Q_A_0001.pdf

PDF 410 KB Posted

Attached to
Update Scope of Collections Statements Federal contract opportunity
Solicitation number
140P6423Q0039
Issued by
Department of the Interior National Park Service Midwest Region

View the file

Other files for this federal contract opportunity

Other files attached to Update Scope of Collections Statements, newest first.
File Type Posted
Sol_140P6423Q0039_Amd_0001.pdf PDF
Technical_Questionnaire_SOCS_project.docx DOCX document
Wage_Determination.pdf PDF
Price_Schedule.pdf PDF
Price_Schedule.xlsx XLSX spreadsheet
Sol_140P6423Q0039.pdf PDF
SOCS_Template.docx DOCX document
SOCS_Template_Instruction_Memo.docx DOCX document
Statement_of_Work.pdf PDF
Provisions_to_be_Completed.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q. How long is the NPS review of the First Draft?

A. Will be sent back within 30 calendar days (page 8)

Q. How long does the contractor have to prepare a Final Draft after receiving NPS comments? (After the First Draft submission, the schedule in the Project Schedule & Deliverables section on page 10 goes from "Review/Comments" to "NPS Review of Consultant Responses" and appears to be missing the Final Draft deliverable in between.)

A. 30 calendar days after receiving NPS comments.

Q. Is the NPS willing to consider an alternative order to the project schedule? Note that the alternative would not affect the overall period of performance, but would suggest a minor re-arrangement of the order in which the project schedule takes place.

A. Yes, alternatives will be considered. Please explain in detail why it’s beneficial.

Q. The Technical Questionnaire mentions a Past Performance Questionnaire. No Past Performance Questionnaire has been included in the Attachments/Links on Sam.gov. If the Past Performance Questionnaire is required, can it be included to offerors in an amendment?

A. There is no Past Performance Questionnaire. Just submit Three prior experiences of projects in similar size and scope per the “TO SUBMIT AN OFFER” section below within the past five years to include:

Brief description of project Point of contact information