About this file

Amendment 1 site visit Questions and answers

View the file

Other files for this federal contract opportunity

Other files attached to FY19 HUD Mechanical Site Prep, newest first.
File Type Posted
Amendment_7.pdf PDF
Amendment_6.pdf PDF
Amendment_5.pdf PDF
Amendment_4.pdf PDF
Amendment_3.pdf PDF
Amendment_2_Revision_1_LOP.pdf PDF
Attachment_3_FY19_HUD_Fuels_Reduction_Site_Prep_Data_Table_2_LOP.xlsx XLSX spreadsheet
Attachmnet_1_Maps.pdf PDF
Attachment_5_NDR_Service_Contract_Addendum_no_CA_Wages.docx DOCX document
Attachment_2_FY19_HUD_Fuels_Reduction_Site_Prep_Data_Table_1.xlsx XLSX spreadsheet
FY19HUD_Fuels_Reduction_and_site_prep_Sol.pdf PDF
Attachment_6_Wage_Determination.docx DOCX document
Attachment_4_2012_FINALPAL_Fire_Plan_080212.doc DOC document
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1

1. CONTRACT ID CODE

I

PA

E OF PAGES

I 4

2. AMENDMENT/MODIFICATION NO. 4. REQUISITION/PURCHASE REQ. NO.

5. PROJECT NO. (If applicable)

3. EFFECTIVE DATE

12/03/2018

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE I USDA Forest Service Central CA Acquisition Service Area 631 Coyote St.

Nevada City, CA 95959

8. NAME AND ADDRESS OF CONTRACTOR (No., street. county, State and ZIP Code) �

9A. AMENDMENT OF SOLICITATION

NO.

129JGP19Q0009

98. DATED (SEE ITEM 11)

11/28/2018

10A. MODIFICATION OF CONTRACT/ORDER NO.

□ 108. DATED (SEE ITEM 13)

CODE !FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

D The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers D is extended, D is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning _____ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor D is not, Dis required to sign this document and return ____ _ copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Amendment 1 is to post site visit sign in sheet and questions and answers. See Attached.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 1 0A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

158. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

NSN 7540-01-152-8070

Previous edition unusable

15C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

OLAINE MARTINEZ

168. UNITED STATES OF AMERICA 16C. DATE SIGNED

(Signature of Contracting Officer) 12/03/2018

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

HUD Fuels Reduction and Site Prep Site Visit Question and Answers 11/20/2018

Q1. Can we masticate slopes over 45/5 slope.

A1. No, no machine work is permitted over 45%. There are areas designated as non-work areas.

Q2. Is Hand work required over 45% slope?

A2. Some areas are specific as Hand work only. A Map will be provided and some areas over 45% are non-work areas or have specific treatment requirements. Some areas Hand work may be more suitable.

It’s how you approach the work.

Q3. Cottonwood Rd closes in the winter what other routes are available?

A3. Highway 120 to Cherry Lake road. Cherry Lake road has maintained 3N01S while other roads in this project area are not. No other route from Groveland.

Q4. Which wages are applicable Federal or State?

A4. Federal wages are applicable and the Wage Determination is included in the Solicitation.

Q5. What is the Ground pressure limit?

A5. 6 or 8 psi see Solicitation specifics.

Q6. Are there any ground presser restrictions on Dozers?

A6. No.

Q7. What is the High water marker for low ground pressure?

A7. 15ft. A diagram for equipment usage can be provided.

Q8. Will be able to get around draws with equipment?

A8. Yes, roads will go all the way around or terrain make it possible to access the majority of these areas.

Q9. Can they use loppers?

A9. Yes, but must be piled.

Q10. How many oaks stay in addition to leave trees?

A10. 6 per acre

Q11. Are all units flagged?

A11. Yes.

Q12. How many Arch site are there and are they flagged?

A12. Several and they are flagged.

Q13. When will the solicitation be out?

A13. Next week, Wednesday or Thursday. It will be posted NLT 11/29/2018.

Q14. How will time be calculated when more than one item is awarded?

A14. If more than one Item is awarded to one offeror than Time will run concurrently.

HUD Fuels Reduction and Site Prep Site Visit Question and Answers 11/20/2018

Q15. Is there a priority of units?

A15. Yes, several units will be sprayed next spring and once they are identified we will provide an amendment.

Amendment 1
FY19 HUD Fuels Reduction and Site prep Site visit sign in sheet
Atachment Amendment 1. Site Visit Q&A