B09_Attachment_0003_Amendment_0001_0001.docx

DOCX document 13 KB Posted

Attached to
BEAUFORT CONDITION & INTEGRITY STUDY Federal contract opportunity
Solicitation number
140P5121Q0066
Issued by
Department of the Interior National Park Service Southeast Region

View the file

Other files for this federal contract opportunity

Other files attached to BEAUFORT CONDITION & INTEGRITY STUDY, newest first.
File Type Posted
Sol_140P5121Q0066_Amd_0001.pdf PDF
B03_wage_Rates_Beaufort_County.pdf PDF
A04_Beaufort_NHL_Project_Scope_Final_202106.docx DOCX document
Sol_140P5121Q0066.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 0001, Questions and Answers

1. Is there any set budget range for this? There are a lot of variations that I can see for the public engagement process and it would be helpful to know what a maximum fee range might be.

Answer: This is a commercial requirement and an estimate can not be released. Pricing should be based on market value for a study based on what is written in the RFQ.

2. Is a time line for completion of 12 months to 18 months acceptable rather than 36 months?

Answer: A contractor can propose a shorter time in their proposal. The Government estimated 36 months based on previous studies. Additionally, contractor should estimate time for reviews and edits.

3. How do you want the proposal submitted? Do we submit our technical proposal followed by the quotation pages as an appendix? Do you just want one electronic copy submitted?

Answer: The proposal can be submitted as one document or two. There is no preference as long as it is submitted electronically.