About this file

This document is a solicitation for a construction project to install structural shoring at the food service facility of the Federal Correctional Institution in Big Spring, Texas. The solicitation is being conducted by the Department of Justice Bureau of Prisons Field Acquisition Office. Offerors must provide all materials, labor, and equipment to complete the project in accordance with the specifications by a completion date of 217 calendar days after receiving notice to proceed. Bids are due on August 2, 2023 by 1:30pm Central Time. The solicitation includes provisions for bonds, insurance requirements, progress meetings, submissions, site access, and other standard contract administration terms.

View the file

Other files for this federal contract opportunity

Other files attached to FCI Big Spring- Install Structural Shoring Food Service, newest first.
File Type Posted
Bid Abstract.pdf PDF
Amendment 00003- Questions and Responses.pdf PDF
Amendment 00002- Bid Extension.pdf PDF
Amendment 01.pdf PDF
Instruction to Bidders.pdf PDF
WD TX2023-0156.pdf PDF
Criminal History Check Form.pdf PDF
SF-24 Bid Bond Form.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

15BFA023B00000018 Page 1 of 54

SOLICITATION,OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NUMBER

15BFA023B00000018

X SEALED BID (IFB)

INVITATION FOR BID

NEGOTIATED (RFP)

REQUEST FOR PROPOSAL

2. TYPE OF SOLICITATION 3. DATE ISSUED

06/22/2023

PAGE OF PAGES

1 54

IMPORTANT -The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER

15B50323PR000238

6. PROJECT NUMBER

23Z5AP5

CODE BFAO

Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, TX 75051

7. ISSUED BY

Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, TX 75051

Patrick Ford

8. ADDRESS OFFER TO

9. FOR

INFORMATION CALL:

a. NAME

Patrick Ford pford@bop.gov

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

202-913-1665

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

The selected contractor shall provide all materials, labor, and equipment to complete the project Install Structural Shoring Food Service at the Federal Correctional Institution located in Big Spring, TX in accordance with the attached Specifications and Drawings. PLEASE

COMPLETE THE FOLLOWING ITEMS:

UNIQUE ENTITY IDENTIFIER (FORMERLY DUNS):_____________________________

TAX IDENTIFICATION NUMBER: ____________________________

CAGE CODE:________________________________

CONTRACTOR EMAIL:_______________________________

11. The Contractor shall begin performance within calendar days and complete it within calendar days after receiving10 217 award, X notice to proceed. This performance period is X mandatory negotiable. (See __________________________.)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12b).

X YES NO

12b. CALENDAR DAYS

Sealed offers in original and copies to perform the work required are due at the place specified in item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

13:30US/

Central a.

08/02/2023

b. An offer guarantee X is, is not required.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.c.

90d. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) bop37133 Highlight

15BFA023B00000018 Page 2 of 54

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

CODE FACILITY CODE

The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ___________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

17.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified) 27

ITEM

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE

UNITED STATES CODE AT

26. ADMINISTERED BY 15B503

Federal Bureau of Prisons FCI Big Spring 1900 Simler Ave Big Spring, TX 79720

Federal Bureau of Prisons FCI Big Spring 1900 Simler Ave Big Spring, TX 79720

27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return __________ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

X 29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a.NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

Patrick R Ford

31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA

BY

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

bop37133 Highlight bop37133 Highlight bop37133 Highlight bop37133 Highlight bop37133 Highlight

15BFA023B00000018 Page 3 of 54

Table of Contents

Section Description Page Number

1 Solicitation, Offer and Award 2 Commodity or Services Schedule 3 Special Contract Requirements

FAO-0001 Bonds FAO-0002 Magnitude FAO-0003 Required Insurance FAO-0004 Pre-Construction Conference FAO-0005 Submittals FAO-0006 Contractor Use of Premises FAO-0007 Payment Services FAO-0008 Request for Final Inspection FAO-0009(a) Construction Contract Security FAO-0010 Assignment of Contract Administration Office and Functions FAO-0011 Schedule of Values FAO-0012 Progress Meetings FAO-0013 Contract Closeout Procedures (for construction contracts exceeding $150,000)

4 Contract Clauses 52.246-12 Inspection of Construction (Aug 1996) 52.236-15 Schedules for Construction Contracts (Apr 1984) 52.242-14 Suspension of Work (Apr 1984) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (Nov 2021) 52.202-1 Definitions (Jun 2020) 52.203-3 Gratuities (Apr 1984) 52.203-5 Covenant Against Contingent Fees (May 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020) 52.203-7 Anti-Kickback Procedures (Jun 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (May 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014) 52.203-12 Limitation On Payments to Influence Certain Federal Transactions (Jun 2020) 52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights (Jun 2020) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (May 2011) 52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020) 52.204-13 System for Award Management Maintenance (Oct 2018) 52.204-14 Service Contract Reporting Requirements (Oct 2016) 52.204-18 Commercial and Government Entity Code Maintenance (Aug 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Nov 2021) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (Oct 2018) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015) 52.219-6 Notice of Total Small Business Set-Aside (Nov 2020) 52.219-8 Utilization of Small Business Concerns (Oct 2022) 52.219-28 Post-Award Small Business Program Rerepresentation (Mar 2023) 52.219-14 Limitations on Subcontracting (Oct 2022) 52.222-1 Notice to the Government of Labor Disputes (Feb 1997) 52.222-3 Convict Labor (June 2003) 52.222-4 Contract Work Hours and Safety Standards--Overtime Compensation (May 2018)

