is earlier, against defective materials, design, and workmanship. Upon receipt of notice from the Government of failure of any of the guaranteed equipment during the guarantee period, new replacement parts shall be furnished and installed promptly by the Contractor at no additional cost to the Government. The Contractor shall also obtain and deliver to the Contracting Officer any warranties of equipment or supplies which the subcontractors, manufacturers, or suppliers would give normal commercial practice.
1.7 ACCIDENT PREVENTION
In accordance with EM 385-1-1, Safety and Health Requirements Manual, the Contractor shall provide for protecting of the lives and health of employees and other persons; preventing of damage to property; and avoiding work interruptions. See Section 01 35 26 GOVERNMENT SAFETY REQUIREMENTS for more information.
1.8 PROTECTION OF EXISTING FACILITIES AND WORKS
The Contractor shall be responsible for the protection of work area from damage and upon completion of the work shall leave existing works in a condition equal to that which existed when the work started.
1.9 CONTRACT DRAWINGS AND SPECIFICATIONS
1.9.1 NOTIFICATION OF DISCREPANCIES
The Contractor shall check all drawings furnished him immediately upon their receipt and shall promptly notify the Contracting Officer of any discrepancies. Dimensions marked on drawings shall be followed in lieu of scale measurements. Enlarged plans and details shall govern where the same
DOCUMENT 00 73 00 Page 3 work is shown at smaller scales. The Contractor shall compare all drawings and verify the figures before laying out the work and will be responsible for any errors which might have been avoided thereby.
1.9.2 OMISSIONS
Omissions from the drawings or specifications or the misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work but they shall be performed as if fully and correctly set forth and described in the drawings and specifications.
1.10 PAYMENT
1.10.1 PROMPT PAYMENT ACT
Pay requests authorized in CONTRACT CLAUSES clause: "Payments Under Fixed Price Construction Contracts", will be paid pursuant to the clause, "Prompt Payment for Construction Contracts". Pay requests will be submitted on ENG Form 93 and 93a, "Payment Estimate Contract Performance" and "Continuation". All information and substantiation required by the identified contract clauses will be submitted with the ENG Form 93, and the required certification will be included on the last page of the ENG Form 93a, signed by an authorized contractor official and dated when signed.
The designated billing office is the Office of the Area Engineer.
1.10.2 PAYMENTS FOR MODIFICATIONS
Payments may be made for cost bearing change orders within the scope of the contract only to the extent funds are authorized in the order on a two part modification. Contractor pricing proposed must be submitted at the earliest possible time after the change order is issued, or at a specific time as directed by the Contracting Officer. At the discretion of the Contracting Officer, any and all payments may be withheld on the modification until the Contractor has submitted a qualifying price proposal, in as much detail as required by the Contracting Officer, and the final price has been agreed.
1.11 AVAILABILITY OF UTILITY SERVICES
All reasonably required amounts of domestic water and electricity will be made available to the Contractor by the Government from existing system outlets and supplies.
1.12 PROFIT
a. Weighted guidelines method of determining profit shall be used on any equitable adjustment change order or modification issued under this contract. The profit factors shall be as follows:
Factor Rate Weight Value Degree of Risk 20 See Item Relative difficulty of work 15 b. below Size of Job 15 Period of performance 15 Contractor's investment 5
DOCUMENT 00 73 00 Page 4
Assistance by Government 5 Subcontracting 25
b. Based on the circumstances of each procurement action, each of the above factors shall be weighted from .03 to .12 as indicated below. The value shall be obtained by multiplying the rate by the weight. The value column when totaled indicates the fair and reasonable profit percentage under the circumstances of the particular procurement.
(1) Degree of Risk. Where the work involves no risk or the degree of risk is very small, the weighting should be .03; as the degree of risk increases, the weighting should be increased up to a maximum of .12. Lump sum items will have, generally, a higher weighted value than the unit price items for which quantities are provided. Other things to consider: the portion of the work to be done by subcontractors, nature of work, where work is to be performed, reasonableness of negotiated costs, amount of labor included in costs, and whether the negotiation is before or after performance of work.
