B09_SA_1_Quality_Assurance_Surveillance_Plan_0001.pdf
PDF 145 KB Posted
- Attached to
- Network Connectivity Fiber Network Backbone Federal contract opportunity
- Solicitation number
- 140D0426Q0575
About this file
This is a Quality Assurance Surveillance Plan (QASP) for the Managed Optical Network Backbone Service contract with the National Cancer Institute (NCI). The QASP establishes the Government's approach for monitoring Contractor performance against requirements defined in the Performance Work Statement (PWS), focusing on network operations, availability, resilience, and security. The Contracting Officer retains overall contract administration authority, while the Contracting Officer's Representative monitors day-to-day performance, documents concerns, and coordinates issues with the CO. NCI technical and security personnel provide specialized input regarding network operations, security, testing, and incidents.
The QASP defines four primary performance areas with specific standards and surveillance methods: (1) Network Operations & Incident Response—requiring continuous 24×7×365 monitoring with 15-minute response times for Priority 1 incidents, monitored monthly and following significant incidents through incident/ticket records and root cause analysis; (2) Network Capacity, Resilience & Connectivity—maintaining required 10/40/100 Gbps backbone connectivity with path diversity and cloud interconnect redundancy, reviewed monthly with additional assessments following significant changes; (3) Security & Compliance—operating AWS Direct Connect via two diverse Northern Virginia sites and managing GCP Interconnect links with end-to-end FIPS-validated encryption and compliance with NIH/NIST policies, reviewed on an ongoing basis; and (4) Domestic Service Delivery & Data Protection—ensuring all service delivery, personnel, and data handling remain within the United States unless otherwise authorized by the CO, verified at contract start and when material changes occur. Per Amendment 1, network cutover must be completed before the end of January 2027, with detailed service startup acceptance testing criteria covering circuit provisioning, physical/optical health, end-to-end connectivity, bandwidth verification, resiliency/failover, stability, monitoring capabilities, and operational readiness documentation. The COR conducts performance evaluations every six months using the Six-Month Quality Assurance Monitoring Report, documents all discrepancies, and meets quarterly with the Contractor Project Manager, NCI Program Manager, and CO to discuss performance issues and corrective actions.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140D0426Q0575_Amd_0004.pdf | ||
| Sol_140D0426Q0575_Amd_0003.pdf | ||
| Sol_140D0426Q0575_Amd_0002.pdf | ||
| B09_SA_2_Q_A_0002.xlsx | XLSX spreadsheet | |
| Sol_140D0426Q0575_Amd_0001.pdf | ||
| B09_SA_1_Q_A_0001.xlsx | XLSX spreadsheet | |
| B09_SA_1_0001.pdf | ||
| B09_SA_1_Attachment_1_-_Contract_Certifications_and_Provisions_0001.pdf | ||
| B09_SA_1_Current_MPON_Topology_0001.pdf | ||
| B08_SOL_Attachment_4_-_Quality_Assurance_Surveillance_Plan.pdf | ||
| Sol_140D0426Q0575.pdf | ||
| B08_SOL_Fiber.pdf | ||
| B08_SOL_Attachment_3_-_Appendix_A.pdf | ||
| B08_SOL_Attachment_2_-_VPAT2_5Rev_508_February2025.pdf | ||
| B08_SOL_Attachment_1_-_Contract_Certifications_and_Provisions.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Quality Assurance Surveillance Plan (QASP)
Managed Optical Network Backbone Service
1. Purpose
This Quality Assurance Surveillance Plan (QASP) describes the Government's approach for monitoring Contractor performance of the Managed Optical Network Backbone Service.
The purpose of surveillance is to assess whether the Contractor is meeting the performance requirements and service outcomes established in the Performance Work Statement (PWS). Government surveillance will focus on critical aspects of performance affecting network operations, availability, resilience, and security.
The QASP does not relieve the Contractor of responsibility for managing, controlling, and ensuring the quality of its own performance.
2. Roles and Responsibilities
The Contracting Officer (CO) retains authority for administration of the contract and contractual remedies.
The Contracting Officer's Representative (COR), will monitor Contractor performance within the scope of delegated authority, document performance concerns, review performance information, and coordinate identified issues with the CO.
NCI technical and security personnel may provide technical input to the COR and CO regarding network operations, security, testing, incidents, and other areas within their assigned responsibilities.
The Contractor remains responsible for performing and managing the services required by the PWS and for identifying and correcting deficiencies in its performance.
3. Surveillance Approach
Government surveillance will focus on the Contractor's achievement of required service outcomes rather than day-to-day direction of Contractor personnel or methods of performance.
Surveillance may include review of operational information, incident records, network performance information, security information, test results, Contractor reports, and other information generated during contract performance.
The Government may increase surveillance when recurring deficiencies, significant incidents, security concerns, or other performance risks warrant additional monitoring.
4. Performance Surveillance
Performance Area Performance Standard Surveillance Method Frequency
Network Operations & Incident Response
Provide continuous 24×7×365 network monitoring and operations. Respond to Priority 1 incidents within 15 minutes and restore service or implement an approved workaround.
Review incident/ticket records, response timestamps, root cause analysis (RCA reports), and applicable operations reporting.
Monthly and following significant incidents
Network Capacity, Resilience & Connectivity
Maintain required 10/40/100 Gbps backbone connectivity, capacity, path diversity, cloud interconnect redundancy, and capacity necessary to support NCI mission operations.
Review network performance/capacity information and results of applicable network changes, validation testing, and failover exercises.
