The purpose of this amendment is to incorporate the attached eight (8) drawings into the solicitation. The proposal due date remains 20 August 2016 before 5 00pm CST. Except

View the file

Other files for this federal contract opportunity

Other files attached to Hominy Water Line Extension, newest first.
File Type Posted
Hominy_WLX_Amendment_002.pdf PDF
246-2016-Q-0038 _Hominy_WLX.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HOMINY WLX Drawings.pdf

1
2
3
4
5
6
7
8
Hominy WLX SOW.pdf
- Project will consist of 3,300 feet of 4” SDR 21 PVC waterline. The line will be connected to existing water system and include a 4-inch gate valve at the connection.
- Three 4.5 inch hydrants will be placed along the line according to the plans with a bury depth of 4 feet. A 4-inch gate valve will precede each hydrant. The hydrants will be purchased by the City of Hominy.
- Three air relief valves will be placed on the line at locations specified in the plans.
- 1200 feet of 1” PEX water service line will be connected to the 4” PVC line and ran to serve 4 homes. Each service line will include a water meter and box, pressure reducing valve, and connection to the home.
- Two of the service lines will each require approximately 30 feet of boring, 60 feet in total, under Stallard Road for a 2” HDPE sleeve.
- All work performed will meet the requirements of the attached technical specifications.
Hominy WLX Engineer's Estimate.pdf
Project
Stamped Specs Hominy WLX.pdf
PAWNEE OEH&E FIELD OFFICE
PART 1 GENERAL
A. Install approximately 3273 feet of 4-inch SDR 21 PVC water line, 1170 feet of 1-inch pex pipe, and appurtenances to serve the four homes.
B. Rural Water District: Hominy PWA
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
END OF SECTION
PART 1 GENERAL
1.02 PAYMENT
END OF SECTION
PART 1 GENERAL
PART 3 EXECUTION
Part 1 GENERAL
A. National Standards Organizations & Associations
B. Federal Agencies
C. State Agencies
END OF SECTION
American Association of State Highway and Transportation Officials (AASHTO)
American Water Works Association AWWA
National Electric Code (NEC)
National Electrical Manufacturer’s Association (NEMA)
Northbrook, IL 60062
Oklahoma Department of Environmental Quality
707 N. Robinson
ASTM D2321
ASTM D2487
PART 1 GENERAL
END OF SECTION
PART 1 GENERAL
A. Section includes information on closeout procedures and site cleanup.
END OF SECTION
PART 1 GENERAL
PART 2 PRODUCTS (not used)
PART 3 EXECUTION
END OF SECTION
PART 1 GENERAL
PART 2 PRODUCTS
PART 3 EXECUTION
END OF SECTION
PART 1 GENERAL
PART 2 PRODUCTS (Not applicable)
PART 3 EXECUTION
END OF SECTION
PART 1 - GENERAL
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
END OF SECTION
PART 1 GENERAL
1. Trenching necessary for the construction of the facilities as indicated on the drawings including, but not limited:
a. Water mains and service lines.
A. Barricades and lights
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION
F. Road, Driveway, and Sidewalk Crossing:
END OF SECTION
PART 1 GENERAL
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION
END OF SECTION
PART 1 GENERAL
1. Backfill necessary for the construction of the facilities as indicated on the plans including, but not limited to water mains and service lines, sewer mains and service lines, concrete manholes, septic tanks, and other structures.
PART 2 PRODUCTS
PART 3 EXECUTION
D. Road, Driveway, and Sidewalk Crossing:
END OF SECTION
PART 1 GENERAL
1. Compaction of excavations, trenching, and backfill necessary for the construction of the facilities as indicated on the drawings including, but not limited to water mains and service lines, sewer mains and service lines, concrete manholes, septic t...
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
C. Road, Driveway, and Sidewalk Crossing:
END OF SECTION
PART 1 GENERAL
A. Material Submitals:
1. Conform to the Section 01330.0000 – Submittal Procedures.
B. Seed mixture.
PART 2 PRODUCTS
A. Prairie (native) hay, not more than 2 years old and free of noxious weeds.
PART 3 EXECUTION
PART 1 - GENERAL
PART 2 - PRODUCTS
PART 3 - EXECUTION
A. Directional drill and install pipe at the locations and of sizes shown on the drawings or as directed by the Project Engineer.
END OF SECTION
L = (N*D*P1/2)/7400L = Allowable Leakage (gph)
PART 1 GENERAL
B. ANSI/AWWA C110/A21.10 – Ductile Iron and Gray Iron Fittings, 3 Inch Through 48 Inch, for Water and Other Liquids.
1.04 SUBMITTALS
PART 2 PRODUCTS
PART 3 EXECUTION