(2) Relative Difficulty of Work. If the work is most difficult and complex, the weighting should be .12 and should be proportionately reduced to .03 on the simplest of jobs. This factor is tied in to some extent with the degree of risk. Some things to consider: the nature of the work, by whom it is to be done, where, and what is the time schedule.
(3) Size of Job. All work not in excess of $100,000 shall be weighted at .12. Work estimated between $100,000 and $5,000,000 shall be proportionately weighted from .12 to .05.
(4) Periods of Performance. Jobs in excess of 24 months are to be weighted at .12. Jobs of lesser duration are to be proportionately weighted to a minimum of .03 for jobs not to exceed 30 days. No weight where additional time not required.
(5) Contractor's Investment. To be weighted from .03 to .12 on the basis of below average, average, and above average. Things to consider: amount of subcontracting, mobilization payment item, Government furnished property, equipment and facilities, and expediting assistance.
(6) Assistance by Government. To be weighted from .12 to .03 on the basis of average to above average. Things to consider: use of Government-owned property, equipment and facilities, and expediting assistance.
(7) Subcontracting. To be weighted inversely proportional to the amount of subcontracting. Where 80 percent or more of the work is to be subcontracted, the weighting is to be .03 and such weighting proportionately increased to .12 where all the work is performed by the Contractor's own forces.
1.13 AS-BUILT DRAWINGS
The Contractor shall provide a marked-up half size drawing to show actual work performed to include necessary sketches, modification drawings, shop drawings and notes. Red ink is to be used for additions and deviations from the contract. Green ink is to be used to indicate work deleted from the contract. The drawings shall be maintained by the contractor as the work progresses and available for review by the government
DOCUMENT 00 73 00 Page 5 representatives. The as-built drawings shall be submitted for approval at the completion of the project. The completed set shall be available at time of final inspection.
1.14 PORTABLE TOILETS
Toilet facilities will not be available for Contractor's use. The Contractor shall provide and maintain portable toilets for use by the Contractor's staff . Toilet(s) shall be placed at the location directed by the Contracting Officer. To prevent overturning by high winds, all portable toilets shall be anchored down.
1.15 FEDERAL HOLIDAYS AND WORKING HOURS
Work hours: The Contractor can work Monday through Friday 0700 to 1700.
Working outside these work hours will need written permission from the COR.
The Contractor will not be allowed to work on Federal holidays or observance days.
The following Federal legal holidays are observed by this installation:
New Year's Day 1 January Martin Luther King's Birthday Third Monday in January President's Day Third Monday in February Memorial Day Last Monday in May Independence Day 4 July Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day 11 November Thanksgiving Day Fourth Thursday in November Christmas Day 25 December
If a wage determination applies the number of holidays specified on it, it has priority over this requirement.
1.16 ANTITERRORISM (AT)/OPERATIONS SECURITY (OPSEC) PROVISIONS
1. AT Level I Training
All Contractor employees, to include subcontractor employees, requiring access to Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days prior to mobilization. The Contractor shall submit certificates of completion and memo listing names of each affected Contractor employee and subcontractor employee who took the training on the date listed on the submitted certificate, to the COR or to the contracting officer, if a COR is not assigned, within 5 calendar days after completion of training by all employees and subcontractor personnel (submittal: AT Level I Training Sign In Sheets). Any following trainings documented via memo shall require at least one formal certificate matching the dates listed on the memo. AT Level I awareness training is available at the following website:
https://jko.jten.mil/courses/atl1/launch.html.
2. Access and General Protection/Security Policy and Procedures
All Contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The Contractor shall also provide
DOCUMENT 00 73 00 Page 6 all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in Contractor security matters or processes.
2.1 Submit a complete, updated and signed, list of all Contractor and subcontractor personnel, including their titles and intended working hours, who will be working on site prior to start of work. This listing shall be revised and resubmitted when personnel changes occur. (SUBMITTAL FIO)
2.2 Personnel Risk Assessment
A minimum of seven days prior to engaging in work submit, to the CO or Project POC, a Personnel Risk Assessment (PRA) for each employee requiring authorized unescorted access to the Jobsite. The Contractor employee will only be allowed authorized unescorted physical access after the PRA is shown to and approved by the Government.
