Attachment_V_Specification_Deliverables.pdf
PDF 67 KB Posted
- Attached to
- Request for Quotation (RFQ) NOAA Ship Rainier Drydock Federal contract opportunity
- Solicitation number
- 1305M219QNMAN0213
About this file
Attachment V Specification Deliverables
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_6.pdf | ||
| Amendment_6.pdf | ||
| Attachment_IV_-_Price_Schedule_RA_REV_B.pdf | ||
| Amendment_5.pdf | ||
| Attachment_I_Specification_Revision_C.pdf | ||
| AC_Images.zip | ZIP file | |
| Amendment_4.pdf | ||
| Attachment_IV_-_Price_Schedule_RA_REV_A.pdf | ||
| RFQ_1350M219QNMAN0213.pdf | ||
| Attachment_I_Specification_Revision_B.pdf | ||
| RA-120-001.pdf | ||
| Amendment_3.pdf | ||
| Attachment_I_Specification_REVISION_A.pdf | ||
| Amendment_2_References.zip | ZIP file | |
| Amendment_2.pdf | ||
| Amendment_1_Work_Item_13111.pdf | ||
| Attachment_III_Past_Performance_Questionnaire.pdf | ||
| Attachment_IV_-_Price_Schedule_RA.xlsx | XLSX spreadsheet | |
| Attachment_II_Past_Performance_Information_Form.pdf | ||
| Attachment_1_Specification.pdf | ||
| RA_DD_REF.zip | ZIP file | |
| RFQ_1350M219QNMAN0213.pdf | ||
| SYNOPSIS__RAINIER_DD.pdf |
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Item Description Quantity Due Date Deliver To
Gen Req Contractor Schedule 1 First 3 days of PoP PE
Gen Req Weekly progress report 1 Weekly PE
Gen Req Weekly Look Ahead 1 Weekly PE
Gen Req Hot Work Permits 1 Daily As Needed OOD
10910 Estimate of ABS Services Fee 1 First Week of PoP PE
10910 ABS Schedule 1 First Week of PoP PE
10910 ABS Load Line Renewal Cert 1 By close of PoP PE
10911 Service Records of Safety and Fire Equipment 2 By close of PoP PE and CO
10912 Pressure Vessel Hydro‐test reports 1 By close of PoP PE
12330 Main Engine Repair Report 1 By close of PoP PE
13110 Diesel Generator Repair Report 1 By close of PoP PE
15050 Hydrostatic test results of repaired piping 1 By close of PoP PE
15051 Survey of Non‐Metallic Expansion Joints 1 By close of PoP PE
15120 Cleaning Report 1 By close of PoP PE
15140 Compressor Inspection Report 1 By close of PoP PE
15170 Boiler Servicing and repair report 1 By close of PoP PE
15330 Grey Water Tank Inspection Report 1 By close of PoP PE
15680 Motor Service Report 1 By close of PoP PE
15720 Certificate of Inspection 1 By close of PoP PE
15830 Report of Services for Davits, and Windlass 1 By close of PoP PE and Chief B
16120 NDT reports 1 By close of PoP PE
16510 Installation Report 1 By close of PoP PE
21230 Weld Inspetion Report 1 By close of PoP PE
21230 Structural test Report 1 By close of PoP PE
21230 ABS Inspection Report (if needed) 1 By close of PoP PE
21230 Certificates and Documentation of equipment 1 By close of PoP PE
21230 Work Completed Report 1 By close of PoP PE
54010 Work Completed Report 1 By close of PoP PE
66440 Weld Inspetion Report 1 By close of PoP PE
66440 Structural test Report 1 By close of PoP PE
66440 ABS Inspection Report (if needed) 1 By close of PoP PE
66440 Certificates and Documentation of equipment 1 By close of PoP PE
66440 Work Completed Report 1 By close of PoP PE