15BFA023B00000018 Page 4 of 54

52.222-6 Construction Wage Rate Requirements (Aug 2018) 52.222-7 Withholding of Funds (May 2014) 52.222-8 Payrolls and Basic Records (Jul 2021) 52.222-9 Apprentices and Trainees (July 2005) 52.222-10 Compliance with Copeland Act Requirements (Feb 1988) 52.222-11 Subcontracts (Labor Standards) (May 2014) 52.222-12 Contract Termination - Debarment (May 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014) 52.222-14 Disputes Concerning Labor Standards (Feb 1988) 52.222-15 Certification of Eligibility (May 2014) 52.222-21 Prohibition of Segregated Facilities (Apr 2015) 52.222-26 Equal Opportunity (Sept 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015) 52.222-37 Employment Reports on Veterans (Jun 2020) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) 52.222-50 Combating Trafficking in Persons (Nov 2021) 52.222-54 Employment Eligibility Verification (May 2022) 52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026 (Jan 2022) 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts (Sep 2013) 52.223-3 Alt I Hazardous Material Identification and Material Safety Data (Feb 2021) - Alternate I (July 1995) 52.223-5 Pollution Prevention and Right-to-Know Information (May 2011) 52.223-6 Drug-Free Workplace (May 2001) 52.223-11 Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (Jun 2016) 52.223-15 Energy Efficiency in Energy-Consuming Products (May 2020) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts (Aug 2018) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (Jun 2020) 52.223-20 Aerosols (Jun 2016) 52.223-21 Foams (Jun 2016) 52.225-13 Restrictions on Certain Foreign Purchases (Feb 2021) 52.227-1 Authorization and Consent (Jun 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (Jun 2020) 52.227-4 Patent Indemnity-Construction Contracts (Dec 2007) 52.228-2 Additional Bond Security (Oct 1997) 52.228-5 Insurance-Work on a Government Installation (Jan 1997) 52.228-11 Individual Surety-Pledge of Assets (Feb 2021) 52.228-12 Prospective Subcontractor Requests for Bonds (Dec 2022) 52.228-14 Irrevocable Letter of Credit (Nov 2014) 52.228-15 Performance and Payment Bonds-Construction (Jun 2020) 52.229-3 Federal, State and Local Taxes (Feb 2013) 52.229-12 Tax on Certain Foreign Procurements (Feb 2021) 52.232-5 Payments under Fixed-Price Construction Contracts (May 2014) 52.232-17 Interest (May 2014) 52.232-23 Assignment of Claims (May 2014) 52.232-27 Prompt Payment for Construction Contracts (Jan 2017) 52.232-33 Payment by Electronic Funds Transfer-System for Award Management (Oct 2018) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-1 Alt I Disputes (May 2014) - Alternate I (Dec 1991) 52.233-3 Protest after Award (Aug 1996) 52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004) 52.236-2 Differing Site Conditions (Apr 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984) 52.236-5 Material and Workmanship (Apr 1984) 52.236-6 Superintendence by the Contractor (Apr 1984)

