This document is an amendment to a solicitation for the replacement of circuit breakers at the National Institute of Standards and Technology facility in Boulder, Colorado. The contractor shall provide all labor, equipment, and materials to remove and replace circuit breakers within Wing 2 and the Spine of Building 1, as outlined in the provided scopes of work and drawings. The amendment provides additional information on site visits, extends the quotation due date to May 14, 2021, and incorporates supplemental drawings.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 5. Panel EMG2058-2 Amend 0002.JPG | JPG image | |
| 2. Panel 2037-1 Amend 0002.JPG | JPG image | |
| 3. Panel 2037-2 Amend 0002.JPG | JPG image | |
| Amend 0002.pdf | ||
| 4. Panel EMG2058-1 Amend 0002.JPG | JPG image | |
| 6. Panel M2210A Amend 0002.JPG | JPG image | |
| 1. Busway Amend 0002.JPG | JPG image | |
| Wing2.Drawings Amend 0001 .pdf | ||
| Spine2.Drawings Amend 0001.pdf | ||
| 1. Drawing B1, W2.pdf | ||
| 1333ND21QNB190072.pdf | ||
| 2. Drawing B1, Spine 2.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
Attachment Page
PAGE 2 OF 8 1333ND21QNB1900720001
The purpose of this amendment is to incorporate the following changes:
A. Addendum to 52.212-1, Instructions to Offerors has been replaced in its entirety due to the following changes:
A second site visit is being offered at 10:00 AM MST on 06 May 2021. Potential contractors are to provide a list of individuals planning to attend the site visit to julie.morris@nist.gov no later than 10:00 AM MST, 04 May 2021, to ensure the names are added to the access list at the front gate. (Changes are designated in RED)
B. Incorporate two attachments – Drawings for Wing 2 and Drawings for Spine 2.
C. The Site Visit Information has been replaced in its entirety. (Changes are designated in RED)
D. The quotation due date, block 8 of the SF 1449, is hereby changed from April 26,2021 at 10:00 AM MT to May 14, 2021 at 10:00 AM MT.
E. No other changes occur as a result of this amendment.
Table of Contents
Addendum to 52.212-1 (Amend 0001)
Site Visit Information
PAGE 3 OF 8 1333ND21QNB1900720001
CLAUSES
Addendum to 52.212-1 (Amend 0001)
PAGE 4 OF 8 1333ND21QNB1900720001
ADDENDUM TO 52.212-1, INSTRUCTIONS TO OFFERORS – COMMERCIAL ITEMS
1. SPECIAL NOTICE TO CONTRACTORS
The Government intends to evaluate proposal and award a contract without discussions. The Government intends to make award to the offeror that presents the quote that provides the best value and most advantageous to the Government, in accordance with FAR Part 13 procedures.
Therefore, the Contractor’s initial proposal should contain the Contractor’s best terms from a technical and price standpoint. The Government reserves the right to conduct discussions if the CO (Contracting Officer) later determines them to be necessary.
1.1 Proposal shall clearly demonstrate that the Contractor understands both the general and specific technical requirements of the Scope of Work (SOW).
1.1.1 Failure to explain Contractor’s ability to meet all requirements may result in the Contractor's quotation not being considered. Clarity and completeness of quotations are of the utmost importance. Therefore, quotations must be written in a practical, clear and concise manner.
1.1.2 Proposals which merely restate the requirement or state that the requirement will be met without providing supporting rationale are not sufficient.
1.2 This requirement is being awarded utilizing the procedures established in FAR Part 13 procedures.
1.3 Contractor’s may be asked to clarify certain aspects of their proposal to resolve minor or clerical errors and will not constitute discussions.
1.4 Request for Quote (RFQ) pricing for base contract line item numbers (CLIN) 0001 and 0003.
1.4.1 The Contractor agrees to hold the prices in its quotation firm for 120 calendar days from the date specified for receipt of quotations, unless another time period is specified in an addendum to the solicitation. Any quotation providing less that the specified acceptance period will be considered non-responsive, will not be evaluated, and will be ineligible for award.
1.5 Pre-Quote Conference and Site Visit.
1.5.1 As indicated in clause 1352.270-71, Pre-bid/Pre-proposal Conference and Site Visit the Government is conducting a site visit/pre-proposal conference during which potential contractors may obtain a better understanding of the work required. Contractors are strongly urged to attend to fully inform themselves about the location and conditions under which the work is to be performed. A second site visit is being offered at 10:00 AM MST on 06 May 2021. Potential contractors are to provide a list of individuals planning to attend the site visit to julie.morris@nist.gov no later than 10:00 AM MST, 04 May 2021, to ensure the names are added to the access list at the front gate.
1.5.2 NIST Boulder is a secure facility. Potential contractors are to provide a list of individuals planning to attend the site visit to noah.branscom@nist.gov and julie.morris@nist.gov no later than 12:00 PM Mountain, 29 March 2021, to ensure the names are added to the access list at the front gate. If this information is not sent as required, personnel will be denied entry onto the campus. NOTE: Attendees must be US Citizens. Allow 45 minutes for processing.