2.3 Authorized Unescorted Access Requirements
Perform a PRA on all Contractor personnel that require authorized unescorted access to the Jobsite. Costs associated with the execution of the PRA shall be at the expense of the Contractor. The content of the PRA is defined by the requirements as follows:
a. Criminal Check - Obtain a criminal background check, completed within the last seven years (assuming continuous employment, otherwise a new one must be accomplished), on all Contractor personnel that require authorized unescorted access to the Jobsite. A minimum of a 7-year criminal background check with the state patrol office shall be performed from all states of residence and employment, for the past seven years. The Project Security Officer through the Contracting Officer will approve, disapprove, or revoke authorized unescorted access to the Jobsite as a result of the seven-year background check.
b. Identity Verification - Contractor employees shall provide positive verification of individual identity prior to authorized unescorted access to the Jobsite. Acceptable forms of identity verification are documents issued by a federal Government agency that include: the individual's photograph, name, and date of birth, such as a passport or military identification (ID) card. Additionally, a state issued driver's license or ID card is acceptable for identity verification.
c. The Criminal Check and Identity Verification shall be updated at least every seven years for each employee requiring authorized unescorted access to the Jobsite.
d. Escort Requirements - Contractor personnel not cleared for authorized access to the Jobsite may be escorted by Government or Contractor personnel that have authorized unescorted access to the Jobsite. All costs related to the escorting of non-cleared personnel shall be at the expense of the Contractor. Additional burden shall not be placed upon the Government to provide these escorts. Prior to access, coordination with the Project Security Officer is required, including but not limited to:
DOCUMENT 00 73 00 Page 7
(1) Verification of identity with photo identification
(2) Name of escorting individual and verification of unescorted status
(3) Time of entry into the Jobsite
(4) Time exiting the Jobsite.
3. Not Used
4. iWATCH and/or CorpsWatch Training
The Contractor and all associated subcontractors shall brief all employees on the local iWATCH, Corps Watch, or See Something, Say Something program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 10 days prior to mobilization and within 30 calendar days of new employees commencing performance with the results reported to the COR. (submittal: iWATCH and/or CorpsWatch Training Sign In Sheets).
http://www.myarmyonesource.com/cmsresources/Army%20OneSource/Media/Videos/ Family%20Programs%20and%20Services/iWatch_Program/iWATCH%2060_4streaming.wmv
5. and 6 NOT USED.
7. OPSEC Training
All new Contractor employees will complete Level I OPSEC training within 30 calendar days prior to mobilization. Additionally, all Contractor employees must complete annual OPSEC awareness training. (submittal: OPSEC Training Sign In Sheets) https://securityawareness.usalearning.gov/opsec/
8. thru 12 NOT USED
13. Will be Escorted in Areas Where They May be Exposed to Classified and/or Sensitive Materials and/or Sensitive or Restricted Areas If applicable, all contract employees, including subcontractor employees who are not in possession of the appropriate security clearance, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas. There is NO classified material at this project location.
14. NOT USED
15. Pre-Screen Candidates using E-Verify Program
The Contractor must pre-screen Candidates using the E-verify Program (http://www.dhs.gov/E-Verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.
16. & 17 Not Used
DOCUMENT 00 73 00 Page 8
1.17 USE OF GOVERNMENT EQUIPMENT
1.17.1 Powerhouse Crane Operation
Government personnel only will operate the powerhouse crane. The Contractor will be responsible for furnishing and performing all rigging and signaling for all lifts. The Government must inspect and approve all rigging prior to performing the lift. The Contractor will be responsible for all off-loading, movement, and loading of required construction equipment. Equipment will be lowered to and from the working level with the powerhouse crane.
1.17.2 Working Hours
The Contractor shall properly prepare and plan all lifts such that Government operators are required for a minimum number of occasions. Use of the crane will only be during normal Government working hours. A crane operator will not be furnished on a standby basis. The Contractor shall coordinate with the powerplant superintendent, in writing 24 hours in advance, the need for a crane operator. The Government will operate the crane during the normal daytime working hours of 7:00 am to 4:00 pm Monday thru Thursday.