15BFA023B00000018 Page 5 of 54

52.236-7 Permits and Responsibilities (Nov 1991) 52.236-8 Other Contracts (Apr 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984) 52.236-10 Operations and Storage Areas (Apr 1984) 52.236-11 Use and Possession Prior to Completion (Apr 1984) 52.236-12 Cleaning Up (Apr 1984) 52.236-14 Availability and Use of Utility Services (Apr 1984) 52.236-26 Preconstruction Conference (Feb 1995) 52.242-13 Bankruptcy (July 1995) 52.243-4 Changes (June 2007) 52.246-21 Warranty of Construction (Mar 1994) 52.248-3 Value Engineering-Construction (Oct 2020) 52.249-10 Default (Fixed-Price Construction) (Apr 1984) 52.249-2 Alt I Termination for Convenience of the Government (Fixed-Price) (Apr 2012) - Alternate I (Sept 1996) 52.204-27 Prohibition on a ByteDance Covered Application (Jun 2023) 52.204-2 Alt II Security Requirements (Mar 2021) - Alternate II (Apr 1984) 52.236-13 Alt I Accident Prevention (Nov 1991) - Alternate I (Nov 1991) 52.236-17 Layout of Work (Apr 1984) 52.236-21 Alt II Specifications and Drawings for Construction (Feb 1997) - Alternate II (Apr 1984) 52.244-6 Subcontracts for Commercial Products and Commercial Services (Mar 2023) 52.253-1 Computer Generated Forms (Jan 1991) 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984) 52.211-12 Liquidated Damages-Construction (Sept 2000) 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (Feb 1999) 52.225-10 Notice of Buy American Requirement-Construction Materials (May 2014) FAO-0015 Changes FAO-0016 Equitable Adjustments: Waiver and Release of Claims 52.204-21 Basic Safeguarding of Covered Contractor Information Systems (Nov 2021) 52.222-35 Equal Opportunity for Veterans (Jun 2020) 52.222-36 Equal Opportunity for Workers with Disabilities (Jun 2020) 52.225-9 Buy American-Construction Materials (Oct 2022) BOP 2852.201-71 Contracting Officer's Representative (COR) (June 2012) 52.24-403-70 Notice of Contractor Personnel Security Requirements (OCT 2005)

BOP 2852.242-71 EVALUATION OF CONTRACTOR PERFORMANCE UTILIZING CPARS (APR

2011) DOJ-01 Whistleblower Information Distribution (Oct 2021) DOJ-02 Contractor Privacy Requirements (JAN 2022) DOJ-03 Personnel Security Requirements For Contractor Employees (Nov 2021) DOJ-08 Continuing Contract Performance During a Pandemic Influenza or other National Emergency

(OCT 2007)

2852.223-70 Unsafe Conditions Due to the Presence of Hazardous Material (NOV 2020) 52.215-21 Alt IV Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data-Modifications (Nov 2021) - Alternate IV (Oct 2010)

5 Attachments 6 Solicitation Provisions

52.228-17 Individual Surety-Pledge of Assets (Bid Guarantee) (Feb 2021) 52.214-35 Submission of Offers in U.S. Currency (Apr 1991) 52.204-7 System for Award Management (Oct 2018) 52.204-16 Commercial and Government Entity Code Reporting (Aug 2020) 52.204-22 Alternative Line Item Proposal (Jan 2017) 52.214-3 Amendments to Invitations for Bids (Dec 2016) 52.214-4 False Statements in Bids (Apr 1984) 52.214-5 Submission of Bids (Dec 2016) 52.214-6 Explanation to Prospective Bidders (Apr 1984) 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids (Nov 1999) 52.214-18 Preparation of Bids-Construction (Apr 1984)

15BFA023B00000018 Page 6 of 54

52.214-19 Contract Award-Sealed Bidding-Construction (Aug 1996) 52.214-34 Submission of Offers in the English Language (Apr 1991) 52.228-1 Bid Guarantee (Sept 1996) 52.233-2 Service of Protest (Sept 2006) 52.236-27 Alt I Site Visit (Construction) (Feb 1995) - Alternate I (Feb 1995) 52.222-5 Construction Wage Rate Requirements - Secondary Site of the Work (May 2014) 2852.233-70 Protests Filed Directly with the Department of Justice (NOV 2020)

7 Representations and Certifications 52.209-7 Information Regarding Responsibility Matters (Oct 2018) 52.209-13 Violation of Arms Control Treaties or Agreements-Certification (Nov 2021) 52.229-11 Tax on Certain Foreign Procurements--Notice and Representation (Jun 2020) FAO-0022 List of References and Bank Information 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021) 52.204-8 Annual Representations and Certifications (Mar 2023)

15BFA023B00000018 Page 7 of 54

Section 2 - Commodity or Services Schedule

Firm Fixed Price

SCHEDULE OF SUPPLIES/SERVICES

CONTINUATION SHEET

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 The selected contractor shall provide all materials, labor, and equipment to complete the project "Install Structural Shoring Food Service” at FCI BIG Spring, TX in accordance with the attached Specifications and Drawings.

PSC: Z2FF

1 JB $________ $_________________

NOTE: The successful contractor shall be responsible for all applicable federal, state, and local taxes. No tax exemption certification will be issued by the Federal Bureau of Prisons. THE TOTAL PRICE SHALL BE WRITTEN ON LINE ITEM 17 OF THE STANDARD

FORM

15BFA023B00000018 Page 8 of 54

Section 3 - Special Contract Requirements

Clauses By Full Text

FAO-0001 Bonds

(a) Bid Guarantee. Each bidder shall submit with his bid a Bid Bond (Standard Form 24) with good and sufficient surety or sureties acceptable to the Government, or other security as provided in provision 52.228-1, in the form of twenty percent (20) of the bid price or not to exceed $3,000,000. The bid bond penalty may be expressed in terms of a percentage of the bid price or may be expressed in dollars and cents. A bid bond is not required for bids of $150,000 or less. (FAR 28.102-1)

(b) Performance and Payment Bonds. Within 10 days after award the contractor shall execute and submit to the Contracting Officer two bonds, each with good and sufficient surety or sureties acceptable to the Government, as follows; a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25A). The penal sums of such bonds will be as follows: (Not required for contracts of $150,000 or less)

(1) Performance Bond: The penal sum of performance bonds at the time of contract award shall be 100 percent of the original contract price.

