Atch_1_-_SOW_Replace_DB_Boat_Ramp_and_Piers.pdf

PDF 467 KB Posted

Attached to
GUIS REPLACE DB BOAT RAMP AND PIERS Federal contract opportunity
Solicitation number
140P5219B0001
Issued by
Department of the Interior National Park Service

About this file

Atch 1 - SOW Replace DB Boat Ramp and Piers

View the file

Other files for this federal contract opportunity

Other files attached to GUIS REPLACE DB BOAT RAMP AND PIERS, newest first.
File Type Posted
Sol_140P5219B0001_Amd_0002.pdf PDF
Sol_140P5219B0001_Amd_0001.pdf PDF
Atch_3_-_ABA_Standards.pdf PDF
EXPLANATION_TO_PROSPECTIVE_BIDDERS_-_SITE_VISIT_SIGIN-IN.pdf PDF
Sol_140P5219B0001.pdf PDF
Atch_2_-_DOL_WD__MS61_01-04-2019.pdf PDF
Exhibit_1_-_Photos_of_Davis_Bayou_Public_Boat_Launch.pdf PDF
Exhibit_2_-_MAPs_Gulf_Islands_National_Seashore.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Gulf Islands National Seashore Park Ocean Springs, Mississippi

STATEMENT OF WORK:

Replace Boat Ramp and Finger Piers at DB Boat Launch

DATED:

02/28/2019

NATIONAL PARK SERVICE

SOUTHEAST REGION

WEST MAJOR ACQUISITION BUYING OFFCE

Replace Davis Bayou Boat Ramp Finger Piers and Concrete Slabs

SOW Format

1. Background

2. Objectives

3. Place of performance

4. Period of performance

5. Scope

6. Tasks

7. Deliverables

8. Government-Furnished Property (GFP)

9. Safety

10. Security Considerations

11. Travel

12. Special Material Requirements

13. Other Unique Requirements and Considerations

14. Quality Assurance Requirement

15. Project Personnel

1. BACKGROUND

This contract is for the replacement of the Davis Bayou Public Boat Ramp and piers.

2. OBJECTIVES:

The Contract is to remove existing finger piers, concrete slabs and install new finger piers as well as new concrete slabs.

3. PLACE OF PERFORMANCE:

Directions: We’re located off highway 90 which is in Ocean Springs. The address is 3500 Park Road Ocean Springs, MS 39564. Once you enter the park on park road off of highway 90. You will continue on park road for 1 ½ mile. Then turn right on Robert Magee Road go for 3/8 of a mile. Then turn left on Boat Launch Road go to the end of road then turn to the right and you will see the boat launch ramp to the right.

4. PERIOD OF PERFORMANCE:

All tasks and deliverables for this contract must be completed within 120 of days after Notice to proceed.

5. SCOPE:

This job will consist of the demolition of the existing finger piers and concrete slabs. Contractor will furnish all labor, materials, equipment, supplies and supervision to perform the job. The contractor will also be responsible for any damage it may could to the existing asphalt park area near the job site.

6. TASKS:

Mobilization/Demobilization Demo and remove existing three piers and concrete slab o Remove existing piers and piling o Remove old broken slab o Dispose of or recycle removed material in approved facility

Install and remove cofferdam o Approximately 178LF o Recommend PZ-27 or equal steel sheeting Utilize 30LF sheeting on front face Utilize 20-25LFsheeting on side walls Brace with H beam whaler and 30LF H-beam piling for support o Dewater of cofferdam cell Supply pumps and manning to dewater cofferdam area Install well sump areas

Install new poured in place boat ramp slab o Prep slab area and place a geogrid (Tensar BX1200 or equal) liner o Install a 24” layer of compacted 610 limestone o Construct two slab areas 20’x50’ each on top of prepared area Install top 24”x 30” footer area with rebar a #5 rebar cage Install bottom 24”x 30” footer area with a #5 rebar cage Install a 8” thich main slab area with side footers 18” thick with #4 rebar grid on 12” centers Pour 4000psi concrete

Build new piers (3 each) o Drive new 12”x 25LF piling treated to 2.5 cca o Install new headers and stringers o Install new grid walk mini mesh FRP grating for top decking

7. DELIVERABLES:

Before notice to proceed

Provide product submittals for materials to be installed for approval by project manager.

Provide a written narrative summary of how the contractor will execute the project with a timeline. This document will be referred to as the implementation plan.

Provide safety plan as identified in Section 9.

Before contract close out Provide one hard-bound copy of Operation and Maintenance (O&M) Manuals to the park for all materials installed. O&M manuals are to include the manufacturer’s specifications and instructions for all new parts.

Provide one hard-bound copy of all warranty information for new part and labor.

8. GOVERNMENT-FURNISHED PROPERTY, MATERIAL, EQUIPMENT, OR INFORMATION

(GFP, GFM, GFE, OR GFI):

N/A

9. SAFETY:

This contractor is to follow at a minimum all OSHA rules and procedures. Contractor must:

1. Provide a safe and healthful workplace for all employees while on NPS site.

2. Provide a safety plan outlining your safety program specific to this site.

3. Provide a level of public safety commensurate with exposure at NPS worksite.

4. Comply in rectifying all unsafe or unhealthful conditions called to his attention by the contracting officer.

5. Allow for informal and formal, announced and unannounced safety inspections by the COTR and the appropriate safety officer at the worksite.

6. Submit an acceptable documented safety plan before beginning work.

10. SECURITY:

N/A.

11. TRAVEL:

Contractor shall be responsible for all travel related expenses for this project, including mobilization of equipment, tools, materials, manpower, lodging, meals, and per diem.

12. SPECIAL MATERIAL REQUIREMENTS:

N/A.

13. OTHER UNIQUE REQUIREMENTS:

N/A.

14. QUALITY ASSURANCE REQUIREMENT:

The contractor shall develop and maintain a quality program to ensure services are performed in accordance with commonly accepted commercial practices. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. As a minimum the contractor shall develop quality control procedures addressing the critical areas identified in this statement of work. The government may periodically evaluate the contractor’s performance in accordance with the statement of work. All new equipment must conform to the manufacturer’s instructions and guidelines for installation.

While performing work, the contractor shall comply with the latest applicable versions of the following:

International Family of Codes, primarily the IBC (International Building Code) NFPA 101 (National Fire Protection Association's Life Safety Code) Federal, State and Local Building Codes, Standards and Policies Local codes only if required by utility companies for service connections.

National Electrical Code (NEC) Occupational Safety and Health Administration (OSHA) requirements

Additional Requirements:

All affected areas must be restored to their original condition from before the work began. Any damages will be fixed and repaired at no cost to the government.

15. PROJECT PERSONNEL:

Contracting Officer:

TBD

NPS, Southeast Region, SOUTH MABO Address Telephone:

Email:

Park Facility Manager:

Ernest J. Echoles Gulf Islands National Seashore 3500 Park Road Ocean Springs, MS 39564 Telephone: 228-230-4115 Email: ernest_echoles@nps.gov

Project Inspector:

TBD

Gulf Islands National Seashore 3500 Park Road Ocean Springs, MS 39564 Telephone: