Sol_140G0121Q0064_Amd_0002.pdf
PDF 92 KB Posted
- Attached to
- FACILITY CLEANUP & WASTE DISPOSAL Federal contract opportunity
- Solicitation number
- 140G0121Q0064
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140G0121Q0064_Amd_0001.pdf | ||
| Attachment 4 - Photos from USGS Ithaca_0001.zip | ZIP file | |
| Sol_140G0121Q0064.pdf | ||
| A2 - Floor Plan Overlay.pdf | ||
| A3 - DOL Wage Determination.pdf | ||
| A1 - Ithaca SOW - FINAL.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140G0121Q0064 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
GRB
RESTON VA 20192
12201 SUNRISE VALLEY DRIVE
205 NATIONAL CENTER
USGS OAG RESTON ACQUISITION BRANCH
03/03/20210002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
02/22/2021
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
FACILITY CLEANUP WITH SOLID & HAZARDOUS WASTE DISPOSAL - USGS ITHACA, NY
Legacy Doc #: UGS
The purpose of this amendment is to provide answers to a series of questions, as follows.
In addition, the deadline for submission has been extended to 3/10/2021, 1700 ET.
Question 1: The scope of work mentions that the removed furniture shall be placed in the roll off for disposal. Are we responsible for providing the roll off box and for arranging the disposal of the waste or would you provide that? Yes, the vendor is responsible for providing roll offs. The vendor is also responsible for the disposal of all waste including return of signed manifests, waste load-out receipts, or bills of lading.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Susan Ruggles
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140G0121Q0064/0002
Question 2: Does the scope of work only include the small lab, the mop room, the warehouse and the ware yard? No, there is the main laboratory, the battery charging room, the equipment test room, a mop area located in the heated warehouse, the cold warehouse, and the ware yard. Please refer to the facility emergency exit plan for the room names.
Question 3: For plumbing, do we need to completely remove all water lines that come out of a wall into those rooms (e.g. cutting and capping pipe down to inside the wall) or would a cap outside the wall would be sufficient? All plumbing and electrical shall be stubbed behind the wall or to the nearest junction box above the ceiling and capped off.
Question 4: Regarding electrical, do we need to remove any lights? No ceiling lights shall be removed. However, not identified in the SOW is a
6 ft. wall-mounted outlet strip in the main laboratory that shall be removed if the USGS does not remove it first.
Question 5: Do we need to re-paint any walls to a color similar to the adjacent wall? No, patch and prime the holes in the walls following Level
2, ASTM C 840.19a or the most current version.
Question 6: Do we need to permanently close (e.g.
fill with concrete) all floor drains in these rooms or just the one for the mop basin? Sealing the drains is to include a flexible plug inserted into the drain to prevent any additional contaminants from entering the drain once the sampling and cleaning with 10% bleach solution has been completed. No concrete is to be used which would render the floor drains unusable for the next tenant.
Question 7: Are we going to have onsite access to electricity (110 V) and water during the field work, including use of onsite restrooms for our personnel? Yes, the facility will be vacated of
USGS personnel, but all utilities shall remain
on. Contractor personnel shall be allowed the use of onsite restrooms.
Question 8: Do you have an inventory or
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
3 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140G0121Q0064/0002 approximate quantities of the hazardous materials
/ hazardous wastes that would need to be disposed off? The vendor is responsible for estimating the amount of hazardous waste that would be the result of cleaning and rinsing all equipment, p-traps, cabinets, walls, and floors. All rinsate is to be captured and sampled for hazardous constituents prior to disposal. If the samples reveal that the rinsate is below action levels, then the rinsate may be disposed of as non-hazardous waste.
Question 9: Is USGS going to remove all materials
(not furniture) observed in the pictures, (e.g.
warehouse materials, wood, etc.) Yes, all USGS owned property that is not identified in the SOW will be removed prior to the vendor starting work. Any materials left will be disposed of as trash.