Questions_and_Answers_Version_2_0003.docx
DOCX document 15 KB Posted
- Attached to
- USCGC BERTHOLF (WSML-750) Federal contract opportunity
- Solicitation number
- 140D0422Q0624
About this file
This document contains questions and answers regarding solicitation 140D0422Q0624 for repair work on the USCGC BERTHOLF. The questions and answers provide clarification on work items, such as sea trials being conducted during the ship's scheduled shakedown cruise following dockside repairs. Shore power may be used if receptacles are available but temporary refrigerated stores should not rely on shore power. The extent of spot coating removal is defined in the work item. A government furnished automatic bus transfer switch will be supplied, and the contractor shall install in accordance with the drawing. Circuit breakers identified in the work items have an 8-12 week lead time and should be provided as government furnished property or procured separately by September 1, 2022.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B08_SOL-_Attachment_1-_Specifications_Updated_BERTHOLF_0003.pdf | ||
| Questions_and_Answers_-_BERTHOLF_0002.docx | DOCX document | |
| Amendment_0001_-_Bertolf_0001.docx | DOCX document | |
| Attachment_1_-_Specifications.pdf | ||
| Attachment_2_-_Pricing_Schedule.xls | XLS spreadsheet | |
| Attachment_4_-_CA20210018.pdf | ||
| Attachment_3_-_NDA.pdf | ||
| Combined_Synopsis__Solicitation_Bertolf.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions for BERTHOLF Solicitation
1. Regarding Work Item 7, paragraph 3.7: Would the required sea trial occur outside of the listed ship availability, or will it have to be performed before March 9, 2023?
0. Response: Sea trials will be conducted in conjunction with the cutter’s scheduled shakedown cruise following the dockside period of performance.
1. Regarding Work Item 10, paragraph 3.2.2: I would like to clarify that the contractor cannot utilize shore power and our own transformer/equipment to power the temporary refrigerated stores equipment?
1. Response: Shore power may be available for use if there are unused receptacles; however, the temporary refrigerated stores should not rely on shore power in the event that shore power is not available.
1. Regarding Work Item 14, paragraph 3.2: Can you please define the extent of spot coating there is to be removed?
2. Response: Extent of repair is defined in paragraph 1.1 of Work Item 14.
1. Work Item 11:
3. Paragraph 1.2 shows Automatic Bus Transfer switch (ABT) as GFP, paragraph 3.7 of work item states “contractor furnished ABT” . Please confirm the new ABT, piece # 3 on material list sheet 1 (identified as piece 2 on sheets 9 and 12) of drawing 750-WMSL-320-593 rev. B is GFP.
0. Response: The ABT identified in paragraph 1.2: Government Furnished Property will be supplied by the government. Paragraph 3.7 should read as follows:
0. ABT (3-57-1) Installation. Install Government Furnished ABT in accordance with Coast Guard Drawing 750-WMSL-320-593.
0. Please be advised that an updated revision has been issued for drawing 750-WMSL-320-593. Most recent version is REV C.
3. The circuit breakers identified in table 3 of work are all LLM with lead times of 8-12 weeks. Contractor recommends these be provided as GFP or as subject of separate RFQ with award date NLT September 1, 2022.
1. Response: the government will not be able to provide the identified circuit breakers. Material is to remain as contractor furnished equipment.
File details come from the government source that posted it. Updated .