Sol_140F0718R0001_Amd_0003.pdf
PDF 143 KB Posted
- Attached to
- AMT TIGLAX SHIPYARD 2018 Federal contract opportunity
- Solicitation number
- 140F0718R0001
About this file
140F0718R0001
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140F0718R0001_Amd_0004.pdf | ||
| Sol_140F0718R0001_Amd_0002.pdf | ||
| Sol_140F0718R0001_Amd_0001.pdf | ||
| Sol_140F0718R0001.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140F0718R0001 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
F07
ANCHORAGE AK 99503-6199
1011 E TUDOR ROAD
FWS, DIVISION OF CONTRACTING AND GE
11/22/20170003
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
11/14/2017
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
LIST OF CHANGES:
Add answers to questions. Bid due date remains unchanged.
All other terms and conditions remain unchanged.
Period of Performance: 02/01/2018 to 04/10/2018
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Anthony Kuntz
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Questions and Answers
Purchase Request: 40364023
Solicitation: F0718R0001
Amendment: 0003
1. What is the make and model of the engines?
Answer: Caterpillar 3412, 1200RPM, 425 hp each.
2. How many gallons of coolant should the contractor expect from each ME?
Answer: 110 gallons per engine.
3. What is the model and size keel coolers for ME?
Answer: Fernstrum DX1660d
4. What is the make and model of the generator engines?
Answer: John Deere 6076ATF
5. How many gallons of coolant should the contractor expect from each generator?
Answer: 55 gallons each
6. What is the model and size of the keel coolers for the generators?
Answer: Fernstrum D10156d
7. Is the contractor required to use the engine manufacturer’s recommended coolant?
Answer: No, the current coolant is Chevron ELC 50/50 mix
8. What style zincs are in the sea chest? Bolt on or welded?
Answer: Welded on 12”, 1 per chest.
9. Request drawings with sizes of shafting and prop components.
Answer: See attached
10. Request drawings with sizes of shafting and rudder components.
Answer: See attached
11. Request drawings with sizes of tail shaft components.
Answer: See attached
12. Request drawings with sizes of shafting components.
Answer: See attached
13. How many UT shots will the contractor take for the hull inspection?
Answer: 150 – 200 shots
14. What is the serial number of the aft crane?
Answer: Slattery model MCT 537, Serial # MCT-537-86-283
15. Request aft crane installation instructions.
Answer: N/A
16. Request technical publication for aft crane.
Answer: Will provide after contract award. Currently unavailable.
17. What size are the portlights?
Answer: 16#
18. What type of materials are the portlights?
Answer: Spigots ar 316SS (to be installed) Original spigots are mild steel and welded in
19. Are the spigots bolt on or welded?
Answer: Welded
20. What size and style is the cargo hatch?
Answer: Deleted from this solicitation
21. What size and style is the aft stores hatch?
Answer: 37” X 47” clear opening, 8” tall coaming, flush top.
22. What is the issue with the MSD?
Answer: Shuts down before completing cycle. No longer a requirement on this solicitation.
23. What brand and model is the MSD?
Answer: Evac Orca II-24
24. For the Dry-dock, is a “Travel-Lift” acceptable if the vessel is blocked according to the docking plan per specified vessel?
Answer: Not sure how a “travel Lift” works. A proposal that includes a “Travel Lift” will be considered subject to acceptance of this method.
25. Are each individual “price estimates” an estimate or actual bid?
Answer: The solicitation is amended to “BID”
26. What paint system is required in the chain locker?
Answer: Suggest it be the same as the holding tank.
27. Item #25 Aft Crane Remove/Reinstall. The first bullet point directs contractor to remove the crane pedestal. The second to last bulletin states to reinstall the crane on a new pedestal. Is the owner providing a new pedestal?
Answer: REPAIR AND REINSTALL ORIGINAL PEDESTAL UNLESS IT IS FOUND TO BE BEYOND
ECONOMICAL REPAIR.
28. Item #25 Aft Crane Remove/Reinstall. The second and third bullet points directs the contractor to make modifications to the crane boom. Have these changes been engineered and approved by a Professional Engineer as required by 29 CFR 1917.45(b)(3)? If so, please provide that document.
Answer: NO REPLY
29. Item #25 Aft Crane Remove/Reinstall. The specification is silent regarding testing. Please provide a test memo.
Answer: WE MAY MAKE SEPARATE ARRANGEMENTS FOR TESTING.
30. Is Item #25 Aft Crane Remove/Reinstall. there a technical manual available? If so, please provide.
Answer: N/A
31. Item #25 Aft Crane Remove/Reinstall. Please provide details regarding the two Nylatron sleeves: diameter, width, does it have bushings?
Answer: SHEAVES. NO DRAWINGS AVAILABLE.
32. Item #25 Aft Crane Remove/Reinstall. Is the existing tubing from the crane that connects to the piping to be replaced?
Answer: RETAIN ORIGINAL SS TUBING IF PRACTICAL, REPLACE WITH NEW IF NOT.
33. Topside Paint Items. The paint specifications are ambiguous on whether the final coat is a spot to the affected areas or an overall full coat. Please clarify.
Answer: Overall full coat.
34. Potable water tank coatings are not included with the “Paint Schedule”. Please provide Answer: ATTACH 2014 TIGLAX PAINT SCHEDULE. NOTE: SOME PRODUCTS IN 2014
SPECIFICATION PROBABLY WILL HAVE NEW EQUIVALENT PRODUCTS AVAILABLE FROM
INTERNATIONAL PAINT.
35. Will the crew be responsible for sanitizing the tank upon completion of repairs?
Answer: Yes
36. In item 11 AFT stores what are the 2 cubby spaces?
Answer: The cubby spaces in item 11 involve less than 20 square feet counting both.
R/V Tiglax paint schedule
Manufacturer: International Paint
Vessel exterior above bottom paint, bulwarks, mooring bitts, forward crane, windlass, trawl winches, upper stack trunk:
QHA027/QHA028 Interzinc Inorganic Zinc
FPJ034/FPA327 H.S. Light Gray Universal Epoxy
PCE992/PCA001 Interthane Ocean Blue Urethane
House and railings, aft crane, mast, lower stack trunk:
QHA027/QHA028 Interzinc Inorganic Zinc
FPJ034/FPA327 H.S. Light Gray Universal Epoxy
PCD053/PCA001 Interthane Stone Finish
Exterior Decks, deck hatches, cloverleafs, ladder treads, door steps:
QHA027/QHA028 Interzinc Inorganic Zinc
FPJ034/FPA327 H.S. Light Gray Universal Epoxy
FPJ034/FPA327 H.S. Dark Gray Universal Epoxy
Exposed steel in engineroom and aft stores above grating, bulkheads and overhead in foc’sle, fan rooms, fiddley, boiler enclosure:
QHA027/QHA028 Interzinc Inorganic Zinc
KTA501/KTA044 Intertuf Surface Tolerant Epoxy
PCB000/PCA001 Interthane Urethane White Finish
Tank tops, bilges below gratings, cargo hold:
KTA501/KTA044 Intertuf Surface Tolerant Epoxy
KTA501/KTA044 Intertuf Surface Tolerant Epoxy
Bottom paint: Compare to 2010 paint schedule
Interspeed 640
BRA 640 Red
BRA 642 Black
Y5584 Shark White for underwater draft marks
Holding Tank and chain locker:
International Interline 624
THA 626 Buff Primer
THA 625 Gray Topcoat
THA White Topcoat
Ballast Tanks:
Intergard 264 FPJ 034 Light gray
Potable Water Tanks:
Interline 925
THA 125/THA 127 White