1.17.3 Hours of Use and Overtime Payment
The Contractor will be allowed 8 hours of crane time during the life of the Contract.
1.18 COORDINATION AND OUTAGES
The Contractor shall commence work after notice to proceed. Work onsite may commence in May 2021 thru the remaining duration of the contract period.
The Contractor's employees shall not open, close or tamper with switches, valves or control devices for existing installed equipment. Only Government operating personnel will be authorized to open or close existing switches, valves and control devices to enable the Contractor to make connections or modifications to existing equipment. Work shall be coordinated and scheduled to reduce the "Outage" time of operating equipment or systems to a minimum. Work in the proximity of exposed energized equipment such as in the switchyard or work involving connections to existing energized or operating equipment or systems shall perform only under the Safe Clearance Procedures. The Contractor will be instructed by the Contracting Officer in the proper procedure for requesting clearances.
Only qualified supervisory personnel will be permitted to request clearances. Request for "Outage" shall be made by the Contractor to the Contracting Officer in each instance not less than 30-days in advance in order to coordinate outages with the dispatching agency. Scheduling of "Outage" will be subject to the approval of the Contracting Officer. The contractor shall assume and plan for single outages to complete the work.
1.19 GAS, VAPOR, FUME, DUST, SLURRY AND MIST CONTROL IN POWERHOUSE
Take all necessary measures to effect maximum control of all gases, vapors, fumes, dust, slurry and mists created by Contractor operations under this contract. To the maximum extent possible, remove all dust and dirt by vacuum cleaning and mopping, unless otherwise directed by the Contracting
DOCUMENT 00 73 00 Page 9
Officer. The required dust and debris control measures include but are not limited to the following:
a. Provision of exhaust ducts which discharge outside the powerhouse structure where mechanical ventilation is used. Comply with requirements of 29 CFR 1910.94 and 29 CFR 1926.57 for ventilation systems.
b. Controlled operation of power-driven tools.
c. Providing and removal of approved dust/fumes preventatives in areas that cannot be properly rendered free from excessive dusting by vacuum cleaning and mopping or other methods.
d. Vacuum cleaning and mopping (or other acceptable method) of spaces within the powerhouse where dust accumulates.
e. Only air, electrical, propane, or battery-driven equipment may be used inside the powerhouse.
PART 2 NOT USED
PART 3 NOT USED
-- End of Section --
DOCUMENT 00 73 00 Page 10
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
6/2000
PART 1 GENERAL
1.1 RETAINAGE OF PAYMENT
1.2 MEASUREMENT
1.2.1 Job Payment Items
1.3 BASE LINE ITEMS
1.3.1 CLIN 0001
1.3.2 CLIN 0002
1.3.3 CLIN 0003
1.4 OPTIONAL LINE ITEMS
1.4.1 CLIN 0004
SECTION 01 22 00 Page 1
SECTION 01 22 00
MEASUREMENT AND PAYMENT
6/2000
PART 1 GENERAL
The following measurement and payment paragraphs describe what constitutes full compensation for all work incidental to completion of the work under those terms. In the event any work is required by the specifications Sections or by the drawings and not specifically mentioned in the measurement and payment paragraphs, separate or direct payment will not be made and all costs thereof are incidental to and included in the contract prices and payments for all items listed in the price schedule. The word "provide" shall be understood to mean "furnish and install" when used in this Section or elsewhere in the technical Sections. In each instance, the contract price for an item shall constitute full compensation for furnishing all plant, labor, equipment, and materials, and for performing all operations required to complete the work included in the item as herein specified, or as otherwise approved.
1.1 RETAINAGE OF PAYMENT
Retainage in the amount of $10,000 will be withheld until all final submittals including Operations and Maintenance Manuals and as-built drawings have been approved by the Government.
1.2 MEASUREMENT
1.2.1 Job Payment Items
Payment items for the work of this Contract for which Contract job payments will be made are listed in the PRICING SCHEDULE, and described below.
