Amendment_1_0001.pdf
PDF 102 KB Posted
- Attached to
- FOST CONCRETE FLOOR PROJECT Federal contract opportunity
- Solicitation number
- 140P4323R0025
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P4323R0025_Amd_0002.pdf | ||
| Amendment_2_0002.pdf | ||
| Sol_140P4323R0025_Amd_0001.pdf | ||
| Provisions_and_Clauses.pdf | ||
| Tunnel_Concrete_Floor_SOW.pdf | ||
| Wage_Determination_NY20230014.pdf | ||
| Combined_Synopsis-Solicitation.pdf | ||
| Sol_140P4323R0025.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 1
The purpose of this amendment is to:
1. Provide Government responses to contractor questions;
2. Provide site access information; and
3. Extend the solicitation close date.
Government responses to contractor questions
1. Approximately what is the distance from Sally Port entry to the concrete pad, through the exhaust vent?
• Approximately 40-50 feet
2. Is there a need for extensive traffic control where the concrete and pump truck will be stations at sally port?
• No traffic control issues. The path that the truck will be set up on is a walking path only (vehicular traffic path for employees only)
Site access information
The site will be accessible for contractor viewing on Monday, 5 June, from 7:00am to 12:00pm.
Please provide a point of contact and telephone number if you plan to attend.
Extend solicitation close date
The solicitation close date is changed from 2 Jun 2023 to 7 Jun 2023.