(2) Payment Bond: The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.

(c) For construction contracts greater than $35,000 but not greater than $150,000, the Contracting Officer shall select two or more of the following payment protections, giving particular consideration to inclusion of an irrevocable letter of credit as one of the selected alternatives (FAR 28.102-1(b)(1)):

(1) A Payment Bond;

(2) An irrevocable letter of credit (ILC);

(3) A tripartite escrow agreement;

(4) A Certificate of Deposit; or

(5) A deposit of the types of security listed in 28.204-1 and 28.204-2.

(d) Individual Sureties.

(1) Bidders may elect to furnish individual surety bonds. If individual surety bonds are furnished for bid guarantees, payment or performance bonds, the individual sureties must submit their bonds proof of ownership and value of the assets which they claim in their net worth at time of bid opening. The Government's preferred method of proof is to have a statement of net worth prepared by a Certified Public Accountant (CPA) in accordance with Generally Accepted Accounting Principles (GAAP). Statements from a CPA that contain disclaimers are not acceptable. The statement of net worth on the Standard Form 28, Affidavit of Individual Surety, is insufficient and will not be accepted without additional proof of value and ownership.

(2) Bidders are cautioned that individual sureties must provide complete and detailed information in Block 9 of Standard Form 28 concerning other contracts on which they have provided bonds. This information shall include contract number, contract location, amount, and type of bond and telephone number of the involved contracting office. Failure to provide the proof and information required may result in rejection of the bid or termination of the contract for failure to provide adequate bonds.

FAO-0002 Magnitude

The magnitude of this project is between $500,000.00 and $1,000,000.00.

FAO-0003 Required Insurance

15BFA023B00000018 Page 9 of 54

See FAR 52.228-5, Insurance - Work on a Government Installation.

The Contractor shall, at its own expense, provide and maintain during the entire performance period of this contract, at least the kinds and minimum amounts of insurance required in the

Schedule or elsewhere in the contract.

TYPE AMOUNT

(1) WORKERS COMPENSATION & EMPLOYER'S LIABILITY $100,000

The required Workmen's Compensation Insurance shall extend to cover employee's liability for accidental bodily injury or death and for occupational disease with a minimum liability of $100,000.

(2) COMPREHENSIVE GENERAL LIABILITY with a minimum limit of:

PER ACCIDENT OR

OCCURRENCE FOR BODILY INJURY $500,000

This insurance shall include contractor's protective and contractual liability.

(3) COMPREHENSIVE AUTOMOBILE LIABILITY with the following minimum limits:

PER PERSON $200,000

PER OCCURRENCE FOR BODILY INJURY $500,000

PER OCCURRENCE FOR PROPERTY DAMAGE $ 20,000

FAO-0004 Pre-Construction Conference

(a) Prior to the start of construction, Contracting Officers shall call a conference with the contractor, subcontractor(s), Warden, Controller/Business Administrator, Safety Manager, Facilities Administrator, Project Representative, A&E firm, Captain and other interested personnel to discuss the statutory labor standards, prevailing wage requirements, submission of the contractor's payrolls, subcontractor's responsibilities, institution work schedules, local policies, contraband, parking, storage of vehicles and equipment, etc.

15BFA023B00000018 Page 10 of 54

Minutes of the conference shall be recorded, listing the names and titles of all attendees, and the subject matter of all items covered.

The minutes shall be signed by the contractor and the Contracting Officer, and a signed copy placed in the contract file.

(b) The Contractor shall familiarize himself/herself with all procedures involved in normal institution routines. Any requirements which may constitute a problem or result in conflict, will be brought to the attention of the Contracting Officer or his representative for determination.

FAO-0005 Submittals

Within 10 calendar days after commencement of work or as otherwise established by the Contracting Officer, all materials and articles requiring approval, as contemplated by the Materials and Workmanship clause, shall be submitted by the contractor.

The submittal process is in place to allow the Government the opportunity to determine whether materials or procedures used by the contractor are in accordance with contract requirements. It is ultimately the Contractor's responsibility via the quality control process to ensure submittal items installed under the contract and work performed on site are in accordance with industry standards and general practices.

(a) The types of submittal requirements specified in this contract may include, but is not limited to; shop drawings, product data, samples, certificates of conformance or compliance, certified test or inspection reports, equipment, materials, and miscellaneous work related submittals for construction. Individual submittal requirements are generally specified in applicable sections for each unit of work in the specifications and/or as a whole in one section in the statement of work.