Include all costs for items of work, which are not specifically mentioned to be included in a particular job item, in the listed job item most closely associated with the work involved. The job price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment; performing all associated Contractor quality control, environmental protection, commissioning, preparation of working as-built drawing redlines, O&M manuals, tests and reports, meeting safety requirements; and for performing all work required for which separate payment is not otherwise provided. Provide a schedule of values for job items with each payment request.
1.3 BASE LINE ITEMS
Payment for all work specified, shown or incidental to complete the work will be made as follows:
1.3.1 CLIN 0001
This CLIN will be measured for payment as a complete pay item (JOB).
Payment shall constitute full compensation for equipment, materials, and operations required to furnish four (4) complete sets of the LIQUID COPPER BASED PESTICIDE (CBP) DISTRIBUTION SYSTEM to control /
SECTION 01 22 00 Page 2 prevent zebra mussel infestation in four (4) of the 14" raw water intake piping serving various cooling systems in the powerhouse. See specification section 43 32 69 for further detail.
1.3.2 CLIN 0002
This CLIN will be measured for payment as a complete pay item (JOB). Price and payment shall be full compensation for all labor, equipment, materials, and operations required to install systems furnished by CLIN 0001 as indicated in specs, and drawings. This shall include but not limited to; on-site hot work required to install insertion type magnetic flowmeters and chemical injeciton ports, work required to install piping, tubing, pump skids, controls, electrical, and etc. and field testing for complete operational systems.
1.3.3 CLIN 0003
This CLIN will be measured for payment as a complete pay item (JOB). All re maining work for this item shall include but not be limited to mobilization and demobilization; general clean-up; and any other incidental and customarily performed work needed to complete work not covered by CLIN 0001 thru CLIN 0002.
1.4 OPTIONAL LINE ITEMS
Payment for all work specified, shown or incidental to complete the work will be made as follows:
1.4.1 CLIN 0004
This CLIN will be measured for payment as a complete pay item (JOB).
Payment shall constitute full compensation for all equipment, materials, and operations required to furnish extra materials listed in the specification section 43 32 69, paragraph 1.4 EXTRA MATERIALS.
SECTION 01 22 00 Page 3
SECTION 01 22 00 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
08/18, OMH 02/2019
PART 1 GENERAL
1.1 SUMMARY
1.1.1 Submittal Information
1.2 SUBMITTALS
1.2.1 Action Codes
1.2.1.1 Contractor Action Codes
1.2.1.2 Government Reviewer Designations
1.3 SUBMITTAL CLASSIFICATION
1.3.1 Government Approved (G)
1.3.2 For Information Only
1.4 PREPARATION
1.4.1 Transmittal Form
1.4.2 Source Drawings for Shop Drawings
1.4.2.1 Source Drawings
1.4.2.2 Terms and Conditions
1.4.3 Electronic File Format
1.5 QUANTITY OF SUBMITTALS
1.5.1 Number of SD-04 Samples
1.6 INFORMATION ONLY SUBMITTALS
1.7 PROJECT SUBMITTAL REGISTER
1.7.1 Submittal Management
1.7.2 Preconstruction Use of Submittal Register
1.7.3 Contractor Use of Submittal Register
1.7.4 Approving Authority Use of Submittal Register
1.7.5 Action Codes
1.7.6 Delivery of Copies
1.8 VARIATIONS
1.8.1 Considering Variations
1.8.2 Proposing Variations
1.8.3 Warranting that Variations are Compatible
1.8.4 Review Schedule Extension
1.9 SCHEDULING
1.10 GOVERNMENT APPROVING AUTHORITY
1.11 DISAPPROVED SUBMITTALS
1.12 APPROVED SUBMITTALS
1.13 APPROVED SAMPLES
1.14 WITHHOLDING OF PAYMENT
PART 2 PRODUCTS
PART 3 EXECUTION
ATTACHMENTS:
SECTION 01 33 00 Page 1
ENG Form 4025-R
Project Submittal Register
SECTION 01 33 00 Page 2
SECTION 01 33 00
SUBMITTAL PROCEDURES
08/18, OMH 02/2019
PART 1 GENERAL
1.1 SUMMARY
1.1.1 Submittal Information
The Contractor is responsible for total management of their work including, but not limited to, approval, scheduling, control, certification of all submittals and compliance with all applicable Buy-American and Trade Agreement clauses. The submittal management system provided in these specifications is intended to be a complete system for the Contractor to use to control the quality of materials, equipment and workmanship provided by manufacturers, fabricators, suppliers and subcontractors. Review each submittal for contract compliance. Compliance with all applicable Buy American and Trade Agreement Clauses is to be included in this review. The Contractor must provide the country of origin on ENG Form 4025 for each item submitted. The Submittal Register (ENG Form 4288) will be utilized to log and monitor all submittal activities.
