This document is a Bid Schedule for the Douglas Canyon Allotment Boundary and Granite Spring Enclosure Fencing project under Solicitation Number 140L3924Q0102 issued by the Department of the Interior Bureau of Land Management Nevada Region.
The Base Bid Schedule includes the following line items: Mobilization and Preparatory Work, Installation of the Douglas Canyon Allotment Boundary Fence, Installation of the Granite Spring Enclosure Fence, and Removal of the North Preston Fence. Pricing is requested as lump sums for each line item.
The Additive Bid Item 1 is for setting 12 Granite Springs Enclosure Posts in Concrete, with pricing requested per each post.
The total for the Base Bid Schedule, Additive Bid Item 1 Schedule, and the combined total for Base Bid and Additive Bid are requested.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A06_Drawings.pdf | ||
| A06_Coordinates_and_Maps.docx | DOCX document | |
| Sol_140L3924Q0102.pdf | ||
| A04_SOW.docx | DOCX document | |
| B03_DBA_Wage_Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Douglas Canyon Allotment Boundary and Granite Spring Enclosure Fencing Bid Schedule
BASE BID SCHEDULE
| CLIN |
| Supplies or Services |
| Quantity and Unit |
| Unit Price |
| Amount |
| Mobilization and Preparatory Work |
| For the lump sum of |
| $ |
Installation of the Douglas Canyon Allotment Boundary Fence Furnish all labor, equipment and materials required to install the 4-Wire Fence in accordance with the Contract Documents.
| For the lump sum of |
| $ |
Installation of the Granite Spring Enclosure Fence Furnish all labor and equipment required to install the Enclosure Fence in accordance with the Contract Documents.
| For the lump sum of |
| $ |
Removal of the North Preston Fence Furnish all labor, equipment and materials required to remove the existing 4-Wire Fence and Panels in accordance with the Contract Documents.
| For the lump sum of |
| $ |
TOTAL FOR BASE BID SCHEDULE $_________________
ADDITIVE ITEM 1 BID SCHEDULE
| CLIN |
| Supplies or Services |
| Quantity and Unit |
| Unit Price |
| Amount |
| 5 |
| Set Granit Springs Enclosure Posts in Concrete |
Furnish all labor, equipment and materials required to set posts in concrete where soil conditions are unstable or rock is encountered, and the drive post embedment cannot be altered to maintain stability in accordance with Contract Documents. ASSUME 12 POSTS WILL NEED TO BE SET IN CONCRETE FOR BIDDING PURPOSES.
| 12 EA $ |
| $ |
TOTAL FOR ADDITIVE BID ITEM 1 $_________________
TOTAL FOR BASE BID SCHEDULE $_________________
TOTAL FOR ADDITIVE BID ITEM SCHEDULE $_________________
TOTAL FOR BASE BID AND ADDITIVE BID $_________________
Bid Schedule B - 2