1.5.3 Contractors are cautioned that, notwithstanding any remarks, clarifications, or responses given at the site visit, all terms and conditions of this solicitation remain unchanged unless they are changed by amendment (See 2.3). Additionally, it is the responsibility of each Contractor, prior to submission of its quotation, to seek clarification of any ambiguity created by amendment of the solicitation.
2. INQUIRIES AND QUESTIONS
2.1 The CO is the only approved point of contact for this acquisition. Address any questions or concerns you may have to the CO via e-mail to: julie.morris@nist.gov.
PAGE 5 OF 8 1333ND21QNB1900720001
2.2 All requests for clarification, inquiries, and questions concerning this solicitation shall be submitted in writing via e-mail to: julie.morris@nist.gov by 12:00 PM MST, 11 May
2.3 All questions and responses to questions shall be provided, in writing, without identification of the questioner. Questions and responses will be published to Contract Opportunities (formerly FBO) in the form of an amendment to the solicitation. Even if provided in other form, only the question responses included in the amendment(s) to the solicitation will govern performance of the contract.
3. SOLICITATION RESPONSE REQUIREMENTS
3.1 The Government will evaluate quotations based on comparative analysis between all quotes received in consideration of the factors and requirements outlined in this RFQ.
3.1.1 Any quotation that does not provide sufficient detail to meet the stated solicitation requirements or performance objectives will be considered ineligible for award unless the deficiency is corrected through discussions (See paragraph 1).
3.2 QUOTATION REQUIREMENTS
3.2.1 Quotations are expected to conform to solicitation provisions and be prepared in accordance with this section. To aid in evaluation, the quotation shall be clearly and concisely written, neatly presented, indexed (cross-indexed as appropriate), and assembled as required by this instruction to offerors. All pages of each part shall be appropriately numbered and identified with the name of the Contractor, the date of the quotation, and the solicitation number.
3.2.2 Format. Text shall be single-spaced, and able to fit on 8½” x 11”, with a minimum one-inch margin all around (should the Government need to print). Each page with content shall count as a single page. Pages shall be numbered consecutively. Text shall be no smaller than 11 font. Bolding, underlining, and italics may be used to identify topic demarcations or points of emphasis. Graphic presentations, including tables, while not subject to the same font size and spacing requirements, shall have spacing and text that is easily readable.
3.2.3 Restriction of Disclosure/Proprietary Information. If the Contractor wishes to restrict the disclosure or use of its quotation, use the legend permitted by FAR 52.215- 1(e). Individual subcontractor/vendor proprietary information may be submitted via separate binders. The information contained in these binders must be referenced (by binder title, page, and section number as appropriate) within the main quotation where the information would have been included if it were not subcontractor/vendor proprietary. The information in these separate binders is subject to all other requirements of the RFQ, will be included in the page count for the appropriate volume, and must be well-marked to clearly indicate any special handling instructions.
3.2.4 The Contractor shall submit one (1) electronic version compatible with the Microsoft Office 2016 Software Suite and/or Adobe Acrobat (PDF), by email.
3.2.5 Submission Address. Quotes are due by email to julie.morris@nist.gov.
FACSIMILE QUOTATIONS ARE NOT AUTHORIZED
3.2.6 Submission Due Dates. Quotations must be received prior the date and time in block 8 of the SF 1449. Quotations received after this date and time are considered late and may not be accepted.
4. Factor A – Price Submittal Requirements
4.1 Factor A – Price, shall comply with the instructions in paragraph 3, above, and include the following documents (in the order listed):
4.1.1 The offeror shall complete and submit the Standard Form 1449, Solicitation/Contract/Order for Commercial Items: Complete Blocks 17a, 17b, 19, 20, 21, 22, 23, 24, 26, 30a, 30b, and 30c only. An official having the authority to contractually bind
PAGE 6 OF 8 1333ND21QNB1900720001
the Offeror’s company must sign the SF 1449 in accordance with the procedures prescribed in
FAR 4.102.
4.1.2 Acknowledge all solicitation amendments using one of the methods set forth in Block 11 of Standard Form 30, the form on which any amendment will be issued.
4.1.3 Complete all required representations and certifications
4.1.4 Completed Schedule B, of the SF 1449.
5. Factor B – Technical Details
5.1 Technical details shall comply with the instructions in paragraph 3, above and is limited as stated in the factors below.
5.2 Exceptions, Deviations, and/or Assumptions. This document shall identify and explain any exceptions or deviations taken to any part of the SOW or conditional assumptions made with respect to the technical requirements of the solicitation. Contractors should note that taking exceptions to the Government's requirements may indicate an unwillingness or inability to perform the contract, and the quotation may be evaluated as such.
5.3 Technical Details shall include the following:
5.3.1 The offeror shall submit technical details sufficient for the Government evaluation team to have a thorough understanding of materials to be used, means and methods of accomplishing the requirements of the SOW, and solutions to addressing the work required.
6. Factor C – Past Performance
6.1 The past performance evaluation will assess the relative risks associated with an offeror's likelihood of success in fulfilling the solicitation's requirements as indicated by the offeror's record of past performance. In this context, "offeror" refers to the prime contractor. Present and past performance shall be evaluated as a measure of the Government's confidence in the offeror's ability to successfully perform based on previous and current contract efforts.