The Contracting Officer may request submittals, in addition to those specified, when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having any designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Submittal Register; G[-[RO][AO][PO]]
SECTION 01 33 00 Page 3
1.2.1 Action Codes
1.2.1.1 Contractor Action Codes
DESIGN BID BUILD SUBMITTALS
Submittal Classifications shown in UFGS Sections
Submittal Classification
Corresponding SpecsIntact
Submittal Register Code which is populated in the SI Submittal Register.
Software
Limitations: (The software shows one character delineation in the
SpecsIntact Submittal Register)
RMS – The following Submittal
Classifications are populated in RMS when the SpecsIntact
Submittal Data File is pulled into RMS)
G Submittal requires Government Approval
G GA
BLANK Submittal is For Information Only
(FIO)
BLANK FIO
1.2.1.2 Government Reviewer Designations
Following the Submittal Classification designation "G", the following reviewer designations may be included:
RO - Resident Office AO - Area Office DO - District Office
AE - Architect Engineer
Additional information will be provided at the pre-design and/or pre-construction conference.
Corps of Engineers, Omaha District Office for "DO" reviewer designations, submittals will be coordinated through:
Michael Hebert U.S. Army Corps of Engineers Omaha District Attn: CENWO-CDS-T 1616 Capitol Ave Omaha, NE 68102-4901 E-mail: CENWO.ConstructionSubmittal@usace.army.mil
SECTION 01 33 00 Page 4
1.3 SUBMITTAL CLASSIFICATION
1.3.1 Government Approved (G)
Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Government.
Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, submittals are considered to be "shop drawings."
1.3.2 For Information Only
Submittals not requiring Government approval will be for information only.
Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are not considered to be "shop drawings."
1.4 PREPARATION
1.4.1 Transmittal Form
Use the ENG Form 4025-R transmittal form for submitting both Government-approved and information-only submittals. Submit in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. If there are multiple Item numbers listed on a particular ENG Form 4025-R submittal, combine all submitted items for review into a single Adobe file with bookmarks (for ease of review). Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
1.4.2 Source Drawings for Shop Drawings
1.4.2.1 Source Drawings
The entire set of source drawing files (DWG or DGN) will not be provided to the Contractor. Request the specific Drawing Number for the preparation of shop drawings. Only those drawings requested to prepare shop drawings will be provided. These drawings are provided only after award.
1.4.2.2 Terms and Conditions
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse is at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor must make no claim, and waives to the fullest extent permitted by law any claim or cause of action of any nature against the Government, its agents, or its subconsultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities, or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic source drawing files are not construction documents.
Differences may exist between the source drawing files and the corresponding construction documents. The Government makes no
SECTION 01 33 00 Page 5 representation regarding the accuracy or completeness of the electronic source drawing files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. The Contractor is responsible for determining if any conflict exists. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished source drawing files, the signed and sealed construction documents govern. Use of these source drawing files does not relieve the Contractor of the duty to fully comply with the contract documents, including and without limitation the need to check, confirm and coordinate the work of all contractors for the project.
If the Contractor uses, duplicates or modifies these electronic source drawing files for use in producing construction data related to this contract, remove all previous indication of ownership (seals, logos, signatures, initials and dates).
