Questions_and_Answers_0001.pdf

PDF 43 KB Posted

Attached to
GATE-JABA-QTRS ROOF REPLACEMENT Federal contract opportunity
Solicitation number
140P4524R0003
Issued by
Department of the Interior National Park Service Northeast Region

About this file

This document contains questions and answers related to solicitation number 140P4524R0003 for the GATE-JABA-QTRS ROOF REPLACEMENT project. The solicitation is for roof replacement work at quarters located within Gateway National Recreation Area and Jockey's Ridge in North Carolina. The scope of work involves replacing roofs on several buildings but does not include repairing or replacing fascia boards, painting, or work on an ancillary garage structure. Progress payments will not be necessary given the anticipated short field work duration of one month. Roofing materials for porch areas will be as specified in the statement of work.

View the file

Other files for this federal contract opportunity

Other files attached to GATE-JABA-QTRS ROOF REPLACEMENT, newest first.
File Type Posted
Sol_140P4524R0003_Amd_0002.pdf PDF
Sol_140P4524R0003_Amd_0001.pdf PDF
Ft__Tilden_106_0001.pdf PDF
Quarters_C_D_E_0001.pdf PDF
Sol_140P4524R0003.pdf PDF
B08_Solicitation_Roof_Replacement_GATE.pdf PDF
B08_Attachment_3_WD_Roof_Replacement_GATE.pdf PDF
B08_Attachment_2_Price_Schedule_Roof_Replacement_GATE.pdf PDF
B08_Atttachment_1_SOW_Roof_Replacement_GATE.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

140P4524R0003

1. Will progress payments be allowed upon completing each singular building?

The NPS does not anticipate the field work to exceed one month. As a result, progress payments would not be necessary.

2. For metal on porch roofs, pitch is very low suggests copper or flat roof covering?

The porch roof areas will be covered as per the SOW in section 4.1.5.

3. Is garage roof being done?

The ancillary garage structure is not included with the SOW.

4. On all the quarters, is the wood facia board being repaired and painted prior to gutter installation?

Fascia board and painting is not included in the SOW.