Secondary Effluent Pumps Scope of work 2.1.24.pdf
PDF 63 KB Posted
- Attached to
- Rehab SE Pumps Federal contract opportunity
- Solicitation number
- 191BWC24R0007
About this file
This combined synopsis/solicitation from the International Boundary and Water Commission seeks quotes for the repair of three Peerless pumps at the Nogales International Wastewater Treatment Plant in Rio Rico, Arizona. The solicitation requires the refurbishment, replacement, or retooling of internal line shafts and any ancillary parts to restore proper functionality to the pumps. Quotes are due by February 26, 2024 and must be submitted to seone.jones@ibwc.gov. The award will be made to the lowest price technically acceptable offeror. The scope of work details the specific pumps requiring repair by serial number and outlines the preparation, coating, and sealing work required. Offerors must complete the provision at 52.212-3 and include their Unique Entity Identifier with any response.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| OM-31-11200 (002)_Redacted.pdf | ||
| 191BWC24R0007 0001.pdf | ||
| 191BWC24R0007.pdf | ||
| Secondary Effluent Pumps Scope of work.pdf | ||
| Diagram.pdf | ||
| CLIN Structure - SE Pumps.docx | DOCX document | |
| WD 2015-5841 Rev. 23.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNITED STATES INTERNATIONAL BOUNDARY AND WATER COMMISSION
(USIBWC)
NOGALES FIELD OFFICE
SCOPE OF WORK FOR
REHAB THREE (3) 10 STAGE VERTICAL LINE SHAFT PUMPS
WITH WATER LUBRICATED SHAFTS AND MECHANICAL SEALS
1. GENERAL
1.1. BACKGROUND
The US International Boundary and Water Commission (USIBWC) operates and maintains the Nogales International Wastewater Treatment Plant (NIWTP) in Rio Rico, Arizona. The NIWTP currently treats approximately 1 7 million gallons per day of raw sewage entering from Nogales, Mexico and Nogales, Arizona. This creates a flow stream with a need for solids removal from the treatment plant on a constant and continuous basis.
1.2. LOCATION
The USIBWC NIWTP is in Rio Rico, Santa Cruz County,just north of Nogales, Arizona.
The treatment plant is situated between the Santa Cruz River that is to the east and 1-19 to the west. There is a railroad track between the highway and the treatment plant.
1.3 SITE CONDITIONS:
Site conditions consist of varying types of weather that can range from one extreme to another. There is also the potential for exposure to wildlife such as javelinas, coyotes, poisonous snakes, and other forms of wildlife.
1.4. SCOPE OF WORK
Three (3) Peerless Pumps 7LB 10 stage water lubricated vertical line shaft pumps.
Serial Numbers are as follows: 739582 A-5, 723570 A-1, 723570 B-1. Pump bowl assemblies will be government provided; Two old pumps needs to be disassembled (one is disassembled) and reassembled using the new bowl pieces provided per manufactures specification. Internal line shafts need refurbishing, replacement, or retooling as necessary to restore correct functionality, and any ancillary parts will be made/refitted to restore correct functionality. These assemblies will be epoxy coated painted at all mechanical flanged joints. Pump housing will be prepared to bare metal and epoxy coated (painted). Mechanical seals and pump shaft bearings are recommended to be O.E.M. Work will be conducted off site. Pumps are already removed from service but bidder will need to package/palletized. Bidder will be responsible for pickup and delivery of the pumps.
1.5. ACCESS TO SITE:
NIWWTP is a restricted Facility; and access to the facility shall be in accordance with existing USIBWC procedures.
1.6. WORKING HOURS:
Working hours shall be from 7:30 am to 4:00 pm local time, Sunday through Saturday except for Federal holidays.
File details come from the government source that posted it. Updated .