(b) The Bureau of Prisons (BOP) Contracting Officer’s Representative (COR) shall act for the Contracting Officer in the review and acceptance of all submittals. The Contractor shall submit submittals as required by the contract/specifications to the COR for transmittal to the Contracting Officer. Fabrication of any work or purchase or use of any submittals (such as materials for which samples are required or equipment, etc.) shall not take place until written acceptance is given by the COR, except at the Contractor's own risk.

(c) The Contractor shall submit all shop drawings and submittals sufficiently in advance (unless otherwise specified in the specifications) of the construction requirements to allow ample time for checking, re-submitting, and re-checking.

(d) Failure of any materials to pass their specified tests shall be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. The Government reserves the right to disapprove any material or equipment which has previously proven unsatisfactory in service.

(e) The Contracting Officer’s or designee’s approval or acceptance of submittals is not to be construed as a complete check.

Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor is responsible for the satisfactory construction of all work. The Contractor is responsible for delivering a final product/system that is operational as intended by the contract requirements, regardless of any Government approvals or acceptance of submittals. The Government assumes no liability during the submittal approval/acceptance process. It is the sole responsibility of the Contractor to deliver a properly functioning product or system.

FAO-0006 Contractor Use of Premises

Work Hours The project schedule is based on a normal forty (40) hour work week, eight (8) hours per day, Monday through Friday, excluding Federal holidays. The Contracting Officer’s Representative (COR) shall establish the work hour time frames for the duration of the project, subject to the approval of the Contracting Officer. Work hours and work days may be altered only with a 48 hour advance approval of the Contracting Officer.

NOTE: Access to the site will be available during normal working hours except during emergencies. It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and conditions in the correctional facility, as working hours may not constitute a full eight hour day. The Government assumes no responsibility to the Contractor, nor to any of his subcontractors, for shorter hours due to institutional emergencies or entry and/or exit of workers necessitated by normal institution routines. The procedures and institutional entrance/exit routines applicable to this project will be explained at both the pre-bid conference/site visit and the pre-construction meeting.

Contraband

15BFA023B00000018 Page 11 of 54

The Contractor shall inform his employees that intoxicating beverages, drugs, weapons, etc., will not be allowed on the site.

Introduction of contraband shall be subject to the penalties prescribed by Title 18 USC-1791.

Explosives The use of explosives is absolutely forbidden without written authorization from the Contracting Officer.

Parking and Temporary Office Parking will be available at the site to the extent it does not interfere with construction activities. Otherwise, parking shall be provided for by the Contractor, at his expense, off the site for workmen employed on the project. Any temporary field office used by the Contractor shall be located in an area approved by the COR.

Safety and Accident Prevention In performing work under this contract the contractor shall:

(a) Conform to the specific safety requirements established by this contract;

(b) Comply with the safety rules of the Government institution that concern related activities not directly addressed in this contract;

(c) Take all reasonable steps and precautions to prevent accidents and preserve the life and health of contractor and Government personnel performing or in any way coming in contact with the performance of this contract; and

(d) Take such additional immediate precautions as the Contracting Officer and/or COR may reasonably require for safety and accident prevention purposes.

FAO-0007 Payment Services

(a) Original application for payment shall be prepared on AIA (American Institute of Architects) Form G-702 "Application and Certificate for Payment" and submitted to the Contracting Officer. The contractor may use another form; however, it shall contain similar information as the AIA Form G-702. The Contracting Officer’s Representative (COR) will approve the amount of payment by signing. The approved application for payment shall be forwarded as follows: Original to Accounting; Copy for Contract Award File.

(b) All small business contractors are required to self-certify on all invoices their small business status.

(c) The following information is required with each application for payment:

• Name and address of contractor

• Contract number

• Contractor invoice/application for payment number

• Description, price, and quantity of construction completed/rendered

• Payment terms (reference the contract payment clause)

• Other substantiating documentation or information required by the contract

• Name, title, and phone number of official to be notified in the event of a defective invoice

• Contractor TIN (Tax ID Number)

FAO-0008 Request for Final Inspection

The Contractor shall give the Contracting Officer’s Representative (COR) a minimum of ten (10) working days advanced written notice of the date on which the work will be fully completed and ready for the Government’s final inspection.