1.4.3 Electronic File Format
Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Name the electronic submittal file specifically according to its contents, and coordinate the file naming convention with the Contracting Officer. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. All documents must make use of optical character recognition (OCR) routines to make text searchable and selectable, so that the text can be copied. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature.
E-mail electronic submittal documents smaller than 10MB to an e-mail address as directed by the Contracting Officer, unless directed otherwise by COR. Provide electronic documents over 10 MB on an optical disc or through an electronic file sharing system, such as secure ftp site or Government web application located at the following website:
https://safe.arl.army.mil/. Use of the Government web application must be initiated by the Government, unless Contractor has a Government CAC card.
The Government may allow the AMRDEC SAFE Web Application located at the following website: https://safe.amrdec.army.mil/safe/. Both Government web applications restrict the number of days files are available to download.
1.5 QUANTITY OF SUBMITTALS
Submittals are to be transmitted electronically, unless directed otherwise.
1.5.1 Number of SD-04 Samples
a. Submit two samples, or two sets of samples showing the range of variation, of each required item. One approved sample or set of samples will be retained by the approving authority and one will be returned to the Contractor.
b. Submit one sample panel or provide one sample installation where directed. Include components listed in the technical section or as directed.
c. Submit one sample installation, where directed.
SECTION 01 33 00 Page 6
d. Submit one sample of nonsolid materials.
1.6 INFORMATION ONLY SUBMITTALS
Submittals without an action code must be certified by the QC manager and submitted to the Contracting Officer for information-only. Approval of the Contracting Officer is not required on information only submittals. The Contracting Officer will mark "receipt acknowledged" on submittals for information and will return only the transmittal cover sheet to the Contractor. Normally, submittals for information only will not be returned. However, the Government reserves the right to return unsatisfactory submittals and require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;
and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.7 PROJECT SUBMITTAL REGISTER
A sample Project Submittal Register showing submittals required by the specifications is attached to this section as "Project Submittal Register."
1.7.1 Submittal Management
Prepare and maintain a submittal register, as the work progresses. Do not change data that is output in columns (c), (d), (e), and (f) as delivered by Government; retain data that is output in columns (a), (g), (h), and (i) as approved. As an attachment, provide a submittal register showing items of equipment and materials for which submittals are required by the specifications. This list may not be all-inclusive and additional submittals may be required.
Column (c): Lists specification section in which submittal is required.
Column (d): Lists each submittal description (SD Number. and type, e.g., SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in each specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting the project requirements.
Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns and all dates on which submittals are received by and returned by the Government.
1.7.2 Preconstruction Use of Submittal Register
Submit the submittal register as an electronic database, using the submittal management program furnished to Contractor, unless directed otherwise by COR. Include the QC plan and the project schedule. Verify
SECTION 01 33 00 Page 7 that all submittals required for the project are listed and add missing submittals. Coordinate and complete the following fields on the register database submitted with the QC plan and the project schedule:
Column (a) Activity Number: Activity number from the project schedule.
Column (g) Contractor Submit Date: Scheduled date for the approving authority to receive submittals.
Column (h) Contractor Approval Date: Date that Contractor needs approval of submittal.
Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.
1.7.3 Contractor Use of Submittal Register
Update the following fields in the Government-furnished submittal register program or equivalent fields in the program used by the Contractor with each submittal throughout the contract.
Column (b) Transmittal Number: List of consecutive, Contractor-assigned numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) Date submittal transmitted.
Column (q) Date approval was received.
1.7.4 Approving Authority Use of Submittal Register
Update the following fields:
Column (b) Transmittal Number: List of consecutive, Contractor-assigned numbers.
Column (l) Date submittal was received.
Column (m) through (p) Dates of review actions.
Column (q) Date of return to Contractor.
1.7.5 Action Codes
See paragraph Action Codes above.
1.7.6 Delivery of Copies
Submit an updated electronic copy of the submittal register to the Contracting Officer with each invoice request, unless a paper copy is requested by the Contracting Officer. Provide an updated Submittal Register monthly regardless of whether an invoice is submitted.
1.8 VARIATIONS
Variations from contract requirements require Contracting Officer approval
SECTION 01 33 00 Page 8 pursuant to contract Clause FAR 52.236-21 Specifications and Drawings for Construction, and will be considered where advantageous to the Government.