Monthly;
additional review following significant changes or testing
Security & Compliance
Operate and optimize Amazon Web Services (AWS) Direct Connect via two diverse Northern Virginia sites;
deploy/manage GCP Interconnect links from Rockville/Shady Grove and Frederick/ATRF to Northern Virginia.
All interconnect traffic and backbone links shall enforce end-to-end encryption with FIPS-validated ciphers; RMF artifacts and continuous monitoring will be maintained per NIH/NIST policies
Review applicable security information and coordinate technical assessment with the ISSO or other designated security personnel.
Ongoing, with periodic review based on applicable security requirements
Domestic Service Delivery & Data Protection
Required service delivery, personnel, remote-access endpoints, and Government data handling remain within the United States unless otherwise authorized in writing by the
CO.
Review relevant Contractor-provided staffing/location information, access information, and other records when necessary to verify compliance.
At contract start, when material changes occur, and when otherwise warranted
Added via Amendment 1: Service Start Date & Service Startup Acceptance Testing
Cutover to new network needs to be completed before the end of January 2027.
The incumbent’s only responsibilities are to maintain their services through the end of January
2027.
The following are the acceptance testing criteria and required performance validation procedures for new services.
Circuit Provisioning and Identification
• Circuit is delivered at the correct sites, interfaces, bandwidth, and handoff type.
• Provider circuit ID, demarcation points, and labeling match the approved design.
Physical / Optical Health
• Interfaces are up with no alarms or physical-layer errors.
• Optical transmit/receive levels are within the equipment/vendor-supported range and have adequate margin.
• No CRC, framing, input/output, or other interface errors are observed during testing.
End-to-End Connectivity
• Successful Layer 2 and/or Layer 3 connectivity is demonstrated between the NCI endpoints connecting to the MPON
• Required VLANs, routing adjacencies, and network paths are established and stable.
• MTU/jumbo-frame support is verified where applicable.
Bandwidth / Throughput
• Sustained bidirectional throughput meets the contracted committed bandwidth or agreed acceptance threshold.
• Testing should demonstrate that the circuit can carry the subscribed rate without unexpected packet loss.
Resiliency / Failover
• Where redundant paths or protection are included, failover and restoration operate as designed.
• A path or interface failure does not result in unacceptable outage duration, routing instability, or traffic loss beyond the agreed recovery objective.
Stability / Burn-In
• Circuit remains operational and error-free for an agreed observation period, such as 24 hours, with no unexplained flaps, alarms, or material performance degradation.
Monitoring and Management
• Circuit is visible in the provider and customer monitoring systems.
• Availability and performance metrics can be collected, and expected alarms are generated for a simulated or observed failure where practical.
Operational Readiness / Documentation
• Circuit inventory, diagrams, circuit IDs, demarcation information, escalation contacts, and provider support procedures are documented.
• Any outstanding exceptions are documented and formally accepted before production turnover.
5. Performance Documentation
The COR will maintain appropriate records of surveillance activities and significant Contractor performance issues in accordance with applicable contract administration procedures.
When a potential performance deficiency is identified, the Government will evaluate the circumstances and determine whether additional information, corrective action, or referral to the CO is appropriate.
Surveillance records may include Contractor reports, Government observations, incident reports, technical findings, correspondence, meeting records, and other information relevant to Contractor performance.
Evaluation Methods
The COR will conduct performance evaluations based upon the required performance levels set forth in the QASP and PWS.
Process of Quality Assurance Assessment
NCI will provide performance feedback. As soon as a discrepancy is identified with a deliverable associated with this contract, the COR and/or CO will notify the Contractor. A determination of the Contractor's performance will be executed every six months.
Performance Meetings
The Contractor Project Manager, NCI Program Manager, COR and CO will meet to discuss contract performance, resolve issues, discuss customer complaints, and provide positive interaction and feedback to all parties. The COR will provide a list of any unresolved deficiencies to the contractor's quality assurance representative to afford him/her the opportunity to show where the problem is already in the process of being worked. If evidence is shown where the contractor's quality program has already documented the deficiency and timely corrective action is working the problem, the COR will follow up with the contractor's quality control representative to ensure the deficiencies are remedied in a timely manner, in accordance with the PWS. All deficiencies associated with performance requirements listed in the Performance Requirements Summary, whether remedied by the contractor or not, will be included in the QASP Report regardless of who identified the deficiency. The contractor's Project Manager will provide a copy of the meeting minutes to all attendees within 5 workdays of the meeting.
6. Performance Deficiencies
When surveillance identifies performance that does not meet contractual requirements, the COR will document the observed condition and coordinate with the CO as appropriate.
The Contractor may be requested to identify the cause of the deficiency, describe corrective actions, and take appropriate action to prevent recurrence, consistent with the requirements and terms of the contract.
Only the Contracting Officer may exercise contractual authority or determine the applicability of contractual remedies.
7. QASP Maintenance
This QASP may be updated during the period of performance when changes to the PWS, performance risks, surveillance needs, or other contract administration considerations warrant revision.
Changes to the QASP will not alter the Contractor's contractual requirements or impose requirements that are not established by the contract.
8.0 Attachments
1 – Six-Month Assurance Monitoring Report
Attachment 1 - Six-Month Quality Assurance Monitoring Report
Survey Period: ______________________________________
COR: ____________________________________
Contractor: ____________________________________
CLIN/contract: ____________________________________
Performance Requirement: _________________________________________
The contractor has met all the requirements of the contract. These are summarized in this report and are supported by the COR periodic surveillance checklists and/or reports and customer feedback attached to this form.
Summary of discrepancies:
Actions taken to remedy discrepancies:
Other comments:
| Evaluation Methods |
| Process of Quality Assurance Assessment |
| Performance Meetings |