FAO-0009(a) Construction Contract Security

FAO-0009(a) Construction Contract Security (Program Statement 3732.01 BOP Identifications and Background Investigation)

In addition to the information contained in clause “DOJ-03 Personnel Security Requirements For Contractor Employees (Nov 2021);

(Alt. I) -- Classified Information – Cleared Contractors”, the following additional security is required to be completed and submitted for all contract employees who will be working under the terms of the contract:

Criminal History Check – BP-A0660 (May 2018)

15BFA023B00000018 Page 12 of 54

CJIS Name Check Request Form BOP Contractor Pre-employment Questionnaire BOP Authority for Release of Information The contactor should be aware that the time required for contractor security clearances to be completed may vary. For the purposes of this solicitation, ____ calendar days [contracting officer to insert the number of days based on performance period memo] have been included in the performance period specified in FAR clause 52.211-10. The number of days listed above is contingent upon the contractor providing completed clearance packages for their employees within 10 calendar days of the Notice to Proceed. For any subsequently awarded subcontract, completed security clearance packages for subcontractor workers shall be submitted in conjunction with the completed SF-1413.

**A form package will be issued by the Administrative Contracting Officer or Contracting Officer's Representative (COR) at the institution upon contract award. Completed packages shall be submitted by the PRIME CONTRACTOR ONLY to obtain clearance for each prime and sub-contract employee. Security Clearance packages will NOT be accepted from sub-contractors. Upon clearance being obtained the contractor will be notified. Should a contract employee NOT be cleared to enter the facility for this project, the contractor will be notified immediately. The contractor will be responsible to submit another contract employee as soon as possible for clearance. Be advised, the Federal Bureau of Prisons cannot disclose why an individual does not pass the security clearance process, as it is a violation of law.**

FAO-0010 Assignment of Contract Administration Office and Functions

Pursuant to FAR 42.201 and 42.202, the assigned Contract Administration Office is listed in Block 26 of the Standard Form 1442 Back. This assignment carries with it the authority to perform all of the contract administration functions listed in FAR 42.302(a) and 42.302(b) to the extent that those functions apply to the contract.

FAO-0011 Schedule of Values

The Contractor shall prepare a Schedule of Values (SOV) for the project and submit to the Contracting Officer for approval prior to submitting the first application for payment. The SOV shall be correlated with the construction schedule. The SOV shall be formatted per the Construction Specification Institute Master Format structure. The Contractor may propose an alternate organizational format to the Contracting Officer for approval.

(a) The SOV shall include:

(1) Project name, location, and contract number;

(2) Contractor’s name and address;

(3) Date of submittal.

(b) The SOV shall be arranged in a tabular form with separate columns to indicate the following for each item listed:

(1) Description of Work or Material;

(2) Related specification section, if applicable;

(3) Name of subcontractor, if applicable;

(4) Name of manufacturer or fabricator, if applicable;

(5) Name of supplier, if applicable;

(6) Change orders (modifications) that have affected value, if applicable;

(7) Dollar value;

(8) Percentage of Contract sum rounded to the nearest percent, adjusted to total 100 percent.

(c) The SOV shall breakdown the contract sum in sufficient detail to facilitate continued evaluation of applications for payment and progress reports. The contractor should separate principal subcontract amounts down into several line items.

(d) SOV amounts shall be rounded to the nearest whole dollar. The total of all SOV amounts shall equal the total contract amount.

15BFA023B00000018 Page 13 of 54

(e) The contractor shall progress the percentage of completion, with the concurrence of the Contracting Officer’s Representative, for each value in conjunction with the preparation of each monthly application for payment. The progressed value percentages shall directly correlate to the calculated total amount due for each monthly progress payment.

(f) The SOV shall remain fixed for the duration of contract performance. Any revisions to the SOV must be requested in writing, with justification, for approval by the Contracting Officer.

FAO-0012 Progress Meetings

The Administrative Contracting Officer (ACO) shall conduct progress meetings at the project site on a monthly basis, or at intervals as determined by the ACO.

(a) At a minimum, the attendees shall include but is not limited to:

(1) FBOP: Administrative Contracting Officer, Contracting Officer’s Representative (COR), Facility Administrator/ Manager, Architect/Engineer (if applicable), Other Personnel (Executive Staff, Captain, Safety Manager, etc.).

(2) Contractor: Project Manager, Superintendent, and technical support disciplines as appropriate (Subcontractors, Manufacturers, Suppliers, etc.).

(b) The meeting should include, but is not limited to issues such as:

Administrative Contracting Officer:

(1) Old business from previous progress meeting(s);

(2) Status of modifications, certified payrolls, submittals, requests for information (RFI);

(3) Review of payments made to date and review/approve current payment request;

(4) Status of modification proposal requests;

(5) Discuss new business.

COR:

(1) Status of escort coverage;

(2) Review gate or sallyport entrance/exit issues;

(3) Discuss other delays contractor may be experiencing;

(4) Discuss performance/quality issues.

Contractor:

(1) Review/discuss updated progress schedule;

(2) Provide 30 day outlook;

(3) Discuss other issues affecting performance.

FAO-0013 Contract Closeout Procedures (for construction contracts exceeding $150,000)

Contract Closeout must be completed within six (6) months of physical completion of the work.