1.8.1 Considering Variations
Discussion of variations with the Contracting Officer before submission will help ensure that functional and quality requirements are met and minimize rejections and resubmittals. When contemplating a variation that results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
Specifically point out variations from contract requirements in transmittal letters. Failure to point out variations may cause the Government to require rejection and removal of such work at no additional cost to the Government.
1.8.2 Proposing Variations
When proposing variations, deliver a written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government. Include the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.
Clearly mark the proposed variation in all documentation.
Check the column "variation" of ENG Form 4025 for submittals that include variations proposed by the Contractor. Set forth in writing the reason for any variations and note such variations on the submittal. The Government reserves the right to rescind inadvertent approval of submittals containing unnoted variations.
1.8.3 Warranting that Variations are Compatible
When delivering a variation for approval, the Contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.8.4 Review Schedule Extension
In addition to the normal submittal review period, a period of 14 calendar days will be allowed for the Government to consider submittals with variations.
1.9 SCHEDULING
Schedule and submit concurrently product data and shop drawings covering component items forming a system or items that are interrelated. Submit pertinent certifications at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.
Contracting Officer review will be completed within 20 calendar days after the date of submission.
The Government review period for each construction submittal does not begin until the submittal is delivered via RMS CM. Contract compliance for all submittals are the Contractor's responsibility. Government acceptance or
SECTION 01 33 00 Page 9 receipt acknowledged does not remove this responsibility for contract compliance on any construction submittal.
1.10 GOVERNMENT APPROVING AUTHORITY
Upon completion of review of submittals requiring Government approval, stamp and date submittals. An electronic copy of the submittal will be retained by the Contracting Officer and an electronic copy of the submittal will be returned to the Contractor. The Government may process submittals in the RMS CM System.
1.11 DISAPPROVED SUBMITTALS
Make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications, give notice to the Contracting Officer as required under the FAR clause titled CHANGES. The Contractor is responsible for the dimensions and design of connection details and the construction of work. Failure to point out variations may cause the Government to require rejection and removal of such work at the Contractor's expense.
If changes are necessary to submittals, make such revisions and resubmit in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.12 APPROVED SUBMITTALS
The Contracting Officer's approval of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing, and other information are satisfactory.
Approval or acceptance by the Government for a submittal does not relieve the Contractor of the responsibility for meeting the contract requirements or for any error that may exist, because under the Quality Control (QC) requirements of this contract, the Contractor is responsible for ensuring information contained with in each submittal accurately conforms with the requirements of the contract documents.
After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.13 APPROVED SAMPLES
Approval of a sample is only for the characteristics or use named in such approval and is not be construed to change or modify any contract requirements. Before submitting samples, provide assurance that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.
Match the approved samples for materials and equipment incorporated in the work. If requested, approved samples, including those that may be damaged in testing, will be returned to the Contractor, at its expense, upon
SECTION 01 33 00 Page 10 completion of the contract. Unapproved samples will also be returned to the Contractor at its expense, if so requested.
Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make as that material. The Government reserves the right to disapprove any material or equipment that has previously proved unsatisfactory in service.
Samples of various materials or equipment delivered on the site or in place may be taken by the Contracting Officer for testing. Samples failing to meet contract requirements will automatically void previous approvals.
Replace such materials or equipment to meet contract requirements.
1.14 WITHHOLDING OF PAYMENT
Payment for materials incorporated in the work will not be made if required approvals have not been obtained.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 33 00 Page 11
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 3 PAGES
Zebra Mussel Mitigation System, Fort Randall Dam, SD
00 73 00 SD-01 Preconstruction Submittals 1.16AT Level I Training Sign In
Sheets G POSecurity Personnel List
1.16iWATCH and/or CorpsWatch Training Sign In Sheets
1.16OPSEC Training Sign In Sheets 01 33 00 SD-01 Preconstruction Submittals
1.7 G [RO][Submittal Register
01 35 26 SD-01 Preconstruction Submittals
1.7 G POAccident…