Questions_and_Responses_02222019.docx
DOCX document 14 KB Posted
- Attached to
- OPTION - Annual Maintenance Service Plan for Powerware and Battery Systems Federal contract opportunity
- Solicitation number
- 20111006
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| UPS_Information.pdf | ||
| Questions_and_Responses_02202019.docx | DOCX document | |
| UPS_SOW_AMOC_2152019.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Responses: 02/22/2019
1. VENDOR QUESTION
The past performance questionnaire for this solicitation has a fill-in for ‘Contract Number’. Do we place the solicitation number 20111006 in this fill-in? Or do we place the reference to other contracts we have supported?
GOVERNMENT RESPONSE
Please reference the contract number from the other contracts you have performed.
2. VENDOR QUESTION
Do we need a current SAM registration prior to the bid due date of 2/25/19? Or only before bid is awarded?
GOVERNMENT RESPONSE
Vendors are required to be registered in the System for Award Management (SAM) in order to receive an award.
3. VENDOR QUESTION
Do not see anything about the Prevailing Wage rate – is that a requirement?
GOVERNMENT RESPONSE
There is no prevailing wage that has been identified for this requirement. This is for a semi-annual service.
4. VENDOR QUESTION
Pricing is for maintenance work; not any battery or other parts replacements (unless under warrantee), correct?
GOVERNMENT RESPONSE
Correct. If AMOC has a bad battery that needs replacing then the Government will purchase the battery. However, per the Statement of Work (SOW) “In the event a battery under warranty needs to be replaced, the contractor shall perform all functions necessary to communicate with the manufacturer, remove and exchange the old battery, and install a new battery.” The battery would be provided by the Government.
5. VENDOR QUESTION
Can an extension be given until 2/27/2019?
GOVERNMENT RESPONSE
No extensions will be given at this time.
**Additional information about CBP’s Eaton UPS’s was also posted to the solicitation.**