Prior to payment of final invoice:

The contractor shall submit the following documents:

15BFA023B00000018 Page 14 of 54

(1) Contractor’s Affidavit of Release of Liens (AIA Document G706A);

(2) Contractor’s Affidavit of Payment of Debts and Claims (AIA Document G706);

(3) All as-built drawings/shop drawings, if applicable;

(4) Contractor’s final invoice;

(5) Release of Claims (GSA Form 1142);

(6) Consent of Surety to Final Payment (AIA Document G707);

(7) Letter establishing warranty dates;

(8) Complete list of subcontractors with telephone numbers and points of contact;

(9) Guarantees and warranties;

(10) All balance and test reports;

(11) All operation/maintenance manuals;

(12) All permits and certifications.

AIA forms can be obtained from The American Institute of Architects at www.aiabookstore.com.

GSA forms can be obtained from the General Services Administration at www.gsa.gov (click on the “Forms Library” link).

15BFA023B00000018 Page 15 of 54

Section 4 - Contract Clauses

Clauses By Reference

52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov

Clause Title Fill-ins (if applicable)

52.246-12 Inspection of Construction (Aug 1996)

52.236-15 Schedules for Construction Contracts (Apr 1984)

52.242-14 Suspension of Work (Apr 1984)

52.204-23 Prohibition on Contracting for Hardware, Software, and Services

Developed or Provided by Kaspersky Lab and Other Covered Entities

(Nov 2021)

52.202-1 Definitions (Jun 2020)

52.203-3 Gratuities (Apr 1984)

52.203-5 Covenant Against Contingent Fees (May 2014)

52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020)

52.203-7 Anti-Kickback Procedures (Jun 2020)

52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or

Improper Activity (May 2014)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014)

52.203-12 Limitation On Payments to Influence Certain Federal Transactions

(Jun 2020)

52.203-17 Contractor Employee Whistleblower Rights and Requirement To

Inform Employees of Whistleblower Rights (Jun 2020)

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or

Statements (Jan 2017)

52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content

Paper (May 2011)

15BFA023B00000018 Page 16 of 54

Clause Title Fill-ins (if applicable)

52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011)

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards

(Jun 2020)

52.204-13 System for Award Management Maintenance (Oct 2018)

52.204-14 Service Contract Reporting Requirements (Oct 2016)

52.204-18 Commercial and Government Entity Code Maintenance (Aug 2020)

52.204-19 Incorporation by Reference of Representations and Certifications (Dec

2014)

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video

Surveillance Services or Equipment (Nov 2021)

52.209-6 Protecting the Government's Interest When Subcontracting with

Contractors Debarred, Suspended, or Proposed for Debarment (Nov

2021)

52.209-9 Updates of Publicly Available Information Regarding Responsibility

Matters (Oct 2018)

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov

2015)

52.219-6 Notice of Total Small Business Set-Aside (Nov 2020)

52.219-8 Utilization of Small Business Concerns (Oct 2022)

52.219-28 Post-Award Small Business Program Rerepresentation (Mar 2023) (h)(1) NAICS Code: "238110"

52.219-14 Limitations on Subcontracting (Oct 2022) (f)(1) End of Base Term: "X"

52.222-1 Notice to the Government of Labor Disputes (Feb 1997)

52.222-3 Convict Labor (June 2003)

52.222-4 Contract Work Hours and Safety Standards--Overtime Compensation

(May 2018)

52.222-6 Construction Wage Rate Requirements (Aug 2018)

52.222-7 Withholding of Funds (May 2014)

52.222-8 Payrolls and Basic Records (Jul 2021)

52.222-9 Apprentices and Trainees (July 2005)

52.222-10 Compliance with Copeland Act Requirements (Feb 1988)

15BFA023B00000018 Page 17 of 54

52.222-11 Subcontracts (Labor Standards) (May 2014)

52.222-12 Contract Termination - Debarment (May 2014)

52.222-13 Compliance with Construction Wage Rate Requirements and Related

Regulations (May 2014)

52.222-14 Disputes Concerning Labor Standards (Feb 1988)

52.222-15 Certification of Eligibility (May 2014)

52.222-21 Prohibition of Segregated Facilities (Apr 2015)

52.222-26 Equal Opportunity (Sept 2016)

52.222-27 Affirmative Action Compliance Requirements for Construction (Apr

2015)

52.222-37 Employment Reports on Veterans (Jun 2020)

52.222-40 Notification of Employee Rights Under the National Labor Relations

Act (Dec 2010)

52.222-50 Combating Trafficking in Persons (Nov 2021)

52.222-54 Employment Eligibility Verification (May 2022)

52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026

(Jan 2022)

52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022)

52.223-2 Affirmative Procurement of Biobased Products Under Service and

Construction Contracts (Sep 2013)

52.223-3 Alt I Hazardous Material Identification and Material Safety Data (Feb 2021)

- Alternate I (July 1995)

52.223-5 Pollution Prevention and Right-to-Know Information (May 2011)

