23Q1044 Siemens Voltage Regulator Justification for Other than Full and Open Competition 1.docx
DOCX document 30 KB Posted
- Attached to
- SIEMENS SINGLE PHASE VOLTAGE REGULATORS Federal contract opportunity
- Solicitation number
- M6700123Q1044
- Issued by
- United States Marine Corps
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 23Q1044 Pre-Solicitation Notice (SAM).docx | DOCX document | |
| 23Q1044 Pre-Solicitation Strategy Single Phase Voltage Regulator (SAM).docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Justification for Other than Full and Open Competition – FAR Part 13 Acquisitions under the SAT
MEMORANDUM TO THE FILE
Subj: JUSTIFICATION FOR USE OF OTHER THAN FULL AND OPEN COMPETITION
FOR A FAR PART 13 ACQUISITION UNDER THE SIMPLIFIED ACQUISITION THRESHOLD
I. BACKGROUND:
1. FAR 13.106-1(b)(1)(i) states for purchases not exceeding the simplified acquisition threshold, Contracting Officers may solicit from one source if the Contracting Officer determines that the circumstances of the contract action deem only one source reasonably available (e.g., urgency, exclusive licensing agreements, brand-name or industrial mobilization).
2. As required by FAR 13.106-3(b)(3)(i), this memorandum explains the absence of competition for this acquisition, as only one source will be solicited for this requirement (or for a portion of the requirement) and the requirement (or portion of the requirement to be sole-sourced) is not expected to exceed the simplified acquisition threshold.
II. DESCRIPTION OF ITEM OR SERVICE:
Siemens Voltage Regulator, JFR Single Phase rated at 7620 VOLTS 546 AMPS 95KV BIL 55/65C 60HZ ANSI Type B Class ONAN.
Quantity 6 @ $40,699.50 each
III. THE DETERMINATION FOR USE OF OTHER THAN FULL AND OPEN COMPETITION IS BASED ON THE FOLLOWING (select all that apply):
A. ___ ONLY ONE RESPONSIBLE SOURCE (select all that apply):
1. ___ RESTRICTIVE RIGHTS. The source has established proprietary rights, limited rights in data, patent rights, copyrights or secret processes in the item or service required.
2. ___ EXCLUSIVE LICENSING AGREEMENTS. The item or service is only available from the Original Equipment Manufacturer (OEM), or there is only one authorized distributor or technical representative for the OEM.
3. ___ OTHER REASONS.
B. X BRAND NAME
Item required must be a brand name, product, or feature of a product, particular to one manufacturer. There are approximately (54) of these Siemens Single Phase Voltage Regulator’s currently in service. The Base (18) feeder lines running from power substation throughout Marine Corps Camp Lejeune and each (1) of these lines required a total of (regulators) wired together form a bank. Since these regulators are wired together to form a bank, the same manufacturer (Siemens) must be used. Different manufacturers cannot be wired together. The high voltage shop has the required tool and computer software to test and monitor the performance of the regulators. If another manufacturer is purchased, it would be incompatible with the existing software and equipment. The purpose of these regulators is to monitor and regulate the output voltage coming from the substation.
C. ___URGENT AND COMPELLING. The supplies or services are of such unusual and compelling urgency that the Government would be seriously injured unless the agency is permitted to limit the number of sources from which it solicits bids or proposals. Urgent requirements are supplies or services that will result in a work stoppage or are mission critical and the routine processing time would result in injury to the Government. The determination that the procurement for the above item/service is an urgent and compelling requirement is based on the following:
1. Date on which the requirement was first identified:
2. Required delivery date/period of performance:
3. Explanation of why delivery/commencement of services by the date mentioned above is required:
V. CERTIFICATIONS:
A. Technical / Requirements Certification: I certify that the facts and representation under my cognizance which are included in this justification are complete and accurate to the best of my knowledge and belief.
| ____________________ | _________________________ | _________ | ||
| Signature | Name (Printed) / Phone # | Date |
B. Contracting Officer Certification: I certify that this justification is accurate and complete to the best of my knowledge and belief.
| ____________________ | _________________________ | _________ | ||
| Signature | Name (Printed) / Phone # | Date |
V 1.4 (03 October 2022)