SF-30 Amendment 0002.pdf

PDF 178 KB Posted

Attached to
Renovation at America House Compound Federal contract opportunity
Solicitation number
19UP3025Q0008
Issued by
Department of State

About this file

This document is a Standard Form 30 Amendment (Amendment 0002) for Solicitation 19UP3025Q0008, issued by the U.S. Embassy Kyiv to modify the original Request for Quotations for renovation work at the America House Compound. The amendment specifically revises the dimensions and scope of work for fire escape landing repairs and awning construction, providing detailed measurements for various areas including the CAC Roof, Fire Escape Landing Area, Utility Building Roof, CAC Floors and Walls, and UB Floors and Walls.

The key modifications include updating the contractor's responsibilities to manufacture, deliver, and install a 95 m² awning, reconstruct 4 storm drainage pipes, perform 88 m² of landing repair and waterproofing, and repaint metal fencing and stairs. The amended attachment provides precise measurements for each area of work, such as roof construction, water drainage systems, metal fencing, stairs, and interior/exterior wall and floor areas, emphasizing that it is the contractor's responsibility to verify all measurements and dimensions.

View the file

Other files for this federal contract opportunity

Other files attached to Renovation at America House Compound, newest first.
File Type Posted
Questions and Answers 19UP3025Q0008.pdf PDF
Site-Visit Minutes 19UP3025Q0008.pdf PDF
SF-30 Amendment 0001.pdf PDF
SF1442_RFQ19UP3025Q0008 Renovation AH.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

PAGE OF PAGES

1 3

2. AMENDMENT/MODIFICATION NO.

3. EFFECTIVE DATE

May 27, 2025

4. REQUISITION/PURCHASE REQ. NO.

PR15275916

5. PROJECT NO. (If applicable)

6. ISSUED BY CODE

7. ADMINISTERED BY (If other than Item 6)

CODE

U.S. Embassy Kyiv

4 Igor Sikorsky St.

04112, Kyiv, Ukraine

8. NAME AND ADDRESS OF CONTRACTOR (NO., street,city,county,State,and ZIP Code)

X

9a. AMENDMENT OF SOLICITATION NO.

19UP3025Q0008

9b. DATED (SEE ITEM 11)

May 09, 2025

10a. MODIFICATION OF CONTRACT/ORDER NO.

10b. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

[X] The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

[ ] is extended, [X] is not extended

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers.

FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF

OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b)

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor [ ] is not, [ ] is required to sign this document and return __ copy to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

This Amendment 0002 was issued to correct dimensions of areas for fire escape landing repairs and awning construction in the Attachment #A – Scope of Work of the Request for Quotations. Accordingly, SEE NEXT PAGES

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

16A. NAME OF CONTRACTING OFFICER

Hunter Crowder

15B. NAME OF CONTRACTOR/OFFEROR

BY

(Signature of person authorized to sign)

15C.DATE

SIGNED

16B. UNITED STATES OF AMERICA

BY

(Signature of Contracting Officer)

16C.DATE SIGNED

NSN 7540-01-152-8070 Standard Form 30 (revised 10/83)

Previous edition unusable Prescribed by GSA FAR (48 CFR) 53.243

19UP3025Q0008- 0002

1. In Attachment A – Scope of Work, paragraph 2.3 - Fire Escape Landing Repairs and

Awning Construction, subparagraph 2.3.1 is hereby revised to read as follows:

2.3.1 Contractor will:

- Manufacture, deliver and install an awning – 95 m2

- Reconstruct storm drainage pipes due to awning structure – 4 pieces

- Perform landings repair and waterproof works - 88 m2

- Repaint metal fencing and stairs – see identified areas in the ATTACHMENT 1.

2. In Attachment A – Scope of Work, paragraph 3.0- Attachments, Attachment 1- List of locations and areas to be repaired is hereby revised to read as follows:

ATTACHMENT 1

List of locations and areas to be repaired

It is the contractor’s responsibility to verify all measurements and dimensions.

- CAC Roof o Roof construction area - 40 m² o Water Drainage system – 4 points o Bituminous shingles - 40 m² o CAC Translucent Canopy &Metal Support areas - 18 m²

- Fire Escape Landing Area o Awning installation area - 95 m² o Water Drainage system – 4 points o Landing floor surface – 88 m² o Metal fencing – 47 linear meters o Metal stairs – 44 m² + 17 m² metal stair support o Stair’s handrails – 36 linear meters o Gates – 22 m²

- Utility Building Roof o Roof cleaning area – 72 m² o Water Drainage system – 4 points

- CAC Floors and Walls area o Floor area – 13.5 m² o Ceiling area – 42.5 m² o Interior walls area – 102 m² o Exterior walls area – 98 m² o Interior walls tiled area – 10 m² o Porch tiled area – 4.5 m²

19UP3025Q0008- 0002

- UB Floors and Walls area o Interior walls – 80 m² o Exterior walls – 90 m² o Ceiling – 72 m² o Restroom floor area - 2 m² o Restroom walls tiled area – 12 m² o Restroom ceiling area – 2 m²