Sol_140R2024Q0111_Amd_0001.pdf
PDF 87 KB Posted
- Attached to
- Sliger Mine Road Security Gates Federal contract opportunity
- Solicitation number
- 140R2024Q0111
About this file
This document is an amendment to Solicitation 140R2024Q0111, a Request for Quote (RFQ) for Sliger Mine Road Security Gates. The purpose of this amendment is to provide answers to questions received and revise the Specifications document. The key details are:
The requirement is for two security gates. The revised Specifications document indicates the gates must have a minimum of two locks. The contractor will not be responsible for installation of the gates. Quotes are due by 10:00 AM PT on July 26, 2024 and should be emailed to the Contracting Officer, Margaret Jones, at margaretjones@usbr.gov. This is a total small business set-aside with a NAICS code of 332323 and a size standard of 500 employees. The agency issuing this solicitation is the Department of the Interior, Bureau of Reclamation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140R2024Q0111_Amd_0002.pdf | ||
| Revised_Specifications_0001.pdf | ||
| Sol_140R2024Q0111.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140R2024Q0111 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Sacramento CA 95825-1898 2800 Cottage Way, Room E-1815
R20
Division of Acquisition Services Regional Office Mid-Pacific Region Bureau of Reclamation
07/18/20240001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/12/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The Solicitation cited in block 9A above, Folsom Sliger Mine Road Security Gates, is hereby amended.
Purpose: The purpose of this amendment is to provide answers to the received questions and revise the Specifications document. Revised language in the Specifications document is indicated in red lettering and included as an attachment to this amendment.
All other terms and conditions remain unchanged.
1. Is the requirement for a box that can house five usable locks to be included somewhere on the gate? The requirement is for a minimum of two locks. See the attached revised
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Margaret Jones
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140R2024Q0111/0001
Specifications document.
2. Will the contractor be responsible for installation? No, the contractor will not be providing installation of the two gates.
3. Is the requirement for two gates as depicted in the pictures? Yes, the requirement is for two gates as specified within the Specifications document and the price schedule. Two gate designs are provided in the Specifications document as examples of acceptable gate designs.