6.2 The offeror shall submit up to three references, which shall be for recent work performed and shall be relevant to the complexity, size, and scope of this solicitation’s requirement.
References provide shall be limited to three singled sided pages per reference.
6.3 Offerors shall reference the addendum to clause 52.212-2 for further details.
7. Limitation of Future Contracting
N/A
8. Confidential Information
The Freedom of Information Act (FOIA) and its amendments have resulted in an increasing number of requests from outside the Government for copies of contractor qualifications and quotations submitted to Federal agencies. If a contractor's submissions contain information that they believe should be withheld from such requesters under FOIA on the grounds that they contain "trade secrets and commercial or financial information" [5 USC§552(b) (4)], the contractor should mark its submissions in the following manner "Some parts of this document, as identified on individual pages, are considered by the submitter to be privileged or confidential trade secrets or commercial or financial information not subject to mandatory disclosure under the Freedom of Information Act.”
Site Visit Information
PAGE 7 OF 8 1333ND21QNB1900720001
NIST/Boulder Site Visit for
Solicitation 1333ND21QNB190072, B1 Wg2 & Spine Circuit Breaker Replacement – NIST Boulder, CO
Notice to Contractors Regarding the Status of the Intended Site Visit
Site Visit Date: May 6, 2021 at 10:00 AM MST
Participants will meet at:
National Institute of Standards and Technologies Building 1 – Main Lobby Entrance 325 Broadway Boulder, CO 80305
Participating attendees will first arrive at the NIST Visitor Center for temporary day badging and security inspection of vehicle prior to entering site. To obtain a temporary day badge and be allowed on site, each attendee must present a picture identification to Security at the Visitor Center. The name as identified on the picture identification must match the name of the individual’s registration (see below). Please allow time to get through Security prior to start of site visit.
Please proceed directly to and park in the NIST, Building 1 South Parking Lot, once passing through the Security Entrance Gate.
Participating attendees should wear comfortable walking shoes as the site visit will be entirely on foot covering a fair distance of uphill and downhill terrain via sidewalk between buildings.
NIST COVID-19 social distancing requirements include the following for all site visit attendees:
1. Please do not attend if you are sick (self-screen for COVID-19 symptoms such as elevated temperature, fever, difficulty breathing, being lite headed, cough, sore throat, body aches, etc.).
2. Please do not attend if you have had exposure (Close Contact*) to a person with confirmed or suspected COVID-19.
3. Maintain social/physical distancing:
a. Stay at least 6 feet (about two arms’ length) from other people
b. No gathering in groups
4. Wear a face covering at all times while in buildings or grouped with safe distancing.**
5. Please avoid, as much as practical, touching of surfaces during site visit.
* Closer than 6 feet or direct contact with secretions with a person with COVID-19 is also close contact. Includes being in the same hospital, emergency room, classroom, vehicle or similar situation.
** NIST will not supply face coverings and anyone without a face covering will NOT be allowed to participate.
6. Each contractor/firm attending shall have no more than two (2) representatives. Names that have not been confirmed will not be allowed to participate in the site visit.
7. The site visit is expected not to exceed 90 minutes in length.
PAGE 8 OF 8 1333ND21QNB1900720001
1.2
C:\PERFORM\FORMS\S30.FRP
Forms Management
C:PERFORMFORMSS30.FRP
Acrobat PDFWriter 2.01 for Windows D:19971010095222 D:19990614133004 Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER
3. EFFECTIVE DATE
4. REQUISITION/PURCHASE REQUISITION NUMBER
5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6)
CODE
STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended.
is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY
CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer) Previous edition unusable
| Descript: |
| Descript1: See Attachment Page. |
| AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT: |
| IDCode: |
| pdfpage1: 1 |
| Pages: 8 |
| DocNo: 1333ND21QNB1900720001 |
| EffDate: APR 22, 2021 |
| ReqNo: NB194000-21-00356 |
| ProjNo: |
| IssuedByCode: 000014 |
| IssuedBy: NATIONAL INST OF STDS AND TECHNOLOGY |
325 BROADWAY
BOULDER CO 80305-3328
| AdminByCode: |
| AdminBy: See Block 6 |
| ContractorCode: |
| FacCode: |
| SolNo: 1333ND21QNB190072 |
| SolDate: MAR 26, 2021 |
| AwdNo: |
| AwdDate: |
| NoCopies: 1 |
| Amended: Yes |
| OffrExt: Yes |
| OffrNoEx: Off |
| ApprData: See Schedule |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).: |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| SignName: |
| SignTitl: |
| ContDate: |
| ContrOfficerInfo: |
| CODate: |
| Contractor Info: |
| ContractorPOC: |
| Contractor: |
| ModAmount: |
| 15B. CONTRACTOR/OFFEROR: |
| signature: |
| AwdChg: Off |
| SolChg: Yes |
| Header: |
| Footer1: |
File details come from the government source that posted it. Updated .