52.223-6 Drug-Free Workplace (May 2001)

52.223-11 Ozone-Depleting Substances and High Global Warming Potential

Hydrofluorocarbons (Jun 2016)

52.223-15 Energy Efficiency in Energy-Consuming Products (May 2020)

52.223-17 Affirmative Procurement of EPA-designated Items in Service and

Construction Contracts (Aug 2018)

15BFA023B00000018 Page 18 of 54

52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving

(Jun 2020)

52.223-20 Aerosols (Jun 2016)

52.223-21 Foams (Jun 2016)

52.225-13 Restrictions on Certain Foreign Purchases (Feb 2021)

52.227-1 Authorization and Consent (Jun 2020)

52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement

(Jun 2020)

52.227-4 Patent Indemnity-Construction Contracts (Dec 2007)

52.228-2 Additional Bond Security (Oct 1997)

52.228-5 Insurance-Work on a Government Installation (Jan 1997)

52.228-11 Individual Surety-Pledge of Assets (Feb 2021)

52.228-12 Prospective Subcontractor Requests for Bonds (Dec 2022)

52.228-14 Irrevocable Letter of Credit (Nov 2014)

52.228-15 Performance and Payment Bonds-Construction (Jun 2020)

52.229-3 Federal, State and Local Taxes (Feb 2013)

52.229-12 Tax on Certain Foreign Procurements (Feb 2021)

52.232-5 Payments under Fixed-Price Construction Contracts (May 2014)

52.232-17 Interest (May 2014)

52.232-23 Assignment of Claims (May 2014)

52.232-27 Prompt Payment for Construction Contracts (Jan 2017)

52.232-33 Payment by Electronic Funds Transfer-System for Award Management

(Oct 2018)

52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013)

52.232-40 Providing Accelerated Payments to Small Business Subcontractors

(Mar 2023)

52.233-1 Alt I Disputes (May 2014) - Alternate I (Dec 1991)

52.233-3 Protest after Award (Aug 1996)

52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004)

52.236-2 Differing Site Conditions (Apr 1984)

15BFA023B00000018 Page 19 of 54

52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984)

52.236-5 Material and Workmanship (Apr 1984)

52.236-6 Superintendence by the Contractor (Apr 1984)

52.236-7 Permits and Responsibilities (Nov 1991)

52.236-8 Other Contracts (Apr 1984)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (Apr 1984)

52.236-10 Operations and Storage Areas (Apr 1984)

52.236-11 Use and Possession Prior to Completion (Apr 1984)

52.236-12 Cleaning Up (Apr 1984)

52.236-14 Availability and Use of Utility Services (Apr 1984)

52.236-26 Preconstruction Conference (Feb 1995)

52.242-13 Bankruptcy (July 1995)

52.243-4 Changes (June 2007)

52.246-21 Warranty of Construction (Mar 1994)

52.248-3 Value Engineering-Construction (Oct 2020)

52.249-10 Default (Fixed-Price Construction) (Apr 1984)

52.249-2 Alt I Termination for Convenience of the Government (Fixed-Price) (Apr

2012) - Alternate I (Sept 1996)

52.204-27 Prohibition on a ByteDance Covered Application (Jun 2023)

52.204-2 Alt II Security Requirements (Mar 2021) - Alternate II (Apr 1984)

52.236-13 Alt I Accident Prevention (Nov 1991) - Alternate I (Nov 1991)

52.236-17 Layout of Work (Apr 1984)

52.236-21 Alt II Specifications and Drawings for Construction (Feb 1997) - Alternate II

(Apr 1984)

(g) desired amount:

"[Contracting Officer complete by inserting desired amount]"

52.244-6 Subcontracts for Commercial Products and Commercial Services (Mar

2023)

52.253-1 Computer Generated Forms (Jan 1991)

15BFA023B00000018 Page 20 of 54

Clauses By Full Text

52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984)

The Contractor shall be required to (a) commence work under this contract within 10 [Contracting Officer insert number] calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 217 calendar days.* The time stated for completion shall include final cleanup of the premises.

* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.

(End of clause)

52.211-12 Liquidated Damages-Construction (Sept 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,199.71 [Contracting Officer insert amount] for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (Feb 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for Minority Participation for Each Trade Goals for Female Participation for Each Trade

18.9 6.9 [Contracting Officer shall insert goals] [Contracting Officer shall insert goals]

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order11246, as amended, and the regulations in 41 CFR 60-4 shall be based on

(1) its implementation of the Equal Opportunity clause,(2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S.

Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the--

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

15BFA023B00000018 Page 21 of 54

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is [Contracting Officer shall insert description of the geographical areas where the contract is to be performed, giving the state, county, and city.]

(End of provision)

52.225-10 Notice of Buy American Requirement-Construction Materials (May 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American- Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers.

The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the…