B09_Attachment_9_Question_and_Answers_0002.docx

DOCX document 26 KB Posted

Attached to
CERC ETC Hall Painting Federal contract opportunity
Solicitation number
140G0124Q0197
Issued by
Department of the Interior US Geological Survey Office of Acquisitions and Grants

About this file

This document contains the Questions and Answers for Amendment 002 to Solicitation 140G0124Q0197 for the CERC ETC Hall Painting project. The key details are:

The USGS Columbia Environmental Research Center in Columbia, MO has a requirement to paint hallway walls, door jambs, and replace cove base in two buildings. The project must be completed within 30 days of the notice to proceed. The solicitation is a 100% Small Business set-aside with a NAICS code of 238320 and size standard of $19 million. The magnitude of construction is between $25,000 and $100,000. Rustoleum paint is acceptable, and contractors may work between 7:30am - 4:30pm, but not on Sundays. There is no incumbent contractor, and subcontracting is allowed. The Request for Quote will be issued on 6/21/2024 with quotes due by 7/8/2024.

View the file

Other files for this federal contract opportunity

Other files attached to CERC ETC Hall Painting, newest first.
File Type Posted
Sol_140G0124Q0197_Amd_0002.pdf PDF
B09_Attachment_8_Pictures_0001.docx DOCX document
Sol_140G0124Q0197_Amd_0001.pdf PDF
B08_Attachment_4_Payment_Bond_SF25A-16d.pdf PDF
B08_Attachment_6_Statement_and_Acknowledgement_of_Subcontractor_SF1413-13e.pdf PDF
B08_Attachment_7_Form_DI-137_Release_of_Claims.pdf PDF
B08_Attachment_1_SOW_ETC_Painting.docx DOCX document
B08_Attachment_3_WD_MO20240084_dtd_19_April_2024.pdf PDF
Sol_140G0124Q0197.pdf PDF
B08_Attachment_5_Payroll_WH-347.pdf PDF
B08_Attachment_2_ETC_Painting_Layout.png PNG image
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140G0124Q0197 Amendment 002 Q&A

1. Is Rustoleum paint and primer good enough for the door jams?

Rustoleum is fine.

2. May my team work after hours?

7:30 – 4:00

3. Is work on Sunday a possibility?

No

4. Is there a specific paint to be used?

No specific brand requirement

5. Could you please clarify whether contractors would be restricted to working during staffing hours or if access would be available after regular working hours as well? If extended access is permitted, we kindly request information on the specific hours during which contractors may access the site.

7:30 – 4:30

6. What is your insurance requirements if any?

Reference FAR 52.228-5 and 1452.228-70 (Page 28)

7. Who is the incumbent? If there is an Incumbent, Can you provide the current or previous contract number?

None

8. I regretfully missed the recent site visit are there meeting minutes, notes, or a site visit report that documents details such as wall colors?

None

9. How many contractors showed up for the site visit?

10. Would this opportunities be available for subcontracting or teaming arrangements?

Subcontract is allowed 52.222-11

11. Are there specific requirements or limitations regarding subcontracting?

Reference FAR 52.222-11 (https://www.acquisition.